环氧树脂的新应用消除了持续的套管压力,而无需昂贵的井下干预-印度尼西亚东加里曼丹的案例历史

Yogi Adi Guna, Michael A. Frank, Novianto Rochman, Thomas Herdian Abi Putra, M. Irvan, Alfatah Fitriansyah, Ibnu Kurniawan
{"title":"环氧树脂的新应用消除了持续的套管压力,而无需昂贵的井下干预-印度尼西亚东加里曼丹的案例历史","authors":"Yogi Adi Guna, Michael A. Frank, Novianto Rochman, Thomas Herdian Abi Putra, M. Irvan, Alfatah Fitriansyah, Ibnu Kurniawan","doi":"10.2118/207419-ms","DOIUrl":null,"url":null,"abstract":"\n An operator recorded 1100 psi of sustained casing pressure between a 9-5/8\" casing and a 3.5\" production tubing annulus seven days after the cementing operation was completed for the 3.5\" production tubing. A production logging run was performed, and results indicated gas was flowing from a zone 86 feet below the 9-5/8\" casing shoe. As per the operator's standard, such a situation suggests subsequent well completion operations cannot be processed and must be remediated. The most common solution for such situations is to perforate and squeeze to ensure zonal isolation in the zone from which the gas is flowing. Due to the slim tubing size this operation can be difficult, and there exists a high risk of leaving set cement inside the 3.5\" tubing. Furthermore, drilling would require extensive time with a coil tubing unit and in the worst case could lead to the loss of the well.\n To provide a dependable barrier for long term well integrity, a novel approach consisting of epoxy resin was discussed. A highly ductile, solids-free resin was designed and tailored to seal off communication from the gas source to surface. The void space in the annulus was estimated to be less than 5 bbl. An equipment package was prepared to mix and pump the resin into the annulus. Resin was pumped through the wellhead casing valve using a hesitation squeeze technique with the maximum surface pressure limited to 3000 psi. Once all resin was pumped, the casing valve was closed to allow enough time for the resin to build compressive strength.\n The job was planned to be performed in multiple stages consisting of smaller volumes. The job was completed in two stages, and the annular pressure was reduced. On the first job, 1 bbl of resin was mixed and injected into the annulus. The pressure build up was decreased from 550 psi per day to 27 psi per day. To lower the annular pressure further, a second resin job was performed using 0.35 bbl resin volume, which further reduced the annular pressure build up to 25 psi within 3 days. No further stages were performed as this was considered a safe working pressure for the well owner. After 2 months no annular pressure was observed.\n The application of this tailored resin helped to improve the wells integrity under these circumstances in this high-pressure gas well. Epoxy resin with its solid-free nature and deep penetration capabilities helped to seal off a very tight flow path. This application of pumping resin through the wellhead to overcome annular gas pressure can be an option when the flow path is strictly limited, or downhole well intervention is very difficult and risky.","PeriodicalId":11069,"journal":{"name":"Day 2 Tue, November 16, 2021","volume":"16 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-12-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Novel Application of Epoxy Resin to Eliminate Sustained Casing Pressure Without Costly Downhole Well Intervention - Case History from East Kalimantan, Indonesia\",\"authors\":\"Yogi Adi Guna, Michael A. Frank, Novianto Rochman, Thomas Herdian Abi Putra, M. Irvan, Alfatah Fitriansyah, Ibnu Kurniawan\",\"doi\":\"10.2118/207419-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n An operator recorded 1100 psi of sustained casing pressure between a 9-5/8\\\" casing and a 3.5\\\" production tubing annulus seven days after the cementing operation was completed for the 3.5\\\" production tubing. A production logging run was performed, and results indicated gas was flowing from a zone 86 feet below the 9-5/8\\\" casing shoe. As per the operator's standard, such a situation suggests subsequent well completion operations cannot be processed and must be remediated. The most common solution for such situations is to perforate and squeeze to ensure zonal isolation in the zone from which the gas is flowing. Due to the slim tubing size this operation can be difficult, and there exists a high risk of leaving set cement inside the 3.5\\\" tubing. Furthermore, drilling would require extensive time with a coil tubing unit and in the worst case could lead to the loss of the well.\\n To provide a dependable barrier for long term well integrity, a novel approach consisting of epoxy resin was discussed. A highly ductile, solids-free resin was designed and tailored to seal off communication from the gas source to surface. The void space in the annulus was estimated to be less than 5 bbl. An equipment package was prepared to mix and pump the resin into the annulus. Resin was pumped through the wellhead casing valve using a hesitation squeeze technique with the maximum surface pressure limited to 3000 psi. Once all resin was pumped, the casing valve was closed to allow enough time for the resin to build compressive strength.\\n The job was planned to be performed in multiple stages consisting of smaller volumes. The job was completed in two stages, and the annular pressure was reduced. On the first job, 1 bbl of resin was mixed and injected into the annulus. The pressure build up was decreased from 550 psi per day to 27 psi per day. To lower the annular pressure further, a second resin job was performed using 0.35 bbl resin volume, which further reduced the annular pressure build up to 25 psi within 3 days. No further stages were performed as this was considered a safe working pressure for the well owner. After 2 months no annular pressure was observed.\\n The application of this tailored resin helped to improve the wells integrity under these circumstances in this high-pressure gas well. Epoxy resin with its solid-free nature and deep penetration capabilities helped to seal off a very tight flow path. This application of pumping resin through the wellhead to overcome annular gas pressure can be an option when the flow path is strictly limited, or downhole well intervention is very difficult and risky.\",\"PeriodicalId\":11069,\"journal\":{\"name\":\"Day 2 Tue, November 16, 2021\",\"volume\":\"16 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-12-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 2 Tue, November 16, 2021\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/207419-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, November 16, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/207419-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

作业公司在完成3.5”生产油管固井作业7天后,在9-5/8”套管和3.5”生产油管环空之间记录了1100 psi的持续套管压力。进行了一次生产测井,结果表明天然气从9-5/8”套管鞋下方86英尺处流出。根据作业公司的标准,这种情况表明后续完井作业无法进行,必须进行补救。在这种情况下,最常见的解决方案是射孔和挤压,以确保在气体流出的区域进行层间隔离。由于油管尺寸较细,该作业很困难,并且存在将固井水泥留在3.5英寸油管内的高风险。此外,使用盘管装置钻井将需要大量时间,在最坏的情况下可能导致油井漏失。为了提供一个可靠的屏障,以保证井的长期完整性,研究人员讨论了一种由环氧树脂组成的新方法。设计并定制了一种高延展性、无固体的树脂,以密封气源与地面之间的通信。环空的空隙空间估计小于5bbl。准备了一个设备包,将树脂混合并泵入环空。树脂通过井口套管阀泵入,使用延迟挤压技术,最大地面压力限制在3000psi。泵送完所有树脂后,关闭套管阀,为树脂建立抗压强度留出足够的时间。该作业计划分多个阶段进行,其中包括较小的体积。该作业分两个阶段完成,环空压力降低。在第一次作业中,将1桶树脂混合并注入环空。累积压力从每天550 psi降至27 psi。为了进一步降低环空压力,使用0.35桶的树脂进行了第二次树脂作业,在3天内将环空压力进一步降低到25 psi。由于井主认为这是一个安全的工作压力,因此没有进行进一步的压裂。2个月后未观察到环空压力。在这种高压气井中,这种定制树脂的应用有助于提高井的完整性。环氧树脂具有无固体特性和深度渗透能力,有助于密封非常紧密的流道。当流动路径受到严格限制,或者井下干预非常困难和危险时,通过井口泵入树脂来克服环空气体压力是一种选择。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Novel Application of Epoxy Resin to Eliminate Sustained Casing Pressure Without Costly Downhole Well Intervention - Case History from East Kalimantan, Indonesia
An operator recorded 1100 psi of sustained casing pressure between a 9-5/8" casing and a 3.5" production tubing annulus seven days after the cementing operation was completed for the 3.5" production tubing. A production logging run was performed, and results indicated gas was flowing from a zone 86 feet below the 9-5/8" casing shoe. As per the operator's standard, such a situation suggests subsequent well completion operations cannot be processed and must be remediated. The most common solution for such situations is to perforate and squeeze to ensure zonal isolation in the zone from which the gas is flowing. Due to the slim tubing size this operation can be difficult, and there exists a high risk of leaving set cement inside the 3.5" tubing. Furthermore, drilling would require extensive time with a coil tubing unit and in the worst case could lead to the loss of the well. To provide a dependable barrier for long term well integrity, a novel approach consisting of epoxy resin was discussed. A highly ductile, solids-free resin was designed and tailored to seal off communication from the gas source to surface. The void space in the annulus was estimated to be less than 5 bbl. An equipment package was prepared to mix and pump the resin into the annulus. Resin was pumped through the wellhead casing valve using a hesitation squeeze technique with the maximum surface pressure limited to 3000 psi. Once all resin was pumped, the casing valve was closed to allow enough time for the resin to build compressive strength. The job was planned to be performed in multiple stages consisting of smaller volumes. The job was completed in two stages, and the annular pressure was reduced. On the first job, 1 bbl of resin was mixed and injected into the annulus. The pressure build up was decreased from 550 psi per day to 27 psi per day. To lower the annular pressure further, a second resin job was performed using 0.35 bbl resin volume, which further reduced the annular pressure build up to 25 psi within 3 days. No further stages were performed as this was considered a safe working pressure for the well owner. After 2 months no annular pressure was observed. The application of this tailored resin helped to improve the wells integrity under these circumstances in this high-pressure gas well. Epoxy resin with its solid-free nature and deep penetration capabilities helped to seal off a very tight flow path. This application of pumping resin through the wellhead to overcome annular gas pressure can be an option when the flow path is strictly limited, or downhole well intervention is very difficult and risky.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Three-Dimensional Visualization of Oil Displacement by Foam in Porous Media Maximizing Condensate Recovery With Proven Cost Simulation for a Giant UAE Field: Base Study to Estimate Productivity between Horizontal and Vertical Wells Rationalization of Flares at Terminal Island A Geoengineering Approach to Maximum Reservoir Contact Wells Design: Case Study in a Carbonate Reservoir Under Water and Miscible Gas Injection Maximizing Brine Recovery After the Displacement of Reservoir Drill-in Fluids to Reduce Well Cost Via New, Alternate Technology In a Reservoir Offshore Abu Dhabi
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1