A Moorland dam - remedial grouting works

Tom Rigby
{"title":"A Moorland dam - remedial grouting works","authors":"Tom Rigby","doi":"10.1680/jdare.24.00011","DOIUrl":null,"url":null,"abstract":"Dam T was constructed around 1880 as a water supply to Greater Manchester and is a Category A impounding reservoir, comprising an earth embankment with a central puddle clay core and storage capacity of approximately 934,000m3. It is one of the earliest dams constructed by Bateman and lies in a cascade of three reservoirs. As part of United Utilities (UU) Portfolio Risk Assessment (PRA) an Internal Erosion Toolbox, flood and slope stability studies were undertaken. These identified that the reservoir's primary failure mechanism was internal erosion through the embankment and presented an unacceptable risk. In order to confirm the conclusions and target a potential solution a Willowstick survey was undertaken which identified two potential seepage flow paths, one flowing into the existing outlet conduit upstream of the core and the other suggesting a compromised central core. This paper summarises the grouting works undertaken to target and remediate the potential core defect in a constrained and environmentally sensitive site. It highlights the benefits of collaborative working, supported by specialist contractors, the Qualified Civil Engineer (QCE) and catchment teams, the use of innovative techniques and lessons learnt from previous projects as well as the challenges presented by the proximity of the public and nesting birds. A total of 322,980 litres of grout was carefully injected into the Tube-a-Manchette (TAM) installations with the works completed in June 2023, two months ahead of programme and significantly below predicted costs, enabling the local walking routes to be reopened prior to the school holidays.","PeriodicalId":505716,"journal":{"name":"Dams and Reservoirs","volume":"135 24","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-04-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Dams and Reservoirs","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1680/jdare.24.00011","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Dam T was constructed around 1880 as a water supply to Greater Manchester and is a Category A impounding reservoir, comprising an earth embankment with a central puddle clay core and storage capacity of approximately 934,000m3. It is one of the earliest dams constructed by Bateman and lies in a cascade of three reservoirs. As part of United Utilities (UU) Portfolio Risk Assessment (PRA) an Internal Erosion Toolbox, flood and slope stability studies were undertaken. These identified that the reservoir's primary failure mechanism was internal erosion through the embankment and presented an unacceptable risk. In order to confirm the conclusions and target a potential solution a Willowstick survey was undertaken which identified two potential seepage flow paths, one flowing into the existing outlet conduit upstream of the core and the other suggesting a compromised central core. This paper summarises the grouting works undertaken to target and remediate the potential core defect in a constrained and environmentally sensitive site. It highlights the benefits of collaborative working, supported by specialist contractors, the Qualified Civil Engineer (QCE) and catchment teams, the use of innovative techniques and lessons learnt from previous projects as well as the challenges presented by the proximity of the public and nesting birds. A total of 322,980 litres of grout was carefully injected into the Tube-a-Manchette (TAM) installations with the works completed in June 2023, two months ahead of programme and significantly below predicted costs, enabling the local walking routes to be reopened prior to the school holidays.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
A Moorland 大坝--补救性灌浆工程
T 号大坝建于 1880 年左右,用于向大曼彻斯特地区供水,是一座甲级蓄水池,由土堤和中央水坑粘土核心组成,蓄水量约为 934,000 立方米。它是贝特曼最早建造的水坝之一,由三座水库组成。作为英国联合公用事业公司(UU)组合风险评估(PRA)的一部分,对内部侵蚀工具箱、洪水和斜坡稳定性进行了研究。研究结果表明,水库的主要破坏机制是堤坝内部侵蚀,存在不可接受的风险。为了确认结论并找到潜在的解决方案,我们进行了柳条测量,发现了两条潜在的渗流路径,一条流入核心上游现有的出口导管,另一条则表明中央核心受到了破坏。本文总结了在一个受限且环境敏感的地点,针对潜在的岩心缺陷进行的灌浆工程。本文强调了在专业承包商、合格土木工程师 (QCE) 和集水区团队的支持下协同工作的益处、创新技术的使用、从以往项目中汲取的经验教训,以及临近公众和鸟类筑巢所带来的挑战。工程于 2023 年 6 月完工,比计划提前了两个月,大大低于预期成本,使当地的步行路线能够在学校放假前重新开放。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
An updated reference table for extreme flood hydrology methods at UK dams The delivery of multiple benefits on the Llyn Tegid reservoir safety improvements project Efficiency of labyrinth vs ogee spillways at high hydraulic heads - case study in Zambia A Moorland dam - remedial grouting works ICOLD 2023, Gothenburg Sweden – Report on Workshop 4
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1