Monitoring concrete pouring progress using knowledge graph-enhanced computer vision

IF 9.6 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Automation in Construction Pub Date : 2025-03-18 DOI:10.1016/j.autcon.2025.106117
Fabian Pfitzner , Songbo Hu , Alexander Braun , André Borrmann , Yihai Fang
{"title":"Monitoring concrete pouring progress using knowledge graph-enhanced computer vision","authors":"Fabian Pfitzner ,&nbsp;Songbo Hu ,&nbsp;Alexander Braun ,&nbsp;André Borrmann ,&nbsp;Yihai Fang","doi":"10.1016/j.autcon.2025.106117","DOIUrl":null,"url":null,"abstract":"<div><div>Accurate progress measurement in concrete pouring is essential to prevent project delays and material waste. This paper introduces a knowledge graph (KG)-enhanced computer vision (CV) method to improve the accuracy and generalizability of traditional methods used in concrete pouring monitoring, which often struggle to integrate contextual data. By combining object detection and extracting information from BIM models, the method creates a KG to represent spatial–temporal relationships among building components and pouring-related resources (<em>e.g</em>., concrete mixer, bucket, hose, workers). Rule-based interpretation and Graph Neural Networks (GNN) classify pouring states and cycles, achieving 80.3% accuracy with the rule-based system and 89.2% with GNN in conducted experiments on ten samples across two construction sites. These findings demonstrate that the KG-enhanced CV method provides generalizability, offering data-driven support for site managers to efficiently coordinate processes. This approach lays the foundation for detailed process-oriented digital twinning of construction projects, enabling deeper insights and better decision-making.</div></div>","PeriodicalId":8660,"journal":{"name":"Automation in Construction","volume":"174 ","pages":"Article 106117"},"PeriodicalIF":9.6000,"publicationDate":"2025-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Automation in Construction","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S0926580525001578","RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 0

Abstract

Accurate progress measurement in concrete pouring is essential to prevent project delays and material waste. This paper introduces a knowledge graph (KG)-enhanced computer vision (CV) method to improve the accuracy and generalizability of traditional methods used in concrete pouring monitoring, which often struggle to integrate contextual data. By combining object detection and extracting information from BIM models, the method creates a KG to represent spatial–temporal relationships among building components and pouring-related resources (e.g., concrete mixer, bucket, hose, workers). Rule-based interpretation and Graph Neural Networks (GNN) classify pouring states and cycles, achieving 80.3% accuracy with the rule-based system and 89.2% with GNN in conducted experiments on ten samples across two construction sites. These findings demonstrate that the KG-enhanced CV method provides generalizability, offering data-driven support for site managers to efficiently coordinate processes. This approach lays the foundation for detailed process-oriented digital twinning of construction projects, enabling deeper insights and better decision-making.

Abstract Image

查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
求助全文
约1分钟内获得全文 去求助
来源期刊
Automation in Construction
Automation in Construction 工程技术-工程:土木
CiteScore
19.20
自引率
16.50%
发文量
563
审稿时长
8.5 months
期刊介绍: Automation in Construction is an international journal that focuses on publishing original research papers related to the use of Information Technologies in various aspects of the construction industry. The journal covers topics such as design, engineering, construction technologies, and the maintenance and management of constructed facilities. The scope of Automation in Construction is extensive and covers all stages of the construction life cycle. This includes initial planning and design, construction of the facility, operation and maintenance, as well as the eventual dismantling and recycling of buildings and engineering structures.
期刊最新文献
Automated residential layout generation and editing using natural language and images Monitoring concrete pouring progress using knowledge graph-enhanced computer vision Automating inspection data from bridge management system into bridge information model Performance-based payment mechanism for common data environment (CDE) adoption in construction projects Reference architecture and ontology framework for digital twin construction
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1