Restoration Strategies for the South China Interconnected Power System after Generator Tripping following DC System Fault

G. Cheng, Z. Xu, J. Chao
{"title":"Restoration Strategies for the South China Interconnected Power System after Generator Tripping following DC System Fault","authors":"G. Cheng, Z. Xu, J. Chao","doi":"10.1109/TDC.2006.1668656","DOIUrl":null,"url":null,"abstract":"When such severe contingency as double pole block fault arouses instability in the South China interconnected power system (SCIPS), selective tripping of generating units in the sending end has to be used as a method to maintain system stability. In case the tripped units go through a shutdown and cold start cycle for long duration, it is desirable that they should be hot started and resynchronized to the system as soon as possible to make a quick recovery of the system after fault. Under conditions where the DC fault is permanent, however, such objective is difficult to achieve. This paper presents a control strategy that power generation of some running units be reduced during this process to permit the tripped units to be resynchronized to the system without changing the power level at the sending end, which enables the tripped units to be restored to load rapidly without disturbing system stability. With user models developed in PSS/E, simulations were performed on the SCIPS to investigate the system behavior during reloading process of those thermal units which had been tripped following DC block fault. The results show that power generation at the sending end can be maintained at a reasonable steady level when output of some running units are appropriately reduced during the reloading process of the thermal units, thus having little impact on the system stability, which demonstrates the feasibility and effectiveness of the proposed scheme","PeriodicalId":123024,"journal":{"name":"2005/2006 IEEE/PES Transmission and Distribution Conference and Exhibition","volume":"95 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2006-05-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2005/2006 IEEE/PES Transmission and Distribution Conference and Exhibition","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/TDC.2006.1668656","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

When such severe contingency as double pole block fault arouses instability in the South China interconnected power system (SCIPS), selective tripping of generating units in the sending end has to be used as a method to maintain system stability. In case the tripped units go through a shutdown and cold start cycle for long duration, it is desirable that they should be hot started and resynchronized to the system as soon as possible to make a quick recovery of the system after fault. Under conditions where the DC fault is permanent, however, such objective is difficult to achieve. This paper presents a control strategy that power generation of some running units be reduced during this process to permit the tripped units to be resynchronized to the system without changing the power level at the sending end, which enables the tripped units to be restored to load rapidly without disturbing system stability. With user models developed in PSS/E, simulations were performed on the SCIPS to investigate the system behavior during reloading process of those thermal units which had been tripped following DC block fault. The results show that power generation at the sending end can be maintained at a reasonable steady level when output of some running units are appropriately reduced during the reloading process of the thermal units, thus having little impact on the system stability, which demonstrates the feasibility and effectiveness of the proposed scheme
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
华南互联电力系统直流系统故障后发电机跳闸的恢复策略
当双极块故障等严重突发事件引起华南互联电力系统失稳时,必须采用发端发电机组选择性跳闸的方法来维持系统稳定。当跳闸机组长时间经历停机和冷启动循环时,应尽快对跳闸机组进行热启动并重新同步到系统中,使系统在故障后能够快速恢复。然而,在直流故障是永久性的情况下,这一目标很难实现。本文提出了一种控制策略,即在不改变发送端的功率水平的情况下,减少部分运行机组的发电量,使跳闸机组重新同步到系统中,从而使跳闸机组在不影响系统稳定性的情况下迅速恢复到负荷状态。通过在PSS/E中建立用户模型,在SCIPS上进行了仿真,研究了在直流块故障后跳闸的热机组在重新加载过程中的系统行为。结果表明,在热电机组再负荷过程中,适当减少部分运行机组的出力,可使送电端发电量保持在合理的稳定水平,对系统稳定性影响较小,证明了所提方案的可行性和有效性
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
相关文献
Interactions of nitrosonium salts with crown ethers
IF 2.4 3区 化学Journal of Heterocyclic ChemistryPub Date : 1982-09-01 DOI: 10.1002/jhet.5570190523
Gwi Suk Heo, Patrick E. Hillman, Richard A. Bartsch
Nitrosonium Salts as Reagents in Inorganic Synthesis
IF 0 Synthesis and Reactivity in Inorganic and Metal-organic ChemistryPub Date : 1974-07-23 DOI: 10.1080/00945717408069633
M. Mocella, M. S. Okamoto, E. Barefield
Solution calorimetry of nitrosonium salts
IF 0 Journal of The Chemical Society-dalton TransactionsPub Date : 1981-03-24 DOI: 10.1039/DT9800002415
A. Finch, P. N. Gates, T. Page
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Progress Report on Natural Esters for Distribution and Power Transformers Modeling Stalled Induction Motors Application and Benefits of Dynamic Shunt Compensation Model Validation of Power System Components Using Hybrid Dynamic Simulation Corrosion and Current Burst Testing of Copper and Aluminum Electrical Power Connectors
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1