利用MPD钻透多层油藏,通过预测和优化所需的MW来最小化压差效应

F. Gutierrez, M. Saleh, Ayoub Hadj-moussa, M. A. Alzaabi, I. Abdelkarim, Mario R. Oviedo Vargas, Olla Kadoura, Mohamed Ahmed Osman, Bilal Iftikhar Choudhry, Javier Ernesto Torres Premoli
{"title":"利用MPD钻透多层油藏,通过预测和优化所需的MW来最小化压差效应","authors":"F. Gutierrez, M. Saleh, Ayoub Hadj-moussa, M. A. Alzaabi, I. Abdelkarim, Mario R. Oviedo Vargas, Olla Kadoura, Mohamed Ahmed Osman, Bilal Iftikhar Choudhry, Javier Ernesto Torres Premoli","doi":"10.2118/197755-ms","DOIUrl":null,"url":null,"abstract":"\n In a specific reservoir of an offshore field Abu Dhabi, several layers of the reservoir are producing subject to pressure depletion while other layers are partially or over pressurized due to water injection. Drilling through multi-layered reservoirs involves several challenges: faults and fractures, differentially stuck pipe and even total loss/kick scenarios due to pressure difference between the different layers. For reentry wells isolating the producing from injection layers is not possible due to the existing well schematic restrictions, completion requirements and target hole drainage size and location.\n MPD was proposed to utilize a mud weight that minimizes the differential pressure between the producing and injecting layers within reservoir which mitigates the drilling problems related to high differential pressure. The game plan was to start drilling the depleted zone with the lowest possible mud weight and to enter the injecting zone (higher pressure) with this mud weight to calculate the exact pressure of the formation using the early kick detection and automatic control features of the fully automated MPD system, in this way reducing the amount of overbalance in the depleted layer if feasible.\n Two wells were drilling using this method successfully. On both wells, a lower than conventional mud weight drilling fluids was used and the MPD system tested and verified the pore pressure of each of the reservoir layers. The calculated pore pressures were less than the wells prognosis. Swaying from the conventional mud weight consideration and the verification of pore pressure did minimize the differential pressure across the two layers which eventually eliminated the chances of drilling fluids losses and drill pipe differential stuck. The fully automated MPD system dealt safely with all the influxes during the pore pressure verifications tests. The new approach succeeded in solving the high differential pressure problem in the reservoir as drilling progressed shoe-to-shoe without interruption. The lower mud weight used had extra benefits in areas that historically required none-damaging weighting agent, this requirement was avoided by eliminating the need for this agent, FPWD was recorded across depleted reservoirs without pipe stuck events. Moreover, it was obvious the rate of penetration was higher on these two wells than offset wells in the same field when conventional mud was used.\n For the first time in the UAE a closed-loop fully automated MPD system was utilized to lower the mud weight used when drilling across the reservoir, first time dynamic pore pressure tests were utilized to ascertain the wells prognosis and the first time FPWD was successfully recorded under substantially high differential pressure. In conclusion, the MPD was proven to be the right solution to overcome the uncertainty in pressure resulted from pressure maintenance program and reservoir depletion.","PeriodicalId":11061,"journal":{"name":"Day 1 Mon, November 11, 2019","volume":"118 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-11-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Drilling Through Multi-Layered Reservoirs Using MPD to Minimize Differential Pressure Effect by Predicting and Optimizing Required MW\",\"authors\":\"F. Gutierrez, M. Saleh, Ayoub Hadj-moussa, M. A. Alzaabi, I. Abdelkarim, Mario R. Oviedo Vargas, Olla Kadoura, Mohamed Ahmed Osman, Bilal Iftikhar Choudhry, Javier Ernesto Torres Premoli\",\"doi\":\"10.2118/197755-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n In a specific reservoir of an offshore field Abu Dhabi, several layers of the reservoir are producing subject to pressure depletion while other layers are partially or over pressurized due to water injection. Drilling through multi-layered reservoirs involves several challenges: faults and fractures, differentially stuck pipe and even total loss/kick scenarios due to pressure difference between the different layers. For reentry wells isolating the producing from injection layers is not possible due to the existing well schematic restrictions, completion requirements and target hole drainage size and location.\\n MPD was proposed to utilize a mud weight that minimizes the differential pressure between the producing and injecting layers within reservoir which mitigates the drilling problems related to high differential pressure. The game plan was to start drilling the depleted zone with the lowest possible mud weight and to enter the injecting zone (higher pressure) with this mud weight to calculate the exact pressure of the formation using the early kick detection and automatic control features of the fully automated MPD system, in this way reducing the amount of overbalance in the depleted layer if feasible.\\n Two wells were drilling using this method successfully. On both wells, a lower than conventional mud weight drilling fluids was used and the MPD system tested and verified the pore pressure of each of the reservoir layers. The calculated pore pressures were less than the wells prognosis. Swaying from the conventional mud weight consideration and the verification of pore pressure did minimize the differential pressure across the two layers which eventually eliminated the chances of drilling fluids losses and drill pipe differential stuck. The fully automated MPD system dealt safely with all the influxes during the pore pressure verifications tests. The new approach succeeded in solving the high differential pressure problem in the reservoir as drilling progressed shoe-to-shoe without interruption. The lower mud weight used had extra benefits in areas that historically required none-damaging weighting agent, this requirement was avoided by eliminating the need for this agent, FPWD was recorded across depleted reservoirs without pipe stuck events. Moreover, it was obvious the rate of penetration was higher on these two wells than offset wells in the same field when conventional mud was used.\\n For the first time in the UAE a closed-loop fully automated MPD system was utilized to lower the mud weight used when drilling across the reservoir, first time dynamic pore pressure tests were utilized to ascertain the wells prognosis and the first time FPWD was successfully recorded under substantially high differential pressure. In conclusion, the MPD was proven to be the right solution to overcome the uncertainty in pressure resulted from pressure maintenance program and reservoir depletion.\",\"PeriodicalId\":11061,\"journal\":{\"name\":\"Day 1 Mon, November 11, 2019\",\"volume\":\"118 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-11-11\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 1 Mon, November 11, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/197755-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Mon, November 11, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/197755-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

在阿布扎比海上油田的一个特定油藏中,油藏的几个层正在生产,而其他层由于注水而处于部分或过压状态。在多层储层中钻井涉及几个挑战:断层和裂缝、不同卡钻的管柱,甚至是由于不同层之间的压力差造成的全漏失/井涌。由于现有的井图限制、完井要求以及目标井眼排水尺寸和位置,再入井不可能将生产层与注入层隔离开来。MPD的目的是利用泥浆比重,将油藏内生产层和注入层之间的压差降到最低,从而减轻与高压差相关的钻井问题。该公司的计划是,以尽可能低的泥浆比重开始钻井枯竭层,然后以该泥浆比重进入注入层(压力较高),利用全自动MPD系统的早期井涌检测和自动控制功能,计算出地层的准确压力,从而在可行的情况下减少枯竭层的过平衡量。使用该方法成功钻探了两口井。在这两口井中,都使用了低于常规泥浆比重的钻井液,MPD系统测试并验证了每个储层的孔隙压力。计算的孔隙压力小于井的预测。从传统的泥浆比重考虑和孔隙压力的验证中摆脱出来,可以最大限度地减少两层之间的压差,最终消除了钻井液漏失和钻杆差卡的可能性。在孔隙压力验证测试期间,全自动MPD系统安全地处理了所有流入。这种新方法成功地解决了储层的高压差问题,钻井过程中没有中断。在以往需要无破坏性加重剂的地区,使用较低的泥浆比重具有额外的好处,通过消除对该加重剂的需求,可以避免这种要求,在无卡钻事件的枯竭油藏中记录FPWD。此外,在同一油田使用常规泥浆时,这两口井的钻速明显高于邻井。在阿联酋,首次使用闭环全自动MPD系统来降低钻井穿越油藏时使用的泥浆比重,首次使用动态孔隙压力测试来确定井的预测,并首次在非常高的压差下成功记录了FPWD。综上所述,MPD被证明是克服压力维持计划和油藏枯竭导致的压力不确定性的正确解决方案。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Drilling Through Multi-Layered Reservoirs Using MPD to Minimize Differential Pressure Effect by Predicting and Optimizing Required MW
In a specific reservoir of an offshore field Abu Dhabi, several layers of the reservoir are producing subject to pressure depletion while other layers are partially or over pressurized due to water injection. Drilling through multi-layered reservoirs involves several challenges: faults and fractures, differentially stuck pipe and even total loss/kick scenarios due to pressure difference between the different layers. For reentry wells isolating the producing from injection layers is not possible due to the existing well schematic restrictions, completion requirements and target hole drainage size and location. MPD was proposed to utilize a mud weight that minimizes the differential pressure between the producing and injecting layers within reservoir which mitigates the drilling problems related to high differential pressure. The game plan was to start drilling the depleted zone with the lowest possible mud weight and to enter the injecting zone (higher pressure) with this mud weight to calculate the exact pressure of the formation using the early kick detection and automatic control features of the fully automated MPD system, in this way reducing the amount of overbalance in the depleted layer if feasible. Two wells were drilling using this method successfully. On both wells, a lower than conventional mud weight drilling fluids was used and the MPD system tested and verified the pore pressure of each of the reservoir layers. The calculated pore pressures were less than the wells prognosis. Swaying from the conventional mud weight consideration and the verification of pore pressure did minimize the differential pressure across the two layers which eventually eliminated the chances of drilling fluids losses and drill pipe differential stuck. The fully automated MPD system dealt safely with all the influxes during the pore pressure verifications tests. The new approach succeeded in solving the high differential pressure problem in the reservoir as drilling progressed shoe-to-shoe without interruption. The lower mud weight used had extra benefits in areas that historically required none-damaging weighting agent, this requirement was avoided by eliminating the need for this agent, FPWD was recorded across depleted reservoirs without pipe stuck events. Moreover, it was obvious the rate of penetration was higher on these two wells than offset wells in the same field when conventional mud was used. For the first time in the UAE a closed-loop fully automated MPD system was utilized to lower the mud weight used when drilling across the reservoir, first time dynamic pore pressure tests were utilized to ascertain the wells prognosis and the first time FPWD was successfully recorded under substantially high differential pressure. In conclusion, the MPD was proven to be the right solution to overcome the uncertainty in pressure resulted from pressure maintenance program and reservoir depletion.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Lessons Learned from History-Matching the First Out-Of-Sequence Fracturing Field Test in North America Energy Saving Challenges and Opportunities in Upstream Operations using Value Methodology An Integrated Solution to Repair Multiple Shallow Leaks in Production Tubing – A Unique Single Trip Well Intervention Technique Openhole Completions as Recovery Case for Drilling Across Salt and High Pressure Floaters The Impact of Dynamic Filtration on Formation Testing in Low Mobility Carbonate Formations. Case Study: Lower Cretaceous Carbonate Reservoir in the UAE
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1