{"title":"Mixed Integer Linear Programming Model for Monthly Unit Commitment in the National Level Power System","authors":"H. Truong, C. Jeenanunta","doi":"10.1109/ICITEED.2019.8930000","DOIUrl":null,"url":null,"abstract":"In electrical power system, unit commitment is a fundamental problem for power system planning which aims to maintain electricity production continuously and respond the electricity consumption during every time interval of the scheduling horizon. For long-term operational planning, monthly unit commitment is especially concerned to optimally implement due to the adequate fuel provision for the available generating units over a month. In this study, optimizing the commitment with fuel limitation, daily peak load demand, and operational conditions for a month is considered. Accordingly, a mixed integer linear programming model is proposed with objective to ensure a sufficiency of fuel for the whole month, satisfying the total energy and covering the daily peak load demand with respecting to many operational constraints. The model is applied to a national level planning in Thailand power system which consists of various generator types including thermal, single-shaft gas turbine (SSGT), hydropower, combined-cycle-system gas turbine (CCGT), combined-cyclesystem steam turbine (CCST), and imported power which are purchased and supplied abroad. Simultaneously, development planning is examined and analyzed to reveal a generating unit status, producing output of each generator and fuel usage. Regarding the results, the decision makers can practically execute for scenario analysis of a variety of demand and fuel availability.","PeriodicalId":6598,"journal":{"name":"2019 11th International Conference on Information Technology and Electrical Engineering (ICITEE)","volume":"13 2 1","pages":"1-6"},"PeriodicalIF":0.0000,"publicationDate":"2019-10-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2019 11th International Conference on Information Technology and Electrical Engineering (ICITEE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICITEED.2019.8930000","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2
Abstract
In electrical power system, unit commitment is a fundamental problem for power system planning which aims to maintain electricity production continuously and respond the electricity consumption during every time interval of the scheduling horizon. For long-term operational planning, monthly unit commitment is especially concerned to optimally implement due to the adequate fuel provision for the available generating units over a month. In this study, optimizing the commitment with fuel limitation, daily peak load demand, and operational conditions for a month is considered. Accordingly, a mixed integer linear programming model is proposed with objective to ensure a sufficiency of fuel for the whole month, satisfying the total energy and covering the daily peak load demand with respecting to many operational constraints. The model is applied to a national level planning in Thailand power system which consists of various generator types including thermal, single-shaft gas turbine (SSGT), hydropower, combined-cycle-system gas turbine (CCGT), combined-cyclesystem steam turbine (CCST), and imported power which are purchased and supplied abroad. Simultaneously, development planning is examined and analyzed to reveal a generating unit status, producing output of each generator and fuel usage. Regarding the results, the decision makers can practically execute for scenario analysis of a variety of demand and fuel availability.