软土地基深基坑中桩的三维有限元分析

N. Le, T. Nguyen
{"title":"软土地基深基坑中桩的三维有限元分析","authors":"N. Le, T. Nguyen","doi":"10.17577/IJERTV10IS010007","DOIUrl":null,"url":null,"abstract":"A large excavation was carried out in the thick soft soil layer to construct the pile cap foundation and the basement floor for the 15 stories-building in Ho Chi Minh City. The soil profile consists of a 25-meter-thick of very soft clay with SPT value of zero laid on an 8.5-meter-thick of soft clay with SPT value of 3 and laid on a 13.9-meter-thick of medium dense fine sand with SPT value of 17. The excavation was supported by the system of 6-meter-depth SP IV steel sheet piles with the tied-back rods on the top of the wall to the 6m H steel piles installed behind the wall. Before the excavation, the spun PHC pile with 600mm diameter and 100mm thick was installed to support the superstructure. As excavation to 3.8 meter depth, four piles with the distance 4.55m, 7.15m, 10.65m and 13.25m from the wall had the top pile displacement 63.5cm, 38.86cm, 19.5cm and 11.4cm, respectively. Furthermore, all these piles were determined to be cracked by using the PIT test. Base on the collected data, back analysis was carried out by using PLAXIS 3D Foundation with Hardening-Soil soil model to determine the response of these piles during excavation. In the results, the maximum bending moment of these piles was over its ultimate value, thereby, we can analyze the reason piles group in this building was failure and use the parameters in PLAXIS for expanding the analysis to other situations. Keywords—Failure, steel sheet piles, excavation, soft clay, bending moment. I. INTRODUTION In Ho Chi Minh City, a large number of high buildings with the basement floors were constructed to supply the living houses and working offices. Ho Chi Minh City lies on a complex stratum with the soft clay layer somewhere is thicker than 30 meters. Therefore, a lot of problems were happened during the excavation process to build the basement floors for the high building. Some works have taken place the failure of inside existing piles due to the deep excavation. In 2007, all the installed piles to support the superstructure of Thao Dien building in District 2 Ho Chi Minh City were tilted during the basement excavation. A 13 stories building in District 7 has the PHC pile top move 0.6 meter when basement construction was carried out [9]. In similarly, the silo cement in Hiep Phuoc industry zone used the spun PHC pile with pile length from 33 to 35 meter through the thick soft soil layer had about 80 percent of piles under the silo were tilted in the same direction. A mumber of 2664 piles among of 7474 piles of the water treatment station in Binh Chanh District had the top horizontal displacement in the excavation process [9]. In 2011, a 15-story building in district 8 built on the ground with 25m deep of soft clay, the piles near the steel sheet pile wall was tilt and beak out during the pit foundation excavation. The maximum top pile horizontal displacement was up to 0.6 meter. Analysing the failure of pile inside deep foundation pit in soft soil is a considered problem. The deep excavation in soft soil is very complicated; the lateral displacement of soft soil produces the passive pressure on pile. It causes the pile movement and bending moment greater than capacity moment of the pile; therefore, the piles are damage. According to Kok S.T (2009), there are three common methods for researching about the effect of excavation to the nearby pile foundation: The Finite element, the centrifuge test and the field test [1,4]. Poulos & Chen (1996) did analysis by using of the finite-element method analyze the response of piles due to unsupported excavation induced lateral soil movement in clay [2]. This method was also used in back – analyzing to the responses of pile subjected to horizontal soil movements in clay, and many researchers use Finite element method for their own studies. Finite element method is easy to progress, and the result less fluctuate and appropriate with reality. However, the result from this analysis is affected by many factors that are required experience and understanding of not only geotechnical issue but also solutions and software. Recent efforts in centrifuge modeling of passive piles adjacent to unbraced excavation was done by Leung, Ong. Initially, Leung (2000) presented the results of centrifuge tests of an adjacent single pile behind an unstrutted stable and failed wall of a deep excavation in dense sand. The research also investigates the influence of head piles fixity for behind the stable wall, the pile head deflection and maximum bending moment for the free-headed pile decreases exponentially with increasing distance from the excavation. Subsequently, Leung (2003) extended the centrifuge test to pile groups, incorporating the effects of interaction factors between the piles with different head fixities. Following Leung (2000), further investigation was done for single pile behind stable wall (Ong, 2006) and instable wall (Leung, 2006) in clay [5,6,7]. Finno et al (1991) and Goh et al (2003) executed the field test. According to Goh (2003), used movement measurer for soil horizontal displacement in actual field and examine the behavior of an existing pile due to nearby excavation of a International Journal of Engineering Research & Technology (IJERT) ISSN: 2278-0181 http://www.ijert.org IJERTV10IS010007 (This work is licensed under a Creative Commons Attribution 4.0 International License.) Published by : www.ijert.org Vol. 10 Issue 01, January-2021","PeriodicalId":13986,"journal":{"name":"International Journal of Engineering Research and","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2021-01-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"3D Finite Element Analysis of Pile Behavior Inside the Deep Excavation in Soft Soil\",\"authors\":\"N. Le, T. Nguyen\",\"doi\":\"10.17577/IJERTV10IS010007\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A large excavation was carried out in the thick soft soil layer to construct the pile cap foundation and the basement floor for the 15 stories-building in Ho Chi Minh City. The soil profile consists of a 25-meter-thick of very soft clay with SPT value of zero laid on an 8.5-meter-thick of soft clay with SPT value of 3 and laid on a 13.9-meter-thick of medium dense fine sand with SPT value of 17. The excavation was supported by the system of 6-meter-depth SP IV steel sheet piles with the tied-back rods on the top of the wall to the 6m H steel piles installed behind the wall. Before the excavation, the spun PHC pile with 600mm diameter and 100mm thick was installed to support the superstructure. As excavation to 3.8 meter depth, four piles with the distance 4.55m, 7.15m, 10.65m and 13.25m from the wall had the top pile displacement 63.5cm, 38.86cm, 19.5cm and 11.4cm, respectively. Furthermore, all these piles were determined to be cracked by using the PIT test. Base on the collected data, back analysis was carried out by using PLAXIS 3D Foundation with Hardening-Soil soil model to determine the response of these piles during excavation. In the results, the maximum bending moment of these piles was over its ultimate value, thereby, we can analyze the reason piles group in this building was failure and use the parameters in PLAXIS for expanding the analysis to other situations. Keywords—Failure, steel sheet piles, excavation, soft clay, bending moment. I. INTRODUTION In Ho Chi Minh City, a large number of high buildings with the basement floors were constructed to supply the living houses and working offices. Ho Chi Minh City lies on a complex stratum with the soft clay layer somewhere is thicker than 30 meters. Therefore, a lot of problems were happened during the excavation process to build the basement floors for the high building. Some works have taken place the failure of inside existing piles due to the deep excavation. In 2007, all the installed piles to support the superstructure of Thao Dien building in District 2 Ho Chi Minh City were tilted during the basement excavation. A 13 stories building in District 7 has the PHC pile top move 0.6 meter when basement construction was carried out [9]. In similarly, the silo cement in Hiep Phuoc industry zone used the spun PHC pile with pile length from 33 to 35 meter through the thick soft soil layer had about 80 percent of piles under the silo were tilted in the same direction. A mumber of 2664 piles among of 7474 piles of the water treatment station in Binh Chanh District had the top horizontal displacement in the excavation process [9]. In 2011, a 15-story building in district 8 built on the ground with 25m deep of soft clay, the piles near the steel sheet pile wall was tilt and beak out during the pit foundation excavation. The maximum top pile horizontal displacement was up to 0.6 meter. Analysing the failure of pile inside deep foundation pit in soft soil is a considered problem. The deep excavation in soft soil is very complicated; the lateral displacement of soft soil produces the passive pressure on pile. It causes the pile movement and bending moment greater than capacity moment of the pile; therefore, the piles are damage. According to Kok S.T (2009), there are three common methods for researching about the effect of excavation to the nearby pile foundation: The Finite element, the centrifuge test and the field test [1,4]. Poulos & Chen (1996) did analysis by using of the finite-element method analyze the response of piles due to unsupported excavation induced lateral soil movement in clay [2]. This method was also used in back – analyzing to the responses of pile subjected to horizontal soil movements in clay, and many researchers use Finite element method for their own studies. Finite element method is easy to progress, and the result less fluctuate and appropriate with reality. However, the result from this analysis is affected by many factors that are required experience and understanding of not only geotechnical issue but also solutions and software. Recent efforts in centrifuge modeling of passive piles adjacent to unbraced excavation was done by Leung, Ong. Initially, Leung (2000) presented the results of centrifuge tests of an adjacent single pile behind an unstrutted stable and failed wall of a deep excavation in dense sand. The research also investigates the influence of head piles fixity for behind the stable wall, the pile head deflection and maximum bending moment for the free-headed pile decreases exponentially with increasing distance from the excavation. Subsequently, Leung (2003) extended the centrifuge test to pile groups, incorporating the effects of interaction factors between the piles with different head fixities. Following Leung (2000), further investigation was done for single pile behind stable wall (Ong, 2006) and instable wall (Leung, 2006) in clay [5,6,7]. Finno et al (1991) and Goh et al (2003) executed the field test. According to Goh (2003), used movement measurer for soil horizontal displacement in actual field and examine the behavior of an existing pile due to nearby excavation of a International Journal of Engineering Research & Technology (IJERT) ISSN: 2278-0181 http://www.ijert.org IJERTV10IS010007 (This work is licensed under a Creative Commons Attribution 4.0 International License.) Published by : www.ijert.org Vol. 10 Issue 01, January-2021\",\"PeriodicalId\":13986,\"journal\":{\"name\":\"International Journal of Engineering Research and\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-01-06\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Engineering Research and\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.17577/IJERTV10IS010007\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Engineering Research and","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.17577/IJERTV10IS010007","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

胡志明市某15层住宅楼的桩承台基础和地下室在厚软土层中进行了大开挖。土壤剖面由厚度为25 m、SPT值为0的极软粘土铺在厚度为8.5 m、SPT值为3的软粘土上,铺在厚度为13.9 m、SPT值为17的中密细砂上组成。基坑支护采用深6米的SP IV型钢板桩体系,墙顶杆与墙后安装的6m H型钢板桩相扣。开挖前,安装直径600mm、厚度100mm的旋压PHC桩支撑上部结构。开挖至3.8 m深度时,距墙4.55m、7.15m、10.65m和13.25m的4根桩顶位移分别为63.5cm、38.86cm、19.5cm和11.4cm。并通过基坑试验确定了这些桩均为开裂桩。在此基础上,利用PLAXIS三维地基与硬化-土壤模型进行反分析,确定了这些桩在开挖过程中的响应。结果表明,这些桩的最大弯矩均超过其极限值,因此,我们可以分析该建筑群桩破坏的原因,并利用PLAXIS中的参数将分析扩展到其他情况。关键词:破坏,钢板桩,开挖,软土,弯矩。在胡志明市,建造了大量带有地下室的高层建筑,以供应生活住宅和工作办公室。胡志明市位于一个复杂的地层上,某些地方的软粘土层厚度超过30米。因此,在高层建筑地下室的开挖过程中出现了很多问题。由于深基坑开挖,部分工程发生了内部既有桩的破坏。2007年,胡志明市2区Thao Dien大厦上部结构已安装的桩基在地下室开挖过程中全部发生倾斜。7区某13层建筑进行地下室施工时,PHC桩顶移动0.6米[9]。相类似的是,合富工业区的筒仓水泥采用旋压PHC桩,桩长33 ~ 35米,穿过厚软土层,筒仓下约80%的桩向同一方向倾斜。平昌区水处理站7474根桩中有2664根桩在开挖过程中发生顶部水平位移[9]。2011年,8区某15层建筑建在25m深软土地基上,基坑开挖时,钢板桩墙附近的桩出现倾斜、尖出现象。顶桩最大水平位移达0.6 m。分析软土地基深基坑内桩的破坏是一个值得考虑的问题。软土地基的深基坑开挖十分复杂;软土的侧向位移对桩产生被动压力。使桩的运动弯矩大于桩的承载力弯矩;因此,桩被破坏。Kok S.T(2009)研究基坑开挖对附近桩基影响的常用方法有三种:有限元法、离心试验法和现场试验法[1,4]。Poulos & Chen(1996)利用有限元方法分析了无支深开挖引起的粘土中土体横向移动对桩的响应[2]。这种方法也被用于对粘土中水平土体运动作用下的桩的响应进行反分析,许多研究者使用有限元方法进行自己的研究。有限元法易于进步,计算结果波动小,符合实际。然而,这种分析的结果受到许多因素的影响,这些因素不仅需要对岩土工程问题的经验和理解,还需要解决方案和软件。Leung, Ong最近对无支撑开挖附近被动桩的离心模拟进行了研究。最初,Leung(2000)提出了在致密砂中深基坑的非支撑稳定和破坏墙后面相邻单桩的离心试验结果。研究了顶桩在稳定墙后的固结影响,自由顶桩的桩顶挠度和最大弯矩随距基坑距离的增加呈指数递减。随后,Leung(2003)将离心试验扩展到群桩,纳入了不同顶固桩之间相互作用因素的影响。继Leung(2000)之后,对粘土中稳定墙(Ong, 2006)和不稳定墙(Leung, 2006)后的单桩进行了进一步的研究[5,6,7]。Finno et al .(1991)和Goh et al .(2003)进行了实地试验。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
3D Finite Element Analysis of Pile Behavior Inside the Deep Excavation in Soft Soil
A large excavation was carried out in the thick soft soil layer to construct the pile cap foundation and the basement floor for the 15 stories-building in Ho Chi Minh City. The soil profile consists of a 25-meter-thick of very soft clay with SPT value of zero laid on an 8.5-meter-thick of soft clay with SPT value of 3 and laid on a 13.9-meter-thick of medium dense fine sand with SPT value of 17. The excavation was supported by the system of 6-meter-depth SP IV steel sheet piles with the tied-back rods on the top of the wall to the 6m H steel piles installed behind the wall. Before the excavation, the spun PHC pile with 600mm diameter and 100mm thick was installed to support the superstructure. As excavation to 3.8 meter depth, four piles with the distance 4.55m, 7.15m, 10.65m and 13.25m from the wall had the top pile displacement 63.5cm, 38.86cm, 19.5cm and 11.4cm, respectively. Furthermore, all these piles were determined to be cracked by using the PIT test. Base on the collected data, back analysis was carried out by using PLAXIS 3D Foundation with Hardening-Soil soil model to determine the response of these piles during excavation. In the results, the maximum bending moment of these piles was over its ultimate value, thereby, we can analyze the reason piles group in this building was failure and use the parameters in PLAXIS for expanding the analysis to other situations. Keywords—Failure, steel sheet piles, excavation, soft clay, bending moment. I. INTRODUTION In Ho Chi Minh City, a large number of high buildings with the basement floors were constructed to supply the living houses and working offices. Ho Chi Minh City lies on a complex stratum with the soft clay layer somewhere is thicker than 30 meters. Therefore, a lot of problems were happened during the excavation process to build the basement floors for the high building. Some works have taken place the failure of inside existing piles due to the deep excavation. In 2007, all the installed piles to support the superstructure of Thao Dien building in District 2 Ho Chi Minh City were tilted during the basement excavation. A 13 stories building in District 7 has the PHC pile top move 0.6 meter when basement construction was carried out [9]. In similarly, the silo cement in Hiep Phuoc industry zone used the spun PHC pile with pile length from 33 to 35 meter through the thick soft soil layer had about 80 percent of piles under the silo were tilted in the same direction. A mumber of 2664 piles among of 7474 piles of the water treatment station in Binh Chanh District had the top horizontal displacement in the excavation process [9]. In 2011, a 15-story building in district 8 built on the ground with 25m deep of soft clay, the piles near the steel sheet pile wall was tilt and beak out during the pit foundation excavation. The maximum top pile horizontal displacement was up to 0.6 meter. Analysing the failure of pile inside deep foundation pit in soft soil is a considered problem. The deep excavation in soft soil is very complicated; the lateral displacement of soft soil produces the passive pressure on pile. It causes the pile movement and bending moment greater than capacity moment of the pile; therefore, the piles are damage. According to Kok S.T (2009), there are three common methods for researching about the effect of excavation to the nearby pile foundation: The Finite element, the centrifuge test and the field test [1,4]. Poulos & Chen (1996) did analysis by using of the finite-element method analyze the response of piles due to unsupported excavation induced lateral soil movement in clay [2]. This method was also used in back – analyzing to the responses of pile subjected to horizontal soil movements in clay, and many researchers use Finite element method for their own studies. Finite element method is easy to progress, and the result less fluctuate and appropriate with reality. However, the result from this analysis is affected by many factors that are required experience and understanding of not only geotechnical issue but also solutions and software. Recent efforts in centrifuge modeling of passive piles adjacent to unbraced excavation was done by Leung, Ong. Initially, Leung (2000) presented the results of centrifuge tests of an adjacent single pile behind an unstrutted stable and failed wall of a deep excavation in dense sand. The research also investigates the influence of head piles fixity for behind the stable wall, the pile head deflection and maximum bending moment for the free-headed pile decreases exponentially with increasing distance from the excavation. Subsequently, Leung (2003) extended the centrifuge test to pile groups, incorporating the effects of interaction factors between the piles with different head fixities. Following Leung (2000), further investigation was done for single pile behind stable wall (Ong, 2006) and instable wall (Leung, 2006) in clay [5,6,7]. Finno et al (1991) and Goh et al (2003) executed the field test. According to Goh (2003), used movement measurer for soil horizontal displacement in actual field and examine the behavior of an existing pile due to nearby excavation of a International Journal of Engineering Research & Technology (IJERT) ISSN: 2278-0181 http://www.ijert.org IJERTV10IS010007 (This work is licensed under a Creative Commons Attribution 4.0 International License.) Published by : www.ijert.org Vol. 10 Issue 01, January-2021
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Uçak Çakışma Saptama Ve Çözümleme Problemi için Karma Tam Sayılı Doğrusal Programlama Modeli Yaklaşımı Investigation of Thermal Conductivity Properties of Polymer Based Composites Containing Waste Materials Design and Prototyping of Sensor-based Anti-Theft Security System using Microcontroller Used Vehicles Survival Rates and Their Impacts on Urban Air Quality of Addis Ababa, Ethiopia Political Commitment, Institutional Capacity and Urban Transport Governance Reform in Addis Ababa, Ethiopia
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1