Installation of Conductor Supported Platform CSP at X Field

Helmi Ngadiman
{"title":"Installation of Conductor Supported Platform CSP at X Field","authors":"Helmi Ngadiman","doi":"10.2118/205727-ms","DOIUrl":null,"url":null,"abstract":"\n This technical paper presents the offshore installation execution work of Conductor Supported Platforms (CSP) at ‘X’ field. The knowledge sharing was based on the successful installation of three (3) numbers of CSP for ‘X’ development project. The platforms were installed at approximately of 70m water depth and encountered technical challenges during offshore execution.\n ‘X’ field is located about approximately 45km North West of Miri, Sarawak. The CSPs were installed by Derrick Barge (DB) via double blocks crane upending method for the substructures and conventional lifting method for the topsides. The CSP was designed for 70 meters water depth with four (4) numbers of vertical legs, four (4) numbers of skirt piles, and one (1) number of pin pile. The weight of the topside was about 600MT, meanwhile the substructure was about 1100MT respectively.\n These CSPs marked as a pioneer in the installation of its kinds at 70m water depth in COMPANY. The concept required high accuracy of detailed offshore installation engineering. This configuration however had caused some challenges during installation. Among the major challenges were issues on the pin-pile verticality, substructure levelness and upending activities via double blocks crane upending method.\n The effective strategies were adopted to improve the on-bottom stability by installing pin pile prior to substructure set down. The pin pile was installed by utilizing Subsea Fast Frame (SFF), in order to achieve pin pile's verticality. The crucial part during pin pile installation was to ensure meeting the verticality accuracy and minimum tolerance may high potentially impact the substructure install ability and meeting level requirement.\n However, due to a big annulus gap at pin pile sleeve of the substructure had caused prolong in levelling operation. In order to improve subsequent platforms levelling operations, a set of centralizers were introduced and installed after confirming the pin pile verticality result, in order to reduce the annulus gap. Despite all the challenges aforementioned, the installation of CSPs were completed successfully and most importantly with Zero Lost Time Injury (LTI).","PeriodicalId":10970,"journal":{"name":"Day 1 Tue, October 12, 2021","volume":"9 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-10-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Tue, October 12, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/205727-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This technical paper presents the offshore installation execution work of Conductor Supported Platforms (CSP) at ‘X’ field. The knowledge sharing was based on the successful installation of three (3) numbers of CSP for ‘X’ development project. The platforms were installed at approximately of 70m water depth and encountered technical challenges during offshore execution. ‘X’ field is located about approximately 45km North West of Miri, Sarawak. The CSPs were installed by Derrick Barge (DB) via double blocks crane upending method for the substructures and conventional lifting method for the topsides. The CSP was designed for 70 meters water depth with four (4) numbers of vertical legs, four (4) numbers of skirt piles, and one (1) number of pin pile. The weight of the topside was about 600MT, meanwhile the substructure was about 1100MT respectively. These CSPs marked as a pioneer in the installation of its kinds at 70m water depth in COMPANY. The concept required high accuracy of detailed offshore installation engineering. This configuration however had caused some challenges during installation. Among the major challenges were issues on the pin-pile verticality, substructure levelness and upending activities via double blocks crane upending method. The effective strategies were adopted to improve the on-bottom stability by installing pin pile prior to substructure set down. The pin pile was installed by utilizing Subsea Fast Frame (SFF), in order to achieve pin pile's verticality. The crucial part during pin pile installation was to ensure meeting the verticality accuracy and minimum tolerance may high potentially impact the substructure install ability and meeting level requirement. However, due to a big annulus gap at pin pile sleeve of the substructure had caused prolong in levelling operation. In order to improve subsequent platforms levelling operations, a set of centralizers were introduced and installed after confirming the pin pile verticality result, in order to reduce the annulus gap. Despite all the challenges aforementioned, the installation of CSPs were completed successfully and most importantly with Zero Lost Time Injury (LTI).
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
在X油田安装导体支撑平台CSP
本文介绍了“X”油田导体支撑平台(CSP)的海上安装实施工作。知识共享是基于为“X”开发项目成功安装了三(3)个CSP。这些平台安装在水深约70米的地方,在海上执行过程中遇到了技术挑战。X油田位于Sarawak Miri西北约45公里处。csp由Derrick Barge (DB)安装,下部结构采用双块起重机吊装方法,上部采用常规吊装方法。CSP设计用于70米水深,具有四(4)个垂直支腿,四(4)个裙边桩和一(1)个销桩。上部结构重量约600MT,下部结构重量约1100MT。这些csp标志着公司在70米水深安装同类设备的先驱。该概念要求高精度的海上安装工程细节。但是,这种配置在安装过程中造成了一些问题。其中主要的挑战是销桩的垂直性、下层结构的水平度和双块吊车吊顶法的翻转活动问题。采用了在下部沉降前安装销桩的有效策略,提高了底层稳定性。销桩采用海底快速框架(SFF)安装,以实现销桩的垂直性。销桩安装的关键是保证桩身的垂直精度,而桩身的最小公差对桩身的安装能力和水平要求有很大的潜在影响。但由于子结构销桩套筒处环隙较大,造成找平作业时间延长。为了改进后续平台调平作业,在确认销桩垂直度结果后,引入一套扶正器进行安装,以减小环空间隙。尽管存在上述所有挑战,csp的安装还是成功完成了,最重要的是实现了零损失时间伤害(LTI)。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Successful Application of Managed Pressure Drilling and Cementing in Naturally Fractured Carbonates Environment of Prohorovskoe Exploration Well The Use of Induction Heating in Assessing the Technical Condition and Operating Intervals in Producing Wells A 3-Step Reaction Model For Numerical Simulation of In-Situ Combustion An Example of Building a Petrophysical Model of Unconsolidated Gas-Saturated Laminated Sediments Using Advanced Wireline and Logging While Drilling Services New method for Handling of Infrastructural Constraints for Integrated Modeling in Steady Case
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1