安装海底网络和海洋观测站:CSnet海上通信骨干(OCB)

A. Clark, D. Kocak
{"title":"安装海底网络和海洋观测站:CSnet海上通信骨干(OCB)","authors":"A. Clark, D. Kocak","doi":"10.23919/OCEANS.2011.6107087","DOIUrl":null,"url":null,"abstract":"This paper discusses the steps key to successful installation of complex seafloor communication, power and sensor networks. Emphasis on a systems engineering approach to design, development and deployment requiring the coordination of a diverse team of optical fiber specialists, marine cable engineers, technicians, deck hands, riggers, ROV operators, ship's crew and officers is essential to safely and efficiently install these systems at thousands of meters of ocean depth. This is illustrated through the detailed description of a system recently installed in the Eastern Mediterranean Sea. CSnet's Offshore Communication Backbone (OCB) will initially serve as the Tsunami Warning and Early Response system of Cyprus (TWERC). Nascent hydrocarbon exploration has also recently begun in this region. As this activity increases, leading to drilling and production, this OCB will similarly be expanded. In a phased approach, the TWERC will be extended to also service this offshore energy enterprise, supporting environmental and well monitoring sensors and providing two way broadband communications and power from seafloor to shore. The initial installation was completed in two preliminary phases. The first phase utilized two vessels (a cable ship and a DP II support ship), each equipped with remotely operated vehicles (ROVs), to lay a total of 255 km of cable, five seafloor nodes, an anchor interface and a seawater ground anode. Both multi-beam and visual (ROV) pre-deployment seafloor surveys of each node (junction box) site was performed. Installing each node, connectivity was maintained (power and communications) with the deployment vessel enabling its functionality to be continuously monitored while being lowered through the water column and after its touchdown on the seafloor. The second phase of this OCB installation deployed a moored buoy that provides both power and communication to the TWERC, in advance of any eventual shore-ended cable and power station and the attendant permitting required for such an installation. This phase required three surface vessels and an ROV to deploy the anchor, the buoy itself and nearly 2.4 km of riser cable with its associated buoyancy modules. Upon their installation, buoy and mooring were “plugged” into the anchor and anchor interface via ROV wet mate connectors (WMCs). Prior to final connection of the TWERC to the surface buoy, final system testing was performed through the riser cable aboard the deployment vessel. With successful operation established, the buoy and riser were connected to the seafloor network and complete end-to-end verification testing was performed over satellite to the Network Operations Command Center (NOCC) on shore. The system is now in operation. The successful installation of the TWERC OCB resulted from strictly adhering to a program management plan, installation storyboard, deployment plan, detailed event table, quality management plan, desktop study (DTS), subsea survey and permits, route position list, load method of procedure, contingency plans and schedule, among other exacting preparation. A step-by-step event table incorporating contingencies for unplanned events during deployment should result in significant cost and schedule savings in addition to the most important aspect, assurance of the safety of personnel and equipment. This was the case in the recent TWERC OCB installation, despite the complexities of coordinating the numerous surface vessels and subsea vehicles required to successfully install the system. This paper also outlines some of the best practices gathered from this and prior cabled seafloor installations, which may assist in future subsea installations. As Benjamin Franklin is purported to have said, “By failing to prepare, you are preparing to fail.”","PeriodicalId":19442,"journal":{"name":"OCEANS'11 MTS/IEEE KONA","volume":"2 1","pages":"1-9"},"PeriodicalIF":0.0000,"publicationDate":"2011-12-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":"{\"title\":\"Installing undersea networks and ocean observatories: The CSnet Offshore Communications Backbone (OCB)\",\"authors\":\"A. Clark, D. Kocak\",\"doi\":\"10.23919/OCEANS.2011.6107087\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper discusses the steps key to successful installation of complex seafloor communication, power and sensor networks. Emphasis on a systems engineering approach to design, development and deployment requiring the coordination of a diverse team of optical fiber specialists, marine cable engineers, technicians, deck hands, riggers, ROV operators, ship's crew and officers is essential to safely and efficiently install these systems at thousands of meters of ocean depth. This is illustrated through the detailed description of a system recently installed in the Eastern Mediterranean Sea. CSnet's Offshore Communication Backbone (OCB) will initially serve as the Tsunami Warning and Early Response system of Cyprus (TWERC). Nascent hydrocarbon exploration has also recently begun in this region. As this activity increases, leading to drilling and production, this OCB will similarly be expanded. In a phased approach, the TWERC will be extended to also service this offshore energy enterprise, supporting environmental and well monitoring sensors and providing two way broadband communications and power from seafloor to shore. The initial installation was completed in two preliminary phases. The first phase utilized two vessels (a cable ship and a DP II support ship), each equipped with remotely operated vehicles (ROVs), to lay a total of 255 km of cable, five seafloor nodes, an anchor interface and a seawater ground anode. Both multi-beam and visual (ROV) pre-deployment seafloor surveys of each node (junction box) site was performed. Installing each node, connectivity was maintained (power and communications) with the deployment vessel enabling its functionality to be continuously monitored while being lowered through the water column and after its touchdown on the seafloor. The second phase of this OCB installation deployed a moored buoy that provides both power and communication to the TWERC, in advance of any eventual shore-ended cable and power station and the attendant permitting required for such an installation. This phase required three surface vessels and an ROV to deploy the anchor, the buoy itself and nearly 2.4 km of riser cable with its associated buoyancy modules. Upon their installation, buoy and mooring were “plugged” into the anchor and anchor interface via ROV wet mate connectors (WMCs). Prior to final connection of the TWERC to the surface buoy, final system testing was performed through the riser cable aboard the deployment vessel. With successful operation established, the buoy and riser were connected to the seafloor network and complete end-to-end verification testing was performed over satellite to the Network Operations Command Center (NOCC) on shore. The system is now in operation. The successful installation of the TWERC OCB resulted from strictly adhering to a program management plan, installation storyboard, deployment plan, detailed event table, quality management plan, desktop study (DTS), subsea survey and permits, route position list, load method of procedure, contingency plans and schedule, among other exacting preparation. A step-by-step event table incorporating contingencies for unplanned events during deployment should result in significant cost and schedule savings in addition to the most important aspect, assurance of the safety of personnel and equipment. This was the case in the recent TWERC OCB installation, despite the complexities of coordinating the numerous surface vessels and subsea vehicles required to successfully install the system. This paper also outlines some of the best practices gathered from this and prior cabled seafloor installations, which may assist in future subsea installations. As Benjamin Franklin is purported to have said, “By failing to prepare, you are preparing to fail.”\",\"PeriodicalId\":19442,\"journal\":{\"name\":\"OCEANS'11 MTS/IEEE KONA\",\"volume\":\"2 1\",\"pages\":\"1-9\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2011-12-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"7\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"OCEANS'11 MTS/IEEE KONA\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.23919/OCEANS.2011.6107087\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"OCEANS'11 MTS/IEEE KONA","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.23919/OCEANS.2011.6107087","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 7

摘要

本文讨论了成功安装复杂海底通信、电力和传感器网络的关键步骤。强调系统工程方法的设计、开发和部署,需要光纤专家、海洋电缆工程师、技术人员、甲板人员、吊具工、ROV操作员、船员和官员等不同团队的协调,这对于在数千米的海洋深处安全有效地安装这些系统至关重要。最近在东地中海安装的一个系统的详细说明说明了这一点。CSnet的离岸通信主干网(OCB)最初将作为塞浦路斯海啸预警和早期响应系统(TWERC)。该地区最近也开始了初步的油气勘探。随着钻井和生产活动的增加,OCB也将随之扩大。在分阶段的方法中,TWERC将扩展到为海上能源企业提供服务,支持环境和井监测传感器,并提供从海底到岸上的双向宽带通信和电力。初始安装分两个初步阶段完成。第一阶段使用了两艘船(一艘电缆船和一艘DP II支持船),每艘船都配备了远程操作车辆(rov),共铺设255公里的电缆,五个海底节点,一个锚定界面和一个海水地面阳极。对每个节点(接线盒)进行了多波束和视觉(ROV)部署前海底调查。安装每个节点后,与部署船保持连接(电力和通信),使其在通过水柱下降以及在海底着陆后能够持续监测其功能。OCB安装的第二阶段部署了一个系泊浮标,在任何最终的岸端电缆和发电站以及此类安装所需的相关许可之前,该浮标为TWERC提供电力和通信。这一阶段需要三艘水面船只和一个ROV来部署锚、浮筒本身以及近2.4公里的立管电缆及其相关浮力模块。安装完成后,浮标和系泊通过ROV湿配合连接器(wmc)“插入”锚和锚接口。在将TWERC与水面浮筒最终连接之前,通过部署船上的立管电缆进行了最终系统测试。作业成功后,浮筒和立管连接到海底网络,并通过卫星向岸上的网络操作指挥中心(NOCC)进行完整的端到端验证测试。该系统现已投入使用。TWERC OCB的成功安装得益于严格遵守项目管理计划、安装故事板、部署计划、详细事件表、质量管理计划、桌面研究(DTS)、海底调查和许可、路线位置列表、加载方法、应急计划和时间表,以及其他严格的准备工作。除了最重要的方面,即确保人员和设备的安全之外,在部署期间包含意外事件应急情况的分步事件表应能大大节省成本和时间表。在最近的TWERC OCB安装中就是这种情况,尽管要成功安装该系统需要协调大量的水面船只和水下车辆,这很复杂。本文还概述了从这次和以前的海底电缆安装中收集到的一些最佳实践,这些实践可能有助于未来的海底电缆安装。正如本杰明·富兰克林所说:“不做好准备,就是在为失败做准备。”
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Installing undersea networks and ocean observatories: The CSnet Offshore Communications Backbone (OCB)
This paper discusses the steps key to successful installation of complex seafloor communication, power and sensor networks. Emphasis on a systems engineering approach to design, development and deployment requiring the coordination of a diverse team of optical fiber specialists, marine cable engineers, technicians, deck hands, riggers, ROV operators, ship's crew and officers is essential to safely and efficiently install these systems at thousands of meters of ocean depth. This is illustrated through the detailed description of a system recently installed in the Eastern Mediterranean Sea. CSnet's Offshore Communication Backbone (OCB) will initially serve as the Tsunami Warning and Early Response system of Cyprus (TWERC). Nascent hydrocarbon exploration has also recently begun in this region. As this activity increases, leading to drilling and production, this OCB will similarly be expanded. In a phased approach, the TWERC will be extended to also service this offshore energy enterprise, supporting environmental and well monitoring sensors and providing two way broadband communications and power from seafloor to shore. The initial installation was completed in two preliminary phases. The first phase utilized two vessels (a cable ship and a DP II support ship), each equipped with remotely operated vehicles (ROVs), to lay a total of 255 km of cable, five seafloor nodes, an anchor interface and a seawater ground anode. Both multi-beam and visual (ROV) pre-deployment seafloor surveys of each node (junction box) site was performed. Installing each node, connectivity was maintained (power and communications) with the deployment vessel enabling its functionality to be continuously monitored while being lowered through the water column and after its touchdown on the seafloor. The second phase of this OCB installation deployed a moored buoy that provides both power and communication to the TWERC, in advance of any eventual shore-ended cable and power station and the attendant permitting required for such an installation. This phase required three surface vessels and an ROV to deploy the anchor, the buoy itself and nearly 2.4 km of riser cable with its associated buoyancy modules. Upon their installation, buoy and mooring were “plugged” into the anchor and anchor interface via ROV wet mate connectors (WMCs). Prior to final connection of the TWERC to the surface buoy, final system testing was performed through the riser cable aboard the deployment vessel. With successful operation established, the buoy and riser were connected to the seafloor network and complete end-to-end verification testing was performed over satellite to the Network Operations Command Center (NOCC) on shore. The system is now in operation. The successful installation of the TWERC OCB resulted from strictly adhering to a program management plan, installation storyboard, deployment plan, detailed event table, quality management plan, desktop study (DTS), subsea survey and permits, route position list, load method of procedure, contingency plans and schedule, among other exacting preparation. A step-by-step event table incorporating contingencies for unplanned events during deployment should result in significant cost and schedule savings in addition to the most important aspect, assurance of the safety of personnel and equipment. This was the case in the recent TWERC OCB installation, despite the complexities of coordinating the numerous surface vessels and subsea vehicles required to successfully install the system. This paper also outlines some of the best practices gathered from this and prior cabled seafloor installations, which may assist in future subsea installations. As Benjamin Franklin is purported to have said, “By failing to prepare, you are preparing to fail.”
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Modelling flint acoustics for detection of submerged Stone Age sites Automatic detection of the number of raypaths Development of the pacific tsunami warning system National Data Buoy Center transition of the Tropical Atmosphere Ocean (TAO) program Navigating and mapping with the SPARUS AUV in a natural and unstructured underwater environment
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1