Structuring risks for a comprehensive understanding of cost overruns in power plant projects

Muhammad Saiful Islam, Madhav Nepal, Martin Skitmore
{"title":"Structuring risks for a comprehensive understanding of cost overruns in power plant projects","authors":"Muhammad Saiful Islam, Madhav Nepal, Martin Skitmore","doi":"10.1108/ci-05-2022-0120","DOIUrl":null,"url":null,"abstract":"Purpose Power plant projects are very complex and encounter serious cost overruns worldwide. Their cost overrun risks are not independent but interrelated in many cases, having structural relationships among each other. The purpose of this study is, therefore, to establish the complex structural relationships of risks involved. Design/methodology/approach In total, 76 published articles from the previous literature are reviewed using the content analysis method. Three risk networks in different phases of power plant projects are depicted based on literature review and case studies. The possible methods of solving these risk networks are also discussed. Findings The study finds critical cost overrun risks and develops risk networks for the procurement, civil and mechanical works of power plant projects. It identifies potential models to assess cost overrun risks based on the developed risk networks. The literature review also revealed some research gaps in the cost overrun risk management of power plants and similar infrastructure projects. Practical implications This study will assist project risk managers to understand the potential risks and their relationships to prevent and mitigate cost overruns for future power plant projects. It will also facilitate decision-makers developing a risk management framework and controlling projects’ cost overruns. Originality/value The study presents conceptual risk networks in different phases of power plant projects for comprehending the root causes of cost overruns. A comparative discussion of the relevant models available in the literature is presented, where their potential applications, limitations and further improvement areas are discussed to solve the developed risk networks for modeling cost overrun risks.","PeriodicalId":221945,"journal":{"name":"Construction Innovation: Information, Process, Management","volume":"34 3","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-10-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Construction Innovation: Information, Process, Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/ci-05-2022-0120","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Purpose Power plant projects are very complex and encounter serious cost overruns worldwide. Their cost overrun risks are not independent but interrelated in many cases, having structural relationships among each other. The purpose of this study is, therefore, to establish the complex structural relationships of risks involved. Design/methodology/approach In total, 76 published articles from the previous literature are reviewed using the content analysis method. Three risk networks in different phases of power plant projects are depicted based on literature review and case studies. The possible methods of solving these risk networks are also discussed. Findings The study finds critical cost overrun risks and develops risk networks for the procurement, civil and mechanical works of power plant projects. It identifies potential models to assess cost overrun risks based on the developed risk networks. The literature review also revealed some research gaps in the cost overrun risk management of power plants and similar infrastructure projects. Practical implications This study will assist project risk managers to understand the potential risks and their relationships to prevent and mitigate cost overruns for future power plant projects. It will also facilitate decision-makers developing a risk management framework and controlling projects’ cost overruns. Originality/value The study presents conceptual risk networks in different phases of power plant projects for comprehending the root causes of cost overruns. A comparative discussion of the relevant models available in the literature is presented, where their potential applications, limitations and further improvement areas are discussed to solve the developed risk networks for modeling cost overrun risks.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
对电厂项目中成本超支的风险进行结构分析
在世界范围内,电厂项目非常复杂,经常遇到严重的成本超支问题。它们的成本超支风险在很多情况下不是独立的,而是相互关联的,彼此之间存在结构性关系。因此,本研究的目的是建立所涉及风险的复杂结构关系。设计/方法/方法总共使用内容分析法对以往文献中发表的76篇文章进行了回顾。在文献综述和案例分析的基础上,描述了电厂项目不同阶段的三种风险网络。讨论了解决这些风险网络的可能方法。该研究发现了关键的成本超支风险,并为电厂项目的采购、土木和机械工程建立了风险网络。它根据已开发的风险网络确定了评估成本超支风险的潜在模型。文献综述也揭示了电厂及类似基础设施项目成本超支风险管理的一些研究空白。本研究将协助项目风险管理人员了解潜在风险及其关系,以预防和减轻未来电厂项目的成本超支。它还将促进决策者制定风险管理框架和控制项目的成本超支。本研究提出电厂项目不同阶段的概念性风险网络,以了解成本超支的根本原因。对文献中可用的相关模型进行了比较讨论,讨论了它们的潜在应用、局限性和进一步改进的领域,以解决用于建模成本超支风险的发达风险网络。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
The feasibility of transparent solar panels for high-rise building façade in Sri Lanka Detecting skewed pricing in tenders for public-sector projects Understanding the key risks in circular construction projects: from systematic review to conceptual framework A critical review of quantity surveying education in an offsite construction perspective: strategies for up-skilling Development and testing of lean simulation game on set-based design
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1