Floating Casings in 10,000ft Laterals with MPD in Haynesville

Harshad Patil, E. Dietrich, Ian Knight, Greg Matherne, Svein Hovland
{"title":"Floating Casings in 10,000ft Laterals with MPD in Haynesville","authors":"Harshad Patil, E. Dietrich, Ian Knight, Greg Matherne, Svein Hovland","doi":"10.2118/210554-ms","DOIUrl":null,"url":null,"abstract":"\n This paper highlights a case study where MPD (Managed Pressure Drilling) techniques were utilized while floating long string casings in the 10,000ft laterals in the Haynesville, saving the client more than 30-40% of rig time. The challenges encompassing the events that cause casing floating equipment conversion, either due to excessive gas, flow out from well or drag, are illustrated herein. This paper demonstrates the specific MPD techniques which facilitated floating casing to TD (Target Depth) and prevent its untimely conversion. The use of unique MPD methods illustrated herein enabled prevention of excess gas, hole collapse and situations relating to ballooning which enabled floating the casing to TD.\n These MPD methods helped reduce casing running times from 34-48hrs to 24-27hrs and prevented shut-in or \"stop & circulate\" scenarios during running casing. These shut-ins and/or \"stop & circulate\" scenarios were largely caused by increased flow out readings as the gas expanded at surface along with indications of well ballooning. Ballooning scenarios were later found to be associated with high surge pressures and higher SBP required to mitigate gas at surface. A holistic approach was taken to identify methods to mitigate such events. It was obvious that MPD pressures had to be manipulated for managing surge to mitigate ballooning, but excessive trip gas which necessitated higher MPD pressures while running casing had to be primarily evaluated. It was later found that excessive gas in these 10,000ft laterals were not just a function of swabbing pressures while POOH (pulling out of hole) with BHA (Bottomhole Assembly), but also related to POOH practices and methods which affected wellbore stability.\n To enable floating casing all the way to TD, first the MPD pressures and bottoms-up circulation strategy while POOH with BHA were analyzed and modified for the client. Second, the MPD balanced pill volume (which is typically spotted in the vertical) and its spotting procedure/calculations were revised to ensure minimizing gas encroachment and migration in vertical hole section. The design of this balanced pill accommodated automatic heavy pill displacement out of the well without the need for stopping and circulating pill while running casing. And third, the MPD control system was modified to automatically manipulate the MPD pressures as the casing was lowered to manage surge and prevent losses/ballooning. This paper illustrates how all of these methods enabled floating the casing in 10,000ft lateral in Haynesville.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"20 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Wed, September 28, 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/210554-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This paper highlights a case study where MPD (Managed Pressure Drilling) techniques were utilized while floating long string casings in the 10,000ft laterals in the Haynesville, saving the client more than 30-40% of rig time. The challenges encompassing the events that cause casing floating equipment conversion, either due to excessive gas, flow out from well or drag, are illustrated herein. This paper demonstrates the specific MPD techniques which facilitated floating casing to TD (Target Depth) and prevent its untimely conversion. The use of unique MPD methods illustrated herein enabled prevention of excess gas, hole collapse and situations relating to ballooning which enabled floating the casing to TD. These MPD methods helped reduce casing running times from 34-48hrs to 24-27hrs and prevented shut-in or "stop & circulate" scenarios during running casing. These shut-ins and/or "stop & circulate" scenarios were largely caused by increased flow out readings as the gas expanded at surface along with indications of well ballooning. Ballooning scenarios were later found to be associated with high surge pressures and higher SBP required to mitigate gas at surface. A holistic approach was taken to identify methods to mitigate such events. It was obvious that MPD pressures had to be manipulated for managing surge to mitigate ballooning, but excessive trip gas which necessitated higher MPD pressures while running casing had to be primarily evaluated. It was later found that excessive gas in these 10,000ft laterals were not just a function of swabbing pressures while POOH (pulling out of hole) with BHA (Bottomhole Assembly), but also related to POOH practices and methods which affected wellbore stability. To enable floating casing all the way to TD, first the MPD pressures and bottoms-up circulation strategy while POOH with BHA were analyzed and modified for the client. Second, the MPD balanced pill volume (which is typically spotted in the vertical) and its spotting procedure/calculations were revised to ensure minimizing gas encroachment and migration in vertical hole section. The design of this balanced pill accommodated automatic heavy pill displacement out of the well without the need for stopping and circulating pill while running casing. And third, the MPD control system was modified to automatically manipulate the MPD pressures as the casing was lowered to manage surge and prevent losses/ballooning. This paper illustrates how all of these methods enabled floating the casing in 10,000ft lateral in Haynesville.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
在Haynesville的10000英尺水平段使用MPD进行浮动套管
本文重点介绍了一个案例研究,该案例在Haynesville的10,000英尺水平段中,将MPD(控压钻井)技术应用于浮式长管柱套管,为客户节省了30-40%以上的钻机时间。包括导致套管浮式设备转换的事件的挑战,无论是由于过多的气体,从井中流出还是阻力,都在这里进行了说明。本文介绍了一种特殊的MPD技术,可以使浮式套管达到目标深度,并防止其过早转换。使用独特的MPD方法可以防止过量气体、井眼坍塌以及与膨胀相关的情况,从而使套管浮至TD。这些MPD方法将套管的运行时间从34-48小时减少到24-27小时,并防止了套管运行过程中的关井或“停止循环”情况。这些关井和/或“停止循环”的情况主要是由于地面气体膨胀和井膨胀迹象导致流出读数增加造成的。后来发现,膨胀情景与高浪涌压力和更高的SBP有关,以缓解地面的气体。采取了一种整体方法来确定减轻此类事件的方法。很明显,必须控制MPD压力来控制涌波,以减轻膨胀,但在下入套管时,由于下入气体过多,需要更高的MPD压力,因此必须首先进行评估。后来发现,在10000英尺的水平段中,过量的气体不仅与底部钻具组合(BHA)的抽汲压力有关,还与影响井筒稳定性的POOH操作和方法有关。为了使浮动套管能够一直下至TD,首先为客户分析了MPD压力和底部向上循环策略,并对POOH与BHA进行了修改。其次,对MPD平衡丸体积(通常在垂直井段进行定位)及其定位程序/计算进行了修改,以确保最大限度地减少垂直井段的气体侵入和运移。这种平衡丸的设计可以自动将重丸排出井外,而无需在下套管时停止和循环丸。第三,MPD控制系统经过改进,可以在下放套管时自动控制MPD压力,以控制井喷,防止漏失/膨胀。本文阐述了所有这些方法是如何在Haynesville的10,000英尺水平段浮起套管的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
First Implementation of Managed Pressure Drilling (MPD) System in Swamp Barge Rig to Drill Narrow Pressure Window HPHT Exploration Well Safely – Return of Experience from Kalimantan, Indonesia Floating Casings in 10,000ft Laterals with MPD in Haynesville A New Approach for Designing an Underbalanced Cementing Plug Using a Managed Pressure Cementing and Pump-Pull Method with Narrow Pore-Frac Pressure Window in HPHT Exploration Well: An Offshore East Kalimantan, Indonesia Case Study Fingerprinting Formation Breathing and Wellbore Ballooning: Getting Mixed Signals Pressurized Mud Cap Drilling Used to Drill and Complete Carbonate Gas Reservoir with Poor Injectivity and Severe Dynamic Losses Offshore Malaysia
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1