{"title":"减少配电变压器负载和降级因素对低压电网承载能力的限制","authors":"Agaba Ame‐Oko, Olga Lavrova","doi":"10.1049/esi2.12143","DOIUrl":null,"url":null,"abstract":"A distribution transformer's thermal operating conditions can impose a limitation on the Hosting Capacity (HC) of an electrical distribution feeder for PV interconnections in the feeder's low‐voltage network. This is undesirable as it curtails PV interconnection of both residential and commercial customers in the secondary networks at a time when there are record numbers of interconnection requests by utilities' customers. The authors analyse the limitations on HC due to transformer loading and degradation considerations. Then, the paper proposes a battery energy storage system (BESS) dispatch strategy that will mitigate the limitation on distribution feeder HC by distribution transformers. Three scenarios of HC were simulated for a test network—HC evaluation without restrictions by the distribution transformer (scenario 1), HC evaluation with restrictions by the distribution transformer (scenario 2), and HC evaluation without restriction by the distribution transformer, and with the implementation of the proposed BESS mitigation strategy (scenario 3). Simulation results show that transformer lifetime is depleted to about 6% of expected lifetime for unrestricted HC in scenario 1. Curtailing the HC by 32% in scenario 2 improves the lifetime to 149% of expected lifetime. Implementing the proposed BESS in scenario 3 improves the transformer lifetime to 127% and increases the HC by 62% above the curtailed value in scenario 2, and by 10% above the original HC in scenario 1. The BESS strategy implementation produced cost savings of 49% and 27% of the transformer cost in scenarios 2 and 3, respectively, due to deferred transformer replacement. Conversely, there is a 1600% replacement cost incurred in scenario 1, which underscores the need for a mitigation strategy. The proposed BESS strategy does not only improve the HC of a distribution feeder but also increases a distribution transformer's lifetime leading to replacement cost savings.","PeriodicalId":33288,"journal":{"name":"IET Energy Systems Integration","volume":null,"pages":null},"PeriodicalIF":1.6000,"publicationDate":"2024-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Mitigation of limitation imposed on hosting capacity in low voltage networks by their distribution transformer loading and degradation considerations\",\"authors\":\"Agaba Ame‐Oko, Olga Lavrova\",\"doi\":\"10.1049/esi2.12143\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A distribution transformer's thermal operating conditions can impose a limitation on the Hosting Capacity (HC) of an electrical distribution feeder for PV interconnections in the feeder's low‐voltage network. This is undesirable as it curtails PV interconnection of both residential and commercial customers in the secondary networks at a time when there are record numbers of interconnection requests by utilities' customers. The authors analyse the limitations on HC due to transformer loading and degradation considerations. Then, the paper proposes a battery energy storage system (BESS) dispatch strategy that will mitigate the limitation on distribution feeder HC by distribution transformers. Three scenarios of HC were simulated for a test network—HC evaluation without restrictions by the distribution transformer (scenario 1), HC evaluation with restrictions by the distribution transformer (scenario 2), and HC evaluation without restriction by the distribution transformer, and with the implementation of the proposed BESS mitigation strategy (scenario 3). Simulation results show that transformer lifetime is depleted to about 6% of expected lifetime for unrestricted HC in scenario 1. Curtailing the HC by 32% in scenario 2 improves the lifetime to 149% of expected lifetime. Implementing the proposed BESS in scenario 3 improves the transformer lifetime to 127% and increases the HC by 62% above the curtailed value in scenario 2, and by 10% above the original HC in scenario 1. The BESS strategy implementation produced cost savings of 49% and 27% of the transformer cost in scenarios 2 and 3, respectively, due to deferred transformer replacement. Conversely, there is a 1600% replacement cost incurred in scenario 1, which underscores the need for a mitigation strategy. The proposed BESS strategy does not only improve the HC of a distribution feeder but also increases a distribution transformer's lifetime leading to replacement cost savings.\",\"PeriodicalId\":33288,\"journal\":{\"name\":\"IET Energy Systems Integration\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":1.6000,\"publicationDate\":\"2024-03-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"IET Energy Systems Integration\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1049/esi2.12143\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"ENERGY & FUELS\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"IET Energy Systems Integration","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1049/esi2.12143","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENERGY & FUELS","Score":null,"Total":0}
引用次数: 0
摘要
配电变压器的热运行条件可能会限制配电馈线的寄存容量 (HC),从而影响馈线低压网络中的光伏互联。这是不可取的,因为在公用事业公司客户的互联请求数量创下新高的时候,它却限制了住宅和商业客户在二次网络中的光伏互联。作者分析了变压器负载和降解因素对 HC 的限制。然后,论文提出了一种电池储能系统 (BESS) 调度策略,该策略将减轻配电变压器对配电馈线 HC 的限制。本文模拟了测试网络的三种 HC 情景:不受配电变压器限制的 HC 评估(情景 1)、受配电变压器限制的 HC 评估(情景 2)、不受配电变压器限制的 HC 评估以及实施所建议的 BESS 缓解策略后的 HC 评估(情景 3)。仿真结果表明,在方案 1 中,如果不限制 HC,变压器寿命将缩短至预期寿命的 6%左右。在方案 2 中,减少 32% 的碳氢化合物可将寿命提高到预期寿命的 149%。在方案 3 中实施拟议的 BESS,可将变压器寿命延长至 127%,并使 HC 比方案 2 中的削减值增加 62%,比方案 1 中的原始 HC 增加 10%。在方案 2 和方案 3 中,由于推迟了变压器的更换,BESS 战略的实施分别节省了 49% 和 27% 的变压器成本。相反,在方案 1 中,更换变压器的成本增加了 1600%,这说明需要采取缓解战略。拟议的 BESS 战略不仅能提高配电馈线的 HC 值,还能延长配电变压器的使用寿命,从而节省更换成本。
Mitigation of limitation imposed on hosting capacity in low voltage networks by their distribution transformer loading and degradation considerations
A distribution transformer's thermal operating conditions can impose a limitation on the Hosting Capacity (HC) of an electrical distribution feeder for PV interconnections in the feeder's low‐voltage network. This is undesirable as it curtails PV interconnection of both residential and commercial customers in the secondary networks at a time when there are record numbers of interconnection requests by utilities' customers. The authors analyse the limitations on HC due to transformer loading and degradation considerations. Then, the paper proposes a battery energy storage system (BESS) dispatch strategy that will mitigate the limitation on distribution feeder HC by distribution transformers. Three scenarios of HC were simulated for a test network—HC evaluation without restrictions by the distribution transformer (scenario 1), HC evaluation with restrictions by the distribution transformer (scenario 2), and HC evaluation without restriction by the distribution transformer, and with the implementation of the proposed BESS mitigation strategy (scenario 3). Simulation results show that transformer lifetime is depleted to about 6% of expected lifetime for unrestricted HC in scenario 1. Curtailing the HC by 32% in scenario 2 improves the lifetime to 149% of expected lifetime. Implementing the proposed BESS in scenario 3 improves the transformer lifetime to 127% and increases the HC by 62% above the curtailed value in scenario 2, and by 10% above the original HC in scenario 1. The BESS strategy implementation produced cost savings of 49% and 27% of the transformer cost in scenarios 2 and 3, respectively, due to deferred transformer replacement. Conversely, there is a 1600% replacement cost incurred in scenario 1, which underscores the need for a mitigation strategy. The proposed BESS strategy does not only improve the HC of a distribution feeder but also increases a distribution transformer's lifetime leading to replacement cost savings.