{"title":"电力系统中发电机组检修调度","authors":"M. Kotb","doi":"10.1109/MEPCON.2008.4562373","DOIUrl":null,"url":null,"abstract":"New method for solving the maintenance schedule (MS) problem is proposed. Comparative study has been introduced between the proposed method and the other heuristic methods for (MS) for electric generation units. The study was implemented and tested on a model for MS problem. The new model introduces the ratio between cost per reserve power as an index to maximize the system's net reserve with minimum cost. Also, maximizing the net reserve , maximizing the system's net reserve rate and minimizing the system's risk methods were implemented and compared with the proposed method. All methods are subjected to the following constraints: generator unit maintenance duration, time constraint, crew availability, lower reserve limit and lower reserve rate limit.","PeriodicalId":236620,"journal":{"name":"2008 12th International Middle-East Power System Conference","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2008-03-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":"{\"title\":\"Maintenance scheduling of generating units in electric power system\",\"authors\":\"M. Kotb\",\"doi\":\"10.1109/MEPCON.2008.4562373\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"New method for solving the maintenance schedule (MS) problem is proposed. Comparative study has been introduced between the proposed method and the other heuristic methods for (MS) for electric generation units. The study was implemented and tested on a model for MS problem. The new model introduces the ratio between cost per reserve power as an index to maximize the system's net reserve with minimum cost. Also, maximizing the net reserve , maximizing the system's net reserve rate and minimizing the system's risk methods were implemented and compared with the proposed method. All methods are subjected to the following constraints: generator unit maintenance duration, time constraint, crew availability, lower reserve limit and lower reserve rate limit.\",\"PeriodicalId\":236620,\"journal\":{\"name\":\"2008 12th International Middle-East Power System Conference\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2008-03-12\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"5\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2008 12th International Middle-East Power System Conference\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/MEPCON.2008.4562373\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2008 12th International Middle-East Power System Conference","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/MEPCON.2008.4562373","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5

摘要

提出了解决维修计划问题的新方法。并将该方法与其他启发式方法进行了比较研究。该研究在MS问题模型上进行了实施和测试。该模型引入了每备用功率成本之比作为指标,以最小成本最大化系统的净备用。实现了净准备金最大化、系统净准备金率最大化和系统风险最小化方法,并与所提方法进行了比较。所有方法都受到以下约束:发电机组维修时间、时间约束、机组可用性、备用下限和备用速率下限。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Maintenance scheduling of generating units in electric power system
New method for solving the maintenance schedule (MS) problem is proposed. Comparative study has been introduced between the proposed method and the other heuristic methods for (MS) for electric generation units. The study was implemented and tested on a model for MS problem. The new model introduces the ratio between cost per reserve power as an index to maximize the system's net reserve with minimum cost. Also, maximizing the net reserve , maximizing the system's net reserve rate and minimizing the system's risk methods were implemented and compared with the proposed method. All methods are subjected to the following constraints: generator unit maintenance duration, time constraint, crew availability, lower reserve limit and lower reserve rate limit.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Implementing distributed generation to mitigate under-frequency load shedding Generation coordination for transient stability enhancement using particle swarm optimization Modeling and simulation of Photovoltaic/Wind Hybrid Electric Power System Interconnected with electrical utility Space-charge measurement in composite dielectrics Design of the instrument current transformer for high frequency high power applications
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1