含酸气井测试挑战—成功案例研究

Mubashir Ahmad Mubashir, Fawad Zain Yousfi, M. Albadi, M. Baslaib, O. A. Jeelani, Amna Yaaqob Khamis Salem Aladsani, S. Alhouqani, Salah Al Qallabi, I. Bankole, Fawzi Omar Al Jaberi, Ashim Dutta, A. Shahat, Jose Alejandro Aranda, Rami Jibreel, Ghada Matar Ali, Anubhav Agarwal, Yohannes Fisher Pangestu, Rahul Kumar, A. Jaiyeola, A. Yugay, G. Pimenta, R. Masoud, Rohit V. Deshmukh, Hessa Al Shehhi, Fares Al Belooshi, Viswasri Pendyala, C. Mandal
{"title":"含酸气井测试挑战—成功案例研究","authors":"Mubashir Ahmad Mubashir, Fawad Zain Yousfi, M. Albadi, M. Baslaib, O. A. Jeelani, Amna Yaaqob Khamis Salem Aladsani, S. Alhouqani, Salah Al Qallabi, I. Bankole, Fawzi Omar Al Jaberi, Ashim Dutta, A. Shahat, Jose Alejandro Aranda, Rami Jibreel, Ghada Matar Ali, Anubhav Agarwal, Yohannes Fisher Pangestu, Rahul Kumar, A. Jaiyeola, A. Yugay, G. Pimenta, R. Masoud, Rohit V. Deshmukh, Hessa Al Shehhi, Fares Al Belooshi, Viswasri Pendyala, C. Mandal","doi":"10.2118/197482-ms","DOIUrl":null,"url":null,"abstract":"\n ADNOC onshore tested HPHT sour gas reservoirs with 30% H2S, 10% CO2 to evaluate the reservoir and well potential as part of the efforts in supplying additional gas for meeting country's growing energy needs. Developing these massive HPHT sour gas reservoirs is essential for providing a sustainable source of energy for years to come.\n This critical project serves the broader national strategy and country aspirations in fulfilling the gas demand over the next few decades to come.\n Few HPHT sour wells were drilled but only one well could be tested successfully. The other two wells had to be suspended due to HSE /environmental and operational reason as elemental Sulphur was detected.\n Based on the previous well test and reservoir data, it was decided to use one of the existing well and sidetrack in the Sour reservoir to gain experience about drilling a long horizontal section in the High pressure, high temperature sour condition. A specialized drilling Rig capable of drilling the long horizontal well was selected. Due to nature of the reservoir, specialized sour service drilling tools were selected considered the long departure and long open hole horizontal length of 10000+ ft. Selection of the downhole material for these conditions was itself a challenge as very few vendors or IOC (Internatioanl oil companies) have experience of developing and producing from +30% H2S and +10% CO2.\n Due to the location of the well, stringent HSE measurements were adapter to ensure zero tolerance for the safety violation in accordance with 100% HSE.\n The testing of the HPHT sour gas was challenging due to not only HSE issues but also from the environment part too as flaring needed to be minimized in the brown field. Hence, it was decided to Tie-in the well to the nearby facilities. The challenge was that the existing facilities were not design to accept the sour gas. This was overcome by blending the sour gas with sweet gas to meet the existing facilities specs and capacities.\n After the well was drilled, the +10000 ft. open hole was flowed to clean to ensure all the drilling fluid lost was recovered to test to access well potential and obtain representative data for full field development plan.\n Drilling, testing and producing the highly sour HPHT gas reservoirs with more than 30% H2S and 10% CO2 along with temperature ranging up to 300 deg F is itself a huge challenge.\n Over the last few years, ADNOC Onshore have developed considerable expertise in testing the sour wells considering all the safety and environmental aspects.\n This paper highlights the work progress and the lessons learned during each step of the operation from planning phase to drilling, tie-in the well to the existing facilities after dilution during testing. All the proposed mitigation plans considering 100% HSE while dealing with these appraisal wells in the Arab sour reservoir having +30% H2S and 10 % CO2 were developed and implemented sucessfully.","PeriodicalId":11328,"journal":{"name":"Day 4 Thu, November 14, 2019","volume":"19 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-11-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Sour Gas Well Testing Challenges-A Successful Case Study\",\"authors\":\"Mubashir Ahmad Mubashir, Fawad Zain Yousfi, M. Albadi, M. Baslaib, O. A. Jeelani, Amna Yaaqob Khamis Salem Aladsani, S. Alhouqani, Salah Al Qallabi, I. Bankole, Fawzi Omar Al Jaberi, Ashim Dutta, A. Shahat, Jose Alejandro Aranda, Rami Jibreel, Ghada Matar Ali, Anubhav Agarwal, Yohannes Fisher Pangestu, Rahul Kumar, A. Jaiyeola, A. Yugay, G. Pimenta, R. Masoud, Rohit V. Deshmukh, Hessa Al Shehhi, Fares Al Belooshi, Viswasri Pendyala, C. Mandal\",\"doi\":\"10.2118/197482-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n ADNOC onshore tested HPHT sour gas reservoirs with 30% H2S, 10% CO2 to evaluate the reservoir and well potential as part of the efforts in supplying additional gas for meeting country's growing energy needs. Developing these massive HPHT sour gas reservoirs is essential for providing a sustainable source of energy for years to come.\\n This critical project serves the broader national strategy and country aspirations in fulfilling the gas demand over the next few decades to come.\\n Few HPHT sour wells were drilled but only one well could be tested successfully. The other two wells had to be suspended due to HSE /environmental and operational reason as elemental Sulphur was detected.\\n Based on the previous well test and reservoir data, it was decided to use one of the existing well and sidetrack in the Sour reservoir to gain experience about drilling a long horizontal section in the High pressure, high temperature sour condition. A specialized drilling Rig capable of drilling the long horizontal well was selected. Due to nature of the reservoir, specialized sour service drilling tools were selected considered the long departure and long open hole horizontal length of 10000+ ft. Selection of the downhole material for these conditions was itself a challenge as very few vendors or IOC (Internatioanl oil companies) have experience of developing and producing from +30% H2S and +10% CO2.\\n Due to the location of the well, stringent HSE measurements were adapter to ensure zero tolerance for the safety violation in accordance with 100% HSE.\\n The testing of the HPHT sour gas was challenging due to not only HSE issues but also from the environment part too as flaring needed to be minimized in the brown field. Hence, it was decided to Tie-in the well to the nearby facilities. The challenge was that the existing facilities were not design to accept the sour gas. This was overcome by blending the sour gas with sweet gas to meet the existing facilities specs and capacities.\\n After the well was drilled, the +10000 ft. open hole was flowed to clean to ensure all the drilling fluid lost was recovered to test to access well potential and obtain representative data for full field development plan.\\n Drilling, testing and producing the highly sour HPHT gas reservoirs with more than 30% H2S and 10% CO2 along with temperature ranging up to 300 deg F is itself a huge challenge.\\n Over the last few years, ADNOC Onshore have developed considerable expertise in testing the sour wells considering all the safety and environmental aspects.\\n This paper highlights the work progress and the lessons learned during each step of the operation from planning phase to drilling, tie-in the well to the existing facilities after dilution during testing. All the proposed mitigation plans considering 100% HSE while dealing with these appraisal wells in the Arab sour reservoir having +30% H2S and 10 % CO2 were developed and implemented sucessfully.\",\"PeriodicalId\":11328,\"journal\":{\"name\":\"Day 4 Thu, November 14, 2019\",\"volume\":\"19 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-11-11\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 4 Thu, November 14, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/197482-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 4 Thu, November 14, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/197482-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

ADNOC在陆上测试了含30% H2S和10% CO2的高温高压含硫气藏,以评估储层和井的潜力,为满足国家日益增长的能源需求提供额外的天然气。开发这些大型高温高温含酸气藏对于在未来几年提供可持续的能源来源至关重要。这个关键项目服务于更广泛的国家战略和国家在未来几十年满足天然气需求的愿望。高温高压酸井很少,但只有一口井测试成功。由于检测到硫元素,由于HSE /环境和操作原因,另外两口井不得不暂停。根据之前的试井和储层资料,决定利用含硫油藏现有的一口井和侧钻,以获得在高压、高温含硫条件下钻长水平段的经验。选择了一台能够钻长水平井的专用钻机。由于储层的性质,选择了专门的含酸钻井工具,考虑了长井距和10000+ ft的长裸眼水平长度。为这些条件选择井下材料本身就是一个挑战,因为很少有供应商或IOC(国际石油公司)有在+30% H2S和+10% CO2环境下开发和生产的经验。由于该井的位置,严格的HSE测量是为了确保对安全违规行为的零容忍,符合100%的HSE标准。高温高压含酸气的测试具有挑战性,不仅存在HSE问题,还存在环境方面的问题,因为棕色气田需要最大限度地减少燃烧。因此,决定将油井与附近的设施相连接。面临的挑战是,现有设施的设计不能接受酸性气体。通过将含硫气体与含硫气体混合,以满足现有设施的规格和容量,解决了这一问题。钻完井后,对10000英尺的裸眼进行清洗,以确保所有流失的钻井液都被回收,以测试井的潜力,并获得整个油田开发计划的代表性数据。高含硫高温高压气藏的钻井、测试和开采本身就是一个巨大的挑战,其硫化氢含量超过30%,二氧化碳含量超过10%,温度高达300华氏度。在过去的几年中,考虑到所有安全和环境方面,ADNOC陆上公司在测试酸井方面积累了相当多的专业知识。本文重点介绍了从计划阶段到钻井,在测试稀释后将井与现有设施连接的每个步骤的工作进展和经验教训。在处理阿拉伯含+30% H2S和10% CO2的酸性油藏评价井时,所有建议的缓解计划都考虑了100%的HSE,并成功开发和实施。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Sour Gas Well Testing Challenges-A Successful Case Study
ADNOC onshore tested HPHT sour gas reservoirs with 30% H2S, 10% CO2 to evaluate the reservoir and well potential as part of the efforts in supplying additional gas for meeting country's growing energy needs. Developing these massive HPHT sour gas reservoirs is essential for providing a sustainable source of energy for years to come. This critical project serves the broader national strategy and country aspirations in fulfilling the gas demand over the next few decades to come. Few HPHT sour wells were drilled but only one well could be tested successfully. The other two wells had to be suspended due to HSE /environmental and operational reason as elemental Sulphur was detected. Based on the previous well test and reservoir data, it was decided to use one of the existing well and sidetrack in the Sour reservoir to gain experience about drilling a long horizontal section in the High pressure, high temperature sour condition. A specialized drilling Rig capable of drilling the long horizontal well was selected. Due to nature of the reservoir, specialized sour service drilling tools were selected considered the long departure and long open hole horizontal length of 10000+ ft. Selection of the downhole material for these conditions was itself a challenge as very few vendors or IOC (Internatioanl oil companies) have experience of developing and producing from +30% H2S and +10% CO2. Due to the location of the well, stringent HSE measurements were adapter to ensure zero tolerance for the safety violation in accordance with 100% HSE. The testing of the HPHT sour gas was challenging due to not only HSE issues but also from the environment part too as flaring needed to be minimized in the brown field. Hence, it was decided to Tie-in the well to the nearby facilities. The challenge was that the existing facilities were not design to accept the sour gas. This was overcome by blending the sour gas with sweet gas to meet the existing facilities specs and capacities. After the well was drilled, the +10000 ft. open hole was flowed to clean to ensure all the drilling fluid lost was recovered to test to access well potential and obtain representative data for full field development plan. Drilling, testing and producing the highly sour HPHT gas reservoirs with more than 30% H2S and 10% CO2 along with temperature ranging up to 300 deg F is itself a huge challenge. Over the last few years, ADNOC Onshore have developed considerable expertise in testing the sour wells considering all the safety and environmental aspects. This paper highlights the work progress and the lessons learned during each step of the operation from planning phase to drilling, tie-in the well to the existing facilities after dilution during testing. All the proposed mitigation plans considering 100% HSE while dealing with these appraisal wells in the Arab sour reservoir having +30% H2S and 10 % CO2 were developed and implemented sucessfully.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Evaluation of bag-of-features (BoF) technique for weed management in sugarcane production Spraying deposits using different nozzles and application volumes for pest management of cotton at reproductive stage Opioid Prescription in Switzerland: Appropriate Comedication use in Cancer and Noncancer Pain Co-Development Aspects of Super Giant Reservoirs With Condensate-Rich Gas Cap Healing Total Losses and Establishing Well Integrity with Engineered Fiber-Based Lost Circulation Control Spacer During Primary Cementing in UAE Offshore
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1