{"title":"考虑CO2排放和最大热等待时间最小化的废钢电炉SCC调度多目标优化","authors":"Ye Yang, Weida Chen, Li Wei","doi":"10.1109/CCDC.2018.8407804","DOIUrl":null,"url":null,"abstract":"Under the carbon emission reduction policy, iron and steel enterprises are faced with huge pressure of carbon emission reduction. In the process of melting scrap steels using electric furnaces, the heats (jobs) are always assigned with different processing routes, and types of the parallel electric furnaces at each production stage are usually different. First, combining these characteristics, a model considering carbon emission and minimization of maximal heat waiting time for multi-objective optimization of scrap steel electric furnace steelmaking and continuous casting (SCC) scheduling is built. Three objectives, i.e. carbon emission, maximal heat waiting time and makespan, are involved in the model. Then the non-dominated sorting genetic algorithm-II (NSGA-II) suitable for solving the problem is designed accordingly. Finally, the numerical analysis shows that the algorithm can obtain satisfactory solution, considering the objective of minimizing maximal heat waiting time is beneficial to avoid the risk of rescheduling, and the research can help decision makers achieve the target of carbon emission reduction ensuring continuous and efficient SCC production.","PeriodicalId":409960,"journal":{"name":"2018 Chinese Control And Decision Conference (CCDC)","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2018-06-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Multi-objective optimization of scrap steel electric furnace SCC scheduling considering CO2 emission and minimization of maximal heat waiting time\",\"authors\":\"Ye Yang, Weida Chen, Li Wei\",\"doi\":\"10.1109/CCDC.2018.8407804\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Under the carbon emission reduction policy, iron and steel enterprises are faced with huge pressure of carbon emission reduction. In the process of melting scrap steels using electric furnaces, the heats (jobs) are always assigned with different processing routes, and types of the parallel electric furnaces at each production stage are usually different. First, combining these characteristics, a model considering carbon emission and minimization of maximal heat waiting time for multi-objective optimization of scrap steel electric furnace steelmaking and continuous casting (SCC) scheduling is built. Three objectives, i.e. carbon emission, maximal heat waiting time and makespan, are involved in the model. Then the non-dominated sorting genetic algorithm-II (NSGA-II) suitable for solving the problem is designed accordingly. Finally, the numerical analysis shows that the algorithm can obtain satisfactory solution, considering the objective of minimizing maximal heat waiting time is beneficial to avoid the risk of rescheduling, and the research can help decision makers achieve the target of carbon emission reduction ensuring continuous and efficient SCC production.\",\"PeriodicalId\":409960,\"journal\":{\"name\":\"2018 Chinese Control And Decision Conference (CCDC)\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-06-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2018 Chinese Control And Decision Conference (CCDC)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/CCDC.2018.8407804\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2018 Chinese Control And Decision Conference (CCDC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CCDC.2018.8407804","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Multi-objective optimization of scrap steel electric furnace SCC scheduling considering CO2 emission and minimization of maximal heat waiting time
Under the carbon emission reduction policy, iron and steel enterprises are faced with huge pressure of carbon emission reduction. In the process of melting scrap steels using electric furnaces, the heats (jobs) are always assigned with different processing routes, and types of the parallel electric furnaces at each production stage are usually different. First, combining these characteristics, a model considering carbon emission and minimization of maximal heat waiting time for multi-objective optimization of scrap steel electric furnace steelmaking and continuous casting (SCC) scheduling is built. Three objectives, i.e. carbon emission, maximal heat waiting time and makespan, are involved in the model. Then the non-dominated sorting genetic algorithm-II (NSGA-II) suitable for solving the problem is designed accordingly. Finally, the numerical analysis shows that the algorithm can obtain satisfactory solution, considering the objective of minimizing maximal heat waiting time is beneficial to avoid the risk of rescheduling, and the research can help decision makers achieve the target of carbon emission reduction ensuring continuous and efficient SCC production.