首页 > 最新文献

Day 2 Wed, September 28, 2022最新文献

英文 中文
A New Approach for Designing an Underbalanced Cementing Plug Using a Managed Pressure Cementing and Pump-Pull Method with Narrow Pore-Frac Pressure Window in HPHT Exploration Well: An Offshore East Kalimantan, Indonesia Case Study 在高压高压探井中采用控压固井和窄孔压裂压力窗泵拉法设计欠平衡固井塞的新方法:印度尼西亚东加里曼丹海上案例研究
Pub Date : 2022-09-27 DOI: 10.2118/210539-ms
_. Setiohadi, Praja Hadistira, Muhammad Alfianoor Yudhatama, Daniel Sitompul, Dhika Escodianto Hutabarat, Andre Wiharja, R. Panjaitan, C. Agriawan, R. Kusumawatie, V. R. Wedhaswari, Bagus Setyo Darmanto, A. Osman, C. Azwar, Wiwin Winarti, Andre Simanjuntak
The operator was drilling their first high-pressure high-temperature (HPHT) exploration well with narrow pressure window in a swamp area of East Kalimantan. The gas field was discovered in 1977 and production started in 1990. Since then, more than 1500 wells have been drilled in this area yielding a total gas production of 9.7 Tcf. Currently T field enters established mature field status which has quite marginal reserves. Therefore, further exploration is seen as one of the solutions to locate additional reserves to enhance overall gas production. The well was drilled directionally with no offset well nearby. While drilling the 6-in open hole section, an unexpected high-pressure zone was penetrated. The zone condition was made worse by lost circulation and a high gas reading. Two cement plugs were placed using a managed pressure cementing with pump and pull method. The first plug was set by applying surface back pressure (SBP) to maintain equivalent bottom hole pressure (BHP) between lowermost pore pressure (PP) and fracture gradient (FG) at the previous shoe. After pumping 1 m3 of cement into the annulus, pump and pull operations commenced. While performing post job circulation on the first plug, it was observed that the returned fluid density at surface was less than original mud weight, indicating the possibility of contaminant invasion from formation. After waiting for the cement to reach 500 psi compressive strength, pressure buildup was observed when annulus was shut-in, indicating an inadequate pressure seal across the cement plug Applying lessons learned from setting the first plug, new design considerations were implemented such as increasing cement volume in the annulus to 4 m3 prior to the pump and pull operation to minimize cement overlapping risk and applying SBP at BHP near FG. A contingency plan was in place to determine the appropriate SBP value to be applied whenever the pumping rate was changed. A second plug job was performed safely and flawlessly by achieving the top of cement as desired. A successful inflow test was performed with indication of no contaminant invasion nor pressure bypass around the cement plug. The rig was able to continue its next operation to sidetrack the well. This paper presents the design considerations, methodology applied, and lessons learned two managed pressure cement plugs using pump and pull method in a well bore with a narrow pore-frac window where the new techniques were implemented to enhance success of the plug job despite the complexity and risk inherent with an underbalanced operation.
该公司在东加里曼丹的沼泽地区钻了他们的第一口高压高温(HPHT)探井,该探井具有狭窄的压力窗口。该气田于1977年被发现,1990年开始生产。从那时起,该地区已经钻了1500多口井,总天然气产量为9.7万亿立方英尺。目前T油田已进入成熟油田状态,储量相当边际。因此,进一步勘探被视为寻找额外储量以提高整体天然气产量的解决方案之一。该井是定向钻井,附近没有邻井。在钻6英寸裸眼井段时,意外地钻入了一个高压区域。漏失和高气体读数使储层状况变得更糟。使用泵拉控压固井方法放置了两个水泥塞。第一个桥塞是通过施加地面背压(SBP)来坐封的,以保持上一个鞋的最低孔隙压力(PP)和裂缝梯度(FG)之间的等效井底压力(BHP)。将1m3的水泥泵入环空后,开始泵拔作业。在对第一个桥塞进行作业后循环时,观察到地面返回的流体密度小于原始泥浆重量,这表明可能有污染物从地层侵入。在等待水泥达到500psi的抗压强度后,在环空关井时观察到压力增加,表明水泥塞的压力密封不足,根据第一次封井的经验教训,实施了新的设计考虑,例如在泵拔作业之前将环空的水泥体积增加到4m3,以尽量减少水泥重叠风险,并在FG附近的BHP使用SBP。制定了应急计划,以便在泵速发生变化时确定适当的收缩压值。第二次封井作业安全、完美地完成了水泥的顶部。进行了一次成功的流入测试,表明没有污染物侵入,水泥塞周围也没有压力旁路。该钻机能够继续进行下一个侧钻作业。本文介绍了在窄孔压裂窗口井眼中使用泵拉法控制压力水泥塞的设计考虑、应用方法和经验教训,尽管不平衡作业固有的复杂性和风险,但新技术的应用提高了水泥塞作业的成功率。
{"title":"A New Approach for Designing an Underbalanced Cementing Plug Using a Managed Pressure Cementing and Pump-Pull Method with Narrow Pore-Frac Pressure Window in HPHT Exploration Well: An Offshore East Kalimantan, Indonesia Case Study","authors":"_. Setiohadi, Praja Hadistira, Muhammad Alfianoor Yudhatama, Daniel Sitompul, Dhika Escodianto Hutabarat, Andre Wiharja, R. Panjaitan, C. Agriawan, R. Kusumawatie, V. R. Wedhaswari, Bagus Setyo Darmanto, A. Osman, C. Azwar, Wiwin Winarti, Andre Simanjuntak","doi":"10.2118/210539-ms","DOIUrl":"https://doi.org/10.2118/210539-ms","url":null,"abstract":"\u0000 The operator was drilling their first high-pressure high-temperature (HPHT) exploration well with narrow pressure window in a swamp area of East Kalimantan. The gas field was discovered in 1977 and production started in 1990. Since then, more than 1500 wells have been drilled in this area yielding a total gas production of 9.7 Tcf. Currently T field enters established mature field status which has quite marginal reserves. Therefore, further exploration is seen as one of the solutions to locate additional reserves to enhance overall gas production. The well was drilled directionally with no offset well nearby. While drilling the 6-in open hole section, an unexpected high-pressure zone was penetrated. The zone condition was made worse by lost circulation and a high gas reading.\u0000 Two cement plugs were placed using a managed pressure cementing with pump and pull method. The first plug was set by applying surface back pressure (SBP) to maintain equivalent bottom hole pressure (BHP) between lowermost pore pressure (PP) and fracture gradient (FG) at the previous shoe. After pumping 1 m3 of cement into the annulus, pump and pull operations commenced. While performing post job circulation on the first plug, it was observed that the returned fluid density at surface was less than original mud weight, indicating the possibility of contaminant invasion from formation. After waiting for the cement to reach 500 psi compressive strength, pressure buildup was observed when annulus was shut-in, indicating an inadequate pressure seal across the cement plug\u0000 Applying lessons learned from setting the first plug, new design considerations were implemented such as increasing cement volume in the annulus to 4 m3 prior to the pump and pull operation to minimize cement overlapping risk and applying SBP at BHP near FG. A contingency plan was in place to determine the appropriate SBP value to be applied whenever the pumping rate was changed. A second plug job was performed safely and flawlessly by achieving the top of cement as desired. A successful inflow test was performed with indication of no contaminant invasion nor pressure bypass around the cement plug. The rig was able to continue its next operation to sidetrack the well.\u0000 This paper presents the design considerations, methodology applied, and lessons learned two managed pressure cement plugs using pump and pull method in a well bore with a narrow pore-frac window where the new techniques were implemented to enhance success of the plug job despite the complexity and risk inherent with an underbalanced operation.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"92 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"126212663","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Bridging the Gap: Highly Depleted Reservoir Entry in a Mature HPHT Field 弥合差距:成熟高温高压油田的高衰竭油藏入口
Pub Date : 2022-09-27 DOI: 10.2118/210543-ms
Michael Cadd, Susannah Stott, R. Graham, Ryan Nowell, Josef Schachner
This case study shows how three highly depleted reservoirs with large negative drilling windows, previously considered un-drillable, were safely entered by combining Managed Pressure Drilling (MPD) and drill-in liner technologies with a novel losses response strategy. The challenge was to bridge the gap between the high pore pressure overburden and the low fracture strength reservoir. The reservoir had been depleted by some 12,000psi since production started, creating a 3,000psi negative drilling window. Conventional strategies to prevent losses were deemed unlikely to succeed, and the focus was instead on how best to respond to the near-inevitable onset of total losses. The gap was bridged using a low static mud weight in combination with high applied surface back pressure to give an Equivalent Mud Weight (EMW) suitable for the high-pressure overburden, whilst allowing immediate reduction in bottom hole pressure in the event of total losses on entry into the weakened reservoir. Endurance testing allowed the MPD equipment to be operated outside of its normal pressure envelope. In the reference case, losses would be managed by reducing Surface Back Pressure (SBP) while continuing to drill ahead. In the low-pressure case, Pressurised Mud Cap Drilling (PMCD) would be used to bullhead the well to a lighter mud while drilling ahead, before restoring returns. A contingency plan was in place for managing elevated gas levels in the returns, which was anticipated following a large reduction of bottom hole pressure across the overburden shales. In the extreme case where high gas levels from the shales prevented bringing returns to surface, cementing would also be carried out in Pressurised Mud Cap mode. A drill-in liner was used because many of the scenarios would not permit safe tripping and Wellbore Strengthening material was included in the mud in an attempt to reduce the severity of the losses. Total losses were seen on two of the three wells, and all three wells were successfully completed. This paper will discuss the technology and techniques used along with the planning and procedures required to enable successful well construction in this challenging environment.
本案例研究展示了如何将控压钻井(MPD)和尾管钻进技术与一种新的漏失响应策略相结合,安全地进入三个高度枯竭的储层,这些储层具有较大的负钻井窗口,以前被认为是不可钻的。挑战在于如何在高孔隙压力覆盖层和低断裂强度储层之间架起桥梁。自生产开始以来,储层已经枯竭了约12,000psi,造成了3,000psi的负钻井窗口。防止损失的传统策略被认为不太可能成功,取而代之的是,重点是如何最好地应对几乎不可避免的全面损失。利用较低的静泥浆比重和较高的地面背压来填补裂缝,从而获得适用于高压覆盖层的等效泥浆比重(EMW),同时在进入弱储层时,如果发生完全漏失,可以立即降低井底压力。耐久性测试允许MPD设备在正常压力范围外运行。在参考案例中,在继续钻进的同时,可以通过降低地面背压(SBP)来控制漏失。在低压情况下,加压泥浆帽钻井(PMCD)将在钻井前将井顶压至较轻的泥浆,然后再恢复产量。在覆盖层页岩的井底压力大幅降低后,预计会出现井底压力升高的情况,因此制定了应急计划来管理回采过程中天然气含量升高的情况。在极端情况下,当页岩气含量过高,无法将井底返至地面时,也可以采用加压泥浆帽模式进行固井。由于许多情况不允许安全起下钻,因此使用了钻入尾管,并且在泥浆中加入了井眼强化材料,以减少漏失的严重程度。三口井中有两口出现了漏失,三口井均成功完井。本文将讨论在这种充满挑战的环境中成功建井所需的技术和工艺以及规划和程序。
{"title":"Bridging the Gap: Highly Depleted Reservoir Entry in a Mature HPHT Field","authors":"Michael Cadd, Susannah Stott, R. Graham, Ryan Nowell, Josef Schachner","doi":"10.2118/210543-ms","DOIUrl":"https://doi.org/10.2118/210543-ms","url":null,"abstract":"\u0000 This case study shows how three highly depleted reservoirs with large negative drilling windows, previously considered un-drillable, were safely entered by combining Managed Pressure Drilling (MPD) and drill-in liner technologies with a novel losses response strategy.\u0000 The challenge was to bridge the gap between the high pore pressure overburden and the low fracture strength reservoir. The reservoir had been depleted by some 12,000psi since production started, creating a 3,000psi negative drilling window. Conventional strategies to prevent losses were deemed unlikely to succeed, and the focus was instead on how best to respond to the near-inevitable onset of total losses. The gap was bridged using a low static mud weight in combination with high applied surface back pressure to give an Equivalent Mud Weight (EMW) suitable for the high-pressure overburden, whilst allowing immediate reduction in bottom hole pressure in the event of total losses on entry into the weakened reservoir. Endurance testing allowed the MPD equipment to be operated outside of its normal pressure envelope. In the reference case, losses would be managed by reducing Surface Back Pressure (SBP) while continuing to drill ahead. In the low-pressure case, Pressurised Mud Cap Drilling (PMCD) would be used to bullhead the well to a lighter mud while drilling ahead, before restoring returns. A contingency plan was in place for managing elevated gas levels in the returns, which was anticipated following a large reduction of bottom hole pressure across the overburden shales. In the extreme case where high gas levels from the shales prevented bringing returns to surface, cementing would also be carried out in Pressurised Mud Cap mode. A drill-in liner was used because many of the scenarios would not permit safe tripping and Wellbore Strengthening material was included in the mud in an attempt to reduce the severity of the losses.\u0000 Total losses were seen on two of the three wells, and all three wells were successfully completed. This paper will discuss the technology and techniques used along with the planning and procedures required to enable successful well construction in this challenging environment.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"1 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"129616771","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Fingerprinting Formation Breathing and Wellbore Ballooning: Getting Mixed Signals 指纹识别地层呼吸和井筒膨胀:获得混合信号
Pub Date : 2022-09-27 DOI: 10.2118/210548-ms
P. Gunn, Maria Retuta
The use of Managed Pressure Drilling (MPD) techniques allows the rapid differentiation of formation breathing or wellbore ballooning from a gas kick through a series of quick shut-in, build-up and flowback tests. These tests have proven to reduce uncertainty, NPT, and total drilling time by ensuring that operations do not enter secondary well control after mistaking flowback for a kick. Such tests provide definitive results when done correctly. However, when performed incorrectly, the wellbore response can appear either ambiguous or indicative of a kick. When done correctly, the ballooning test shows dissipation in both pressure build-up and flowback over time. However, when done incorrectly, both pressure and flowback can appear to gain drive. This is caused by induced losses being allowed to start equalizing with the wellbore with significant flowback volume prior to beginning the shut-in, build-up and flowback testing. As a result, ballooning testing can show classic signs of a gas kick as increasing pressure and flowback is observed or ambiguous results from the rising and then falling pressure and flowback. This can necessitate some combination of entering costly secondary well control and the need to trip back in to circulate bottoms up only to observe minimal signs of reservoir fluids. This paper presents type modelling that accounts for the observed unexpected results and reiterates rigid testing parameters for the successful implementation of diagnostic testing.
使用控压钻井(MPD)技术,可以通过一系列快速关井、堆积和返排测试,快速区分地层呼吸或井筒膨胀与气涌。这些测试已经证明,通过确保作业不会在误将返排视为井涌后进入二次井控,减少了不确定性、NPT和总钻井时间。如果操作正确,这些测试可提供明确的结果。然而,如果操作不当,井眼响应可能不明确,也可能表明存在井涌。当操作正确时,气球测试显示随着时间的推移,压力积聚和反排都在消散。然而,如果操作不当,压力和反排都可能获得动力。这是由于在开始关井、建井和反排测试之前,允许诱导损失开始与井筒平衡,并产生大量返排量。因此,当观察到压力增加和返排时,球囊测试可以显示气涌的典型迹象,或者从压力上升和下降以及返排中得到模糊的结果。这可能需要进行昂贵的二次井控,并且需要回钻循环,以观察到最小的储层流体迹象。本文提出了类型建模,说明了观察到的意外结果,并重申了诊断测试成功实施的刚性测试参数。
{"title":"Fingerprinting Formation Breathing and Wellbore Ballooning: Getting Mixed Signals","authors":"P. Gunn, Maria Retuta","doi":"10.2118/210548-ms","DOIUrl":"https://doi.org/10.2118/210548-ms","url":null,"abstract":"\u0000 The use of Managed Pressure Drilling (MPD) techniques allows the rapid differentiation of formation breathing or wellbore ballooning from a gas kick through a series of quick shut-in, build-up and flowback tests. These tests have proven to reduce uncertainty, NPT, and total drilling time by ensuring that operations do not enter secondary well control after mistaking flowback for a kick. Such tests provide definitive results when done correctly. However, when performed incorrectly, the wellbore response can appear either ambiguous or indicative of a kick.\u0000 When done correctly, the ballooning test shows dissipation in both pressure build-up and flowback over time. However, when done incorrectly, both pressure and flowback can appear to gain drive. This is caused by induced losses being allowed to start equalizing with the wellbore with significant flowback volume prior to beginning the shut-in, build-up and flowback testing.\u0000 As a result, ballooning testing can show classic signs of a gas kick as increasing pressure and flowback is observed or ambiguous results from the rising and then falling pressure and flowback. This can necessitate some combination of entering costly secondary well control and the need to trip back in to circulate bottoms up only to observe minimal signs of reservoir fluids. This paper presents type modelling that accounts for the observed unexpected results and reiterates rigid testing parameters for the successful implementation of diagnostic testing.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"1 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"128366040","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
Floating Casings in 10,000ft Laterals with MPD in Haynesville 在Haynesville的10000英尺水平段使用MPD进行浮动套管
Pub Date : 2022-09-27 DOI: 10.2118/210554-ms
Harshad Patil, E. Dietrich, Ian Knight, Greg Matherne, Svein Hovland
This paper highlights a case study where MPD (Managed Pressure Drilling) techniques were utilized while floating long string casings in the 10,000ft laterals in the Haynesville, saving the client more than 30-40% of rig time. The challenges encompassing the events that cause casing floating equipment conversion, either due to excessive gas, flow out from well or drag, are illustrated herein. This paper demonstrates the specific MPD techniques which facilitated floating casing to TD (Target Depth) and prevent its untimely conversion. The use of unique MPD methods illustrated herein enabled prevention of excess gas, hole collapse and situations relating to ballooning which enabled floating the casing to TD. These MPD methods helped reduce casing running times from 34-48hrs to 24-27hrs and prevented shut-in or "stop & circulate" scenarios during running casing. These shut-ins and/or "stop & circulate" scenarios were largely caused by increased flow out readings as the gas expanded at surface along with indications of well ballooning. Ballooning scenarios were later found to be associated with high surge pressures and higher SBP required to mitigate gas at surface. A holistic approach was taken to identify methods to mitigate such events. It was obvious that MPD pressures had to be manipulated for managing surge to mitigate ballooning, but excessive trip gas which necessitated higher MPD pressures while running casing had to be primarily evaluated. It was later found that excessive gas in these 10,000ft laterals were not just a function of swabbing pressures while POOH (pulling out of hole) with BHA (Bottomhole Assembly), but also related to POOH practices and methods which affected wellbore stability. To enable floating casing all the way to TD, first the MPD pressures and bottoms-up circulation strategy while POOH with BHA were analyzed and modified for the client. Second, the MPD balanced pill volume (which is typically spotted in the vertical) and its spotting procedure/calculations were revised to ensure minimizing gas encroachment and migration in vertical hole section. The design of this balanced pill accommodated automatic heavy pill displacement out of the well without the need for stopping and circulating pill while running casing. And third, the MPD control system was modified to automatically manipulate the MPD pressures as the casing was lowered to manage surge and prevent losses/ballooning. This paper illustrates how all of these methods enabled floating the casing in 10,000ft lateral in Haynesville.
本文重点介绍了一个案例研究,该案例在Haynesville的10,000英尺水平段中,将MPD(控压钻井)技术应用于浮式长管柱套管,为客户节省了30-40%以上的钻机时间。包括导致套管浮式设备转换的事件的挑战,无论是由于过多的气体,从井中流出还是阻力,都在这里进行了说明。本文介绍了一种特殊的MPD技术,可以使浮式套管达到目标深度,并防止其过早转换。使用独特的MPD方法可以防止过量气体、井眼坍塌以及与膨胀相关的情况,从而使套管浮至TD。这些MPD方法将套管的运行时间从34-48小时减少到24-27小时,并防止了套管运行过程中的关井或“停止循环”情况。这些关井和/或“停止循环”的情况主要是由于地面气体膨胀和井膨胀迹象导致流出读数增加造成的。后来发现,膨胀情景与高浪涌压力和更高的SBP有关,以缓解地面的气体。采取了一种整体方法来确定减轻此类事件的方法。很明显,必须控制MPD压力来控制涌波,以减轻膨胀,但在下入套管时,由于下入气体过多,需要更高的MPD压力,因此必须首先进行评估。后来发现,在10000英尺的水平段中,过量的气体不仅与底部钻具组合(BHA)的抽汲压力有关,还与影响井筒稳定性的POOH操作和方法有关。为了使浮动套管能够一直下至TD,首先为客户分析了MPD压力和底部向上循环策略,并对POOH与BHA进行了修改。其次,对MPD平衡丸体积(通常在垂直井段进行定位)及其定位程序/计算进行了修改,以确保最大限度地减少垂直井段的气体侵入和运移。这种平衡丸的设计可以自动将重丸排出井外,而无需在下套管时停止和循环丸。第三,MPD控制系统经过改进,可以在下放套管时自动控制MPD压力,以控制井喷,防止漏失/膨胀。本文阐述了所有这些方法是如何在Haynesville的10,000英尺水平段浮起套管的。
{"title":"Floating Casings in 10,000ft Laterals with MPD in Haynesville","authors":"Harshad Patil, E. Dietrich, Ian Knight, Greg Matherne, Svein Hovland","doi":"10.2118/210554-ms","DOIUrl":"https://doi.org/10.2118/210554-ms","url":null,"abstract":"\u0000 This paper highlights a case study where MPD (Managed Pressure Drilling) techniques were utilized while floating long string casings in the 10,000ft laterals in the Haynesville, saving the client more than 30-40% of rig time. The challenges encompassing the events that cause casing floating equipment conversion, either due to excessive gas, flow out from well or drag, are illustrated herein. This paper demonstrates the specific MPD techniques which facilitated floating casing to TD (Target Depth) and prevent its untimely conversion. The use of unique MPD methods illustrated herein enabled prevention of excess gas, hole collapse and situations relating to ballooning which enabled floating the casing to TD.\u0000 These MPD methods helped reduce casing running times from 34-48hrs to 24-27hrs and prevented shut-in or \"stop & circulate\" scenarios during running casing. These shut-ins and/or \"stop & circulate\" scenarios were largely caused by increased flow out readings as the gas expanded at surface along with indications of well ballooning. Ballooning scenarios were later found to be associated with high surge pressures and higher SBP required to mitigate gas at surface. A holistic approach was taken to identify methods to mitigate such events. It was obvious that MPD pressures had to be manipulated for managing surge to mitigate ballooning, but excessive trip gas which necessitated higher MPD pressures while running casing had to be primarily evaluated. It was later found that excessive gas in these 10,000ft laterals were not just a function of swabbing pressures while POOH (pulling out of hole) with BHA (Bottomhole Assembly), but also related to POOH practices and methods which affected wellbore stability.\u0000 To enable floating casing all the way to TD, first the MPD pressures and bottoms-up circulation strategy while POOH with BHA were analyzed and modified for the client. Second, the MPD balanced pill volume (which is typically spotted in the vertical) and its spotting procedure/calculations were revised to ensure minimizing gas encroachment and migration in vertical hole section. The design of this balanced pill accommodated automatic heavy pill displacement out of the well without the need for stopping and circulating pill while running casing. And third, the MPD control system was modified to automatically manipulate the MPD pressures as the casing was lowered to manage surge and prevent losses/ballooning. This paper illustrates how all of these methods enabled floating the casing in 10,000ft lateral in Haynesville.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"20 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"124683191","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Perforating Using MPD Techniques: Design and Execution MPD射孔技术:设计与实施
Pub Date : 2022-09-27 DOI: 10.2118/210542-ms
André Alonso Fernandes, Davi Valle Ferreira, E. Schnitzler, Fabiano Hamilton de Castro, Isadora Luisa de Paiva Goncalves do Carmo, Pedro Menezes Santana, Roger Savoldi Roman
An appraisal well was drilled in Brazilian pre-salt area using overbalance drilling fluid, with conventional techniques. While drilling reservoir (in a 12 1/4" phase), total losses were found. Unsuccessful attempts with LCM and cement pills revealed that only MPD/PMCD techniques could deliver the well to TD. It was decided to anticipate the installation of the 9 5/8" casing, covering only the upper portion of the reservoir, and well was suspended. The remaining reservoir could be drilled later with a rig equipped with MPD system. This well was designed as a 2-zones intelligent completion in cased hole configuration. Due to the fluid losses a new design had to be considered. Due to reservoir uncertainties, definition on the separation between zones would only be taken after drilling the remaining reservoir section. To overcome this challenge without adding time and complexity to the overall design, the best solution was to perforate the cased hole section after drilling the remaining section, meaning doing it with reservoir communicated to the wellbore and in PMCD mode. Several options were evaluated to design the TCP operation in PMCD. Well control strategies, contingencies, thermal effects, and dynamic shocks were considered. The solution consisted in running the TCP with a closed string, without NRVs and having robust contingencies in case of washout or drillpipe failure after perforating. The well was drilled, and total fluid losses occurred again. It was then successfully perforated still in PMCD, then lower and upper completion were installed. Despite these challenges, this was the fastest intelligent completion in all Petrobras pre-salt fields so far.
在巴西盐下地区,采用常规技术,使用过平衡钻井液进行了一口评价井的钻探。在钻井储层时(在12 1/4”阶段),发现了总漏失。使用LCM和水泥丸的失败尝试表明,只有MPD/PMCD技术才能将井送到TD。最终决定提前安装9 5/8”套管,仅覆盖储层上部,然后暂停钻井。剩下的储层可以稍后使用配备MPD系统的钻机进行钻探。该井被设计为两层套管井智能完井结构。由于流体损失,必须考虑新的设计。由于储层的不确定性,只有在钻完剩余的储层段后才能确定层间的分隔。为了在不增加整体设计时间和复杂性的情况下克服这一挑战,最好的解决方案是在钻完剩余部分后对套管井段进行射孔,这意味着在PMCD模式下进行储层与井筒连通的射孔。评估了几种方案,以设计PMCD中的TCP操作。考虑了井控策略、意外事故、热效应和动态冲击。该解决方案包括使用封闭管柱下入TCP,不使用nrv,并且在射孔后冲蚀或钻杆失效的情况下具有强大的应急能力。钻完井后,再次发生全失液。然后在PMCD中成功射孔,然后安装下部和上部完井。尽管存在这些挑战,但这是迄今为止Petrobras所有盐下油田中最快的智能完井。
{"title":"Perforating Using MPD Techniques: Design and Execution","authors":"André Alonso Fernandes, Davi Valle Ferreira, E. Schnitzler, Fabiano Hamilton de Castro, Isadora Luisa de Paiva Goncalves do Carmo, Pedro Menezes Santana, Roger Savoldi Roman","doi":"10.2118/210542-ms","DOIUrl":"https://doi.org/10.2118/210542-ms","url":null,"abstract":"\u0000 An appraisal well was drilled in Brazilian pre-salt area using overbalance drilling fluid, with conventional techniques. While drilling reservoir (in a 12 1/4\" phase), total losses were found. Unsuccessful attempts with LCM and cement pills revealed that only MPD/PMCD techniques could deliver the well to TD. It was decided to anticipate the installation of the 9 5/8\" casing, covering only the upper portion of the reservoir, and well was suspended. The remaining reservoir could be drilled later with a rig equipped with MPD system.\u0000 This well was designed as a 2-zones intelligent completion in cased hole configuration. Due to the fluid losses a new design had to be considered. Due to reservoir uncertainties, definition on the separation between zones would only be taken after drilling the remaining reservoir section.\u0000 To overcome this challenge without adding time and complexity to the overall design, the best solution was to perforate the cased hole section after drilling the remaining section, meaning doing it with reservoir communicated to the wellbore and in PMCD mode.\u0000 Several options were evaluated to design the TCP operation in PMCD. Well control strategies, contingencies, thermal effects, and dynamic shocks were considered. The solution consisted in running the TCP with a closed string, without NRVs and having robust contingencies in case of washout or drillpipe failure after perforating.\u0000 The well was drilled, and total fluid losses occurred again. It was then successfully perforated still in PMCD, then lower and upper completion were installed. Despite these challenges, this was the fastest intelligent completion in all Petrobras pre-salt fields so far.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"64 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"133927823","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
First Implementation of Managed Pressure Drilling (MPD) System in Swamp Barge Rig to Drill Narrow Pressure Window HPHT Exploration Well Safely – Return of Experience from Kalimantan, Indonesia 首次在沼泽驳船钻井平台上实施控压钻井(MPD)系统,安全钻出窄压力窗高温高压探井——印度尼西亚加里曼丹经验的回馈
Pub Date : 2022-09-27 DOI: 10.2118/210553-ms
_. Setiohadi, Praja Hadistira, Muhammad Alfianoor Yudhatama, Daniel Sitompul, Dikha Escodianto Hutabarat, Andre Wiharja, C. Agriawan, A. Martadinata, _. Sudiariaji, Agus Sidianto, Andry Prasthio, F. Irawan
The first ever HPHT exploration well in Kalimantan was drilled by Swamp Barge Rig with narrow pressure window environment. The well was planned to be drilled using 2.9 SG mud weight to 4575 m vertical depth with 0.10 SG pressure window. Maximum predicted bottom hole temperature of the well was 186° C while the maximum expected wellhead pressure (MEWHP) reached 11,300 Psi. MPD becomes mandatory to complete the well and becomes a novel implement for swamp barge rig operation. Therefore, MPD workshop was held among the teams to ensure all personnel become familiar with the system. On other hand, the equipment configuration was set with some modifications to accommodate the operation requirement, contingency, tight stack up below rotary table and hoisting devices limitation. Rotating Control Device (RCD) was stacked up part by part on tight moon pool space. Several modifications were done properly and gave operation flexibility plus robust contingency. RCD alignment was reset periodically and natural rubbers were utilized to enhanced rubbers lifetime in high temperature condition. EKD system with Coriolis utilization was being main mitigation during drilling with limited kick margin that will allow reservoir section to be accessed. Formation pressure investigation was also performed to give additional information on formation pressure for better well assessment. SBP application on dual gradient tripping and managed pressure cementing give a means to secure the well safely and properly during high gas event with losses condition. As the result, MPD implementation enables the operator to complete HPHT exploration well on swamp barge rig project safely despite the complexity and risk of narrow formation pressure window operation.
加里曼丹第一口高温高压探井是用窄压力窗环境下的Swamp Barge钻机钻探的。该井计划使用2.9 SG泥浆密度,井深4575米,压力窗0.10 SG。该井的最大预测井底温度为186℃,最大预期井口压力(MEWHP)达到11,300 Psi。MPD已成为完井作业的必备工具,并成为沼泽驳船钻井作业的新工具。因此,在各小组之间举行了MPD讲习班,以确保所有人员熟悉该系统。另一方面,设备配置进行了一些修改,以适应作业要求、应急情况、转盘以下紧密堆叠以及吊装设备的限制。旋转控制装置(RCD)在狭小的月池空间上逐块堆放。通过适当的修改,提高了操作的灵活性和鲁棒性。定期重置RCD对准,并利用天然橡胶提高橡胶在高温条件下的使用寿命。在有限的井涌余量下,利用科里奥利的EKD系统是钻井期间的主要缓解措施,这将允许进入储层段。此外,还进行了地层压力调查,以获得更多的地层压力信息,从而更好地进行井评价。SBP在双梯度起下钻和控压固井中的应用,为在高含气量、漏失情况下安全、合理地保护油井提供了一种手段。因此,MPD的实施使作业者能够安全完成沼泽驳船钻井项目的高温高压探井,尽管地层压力窗口操作的复杂性和风险很小。
{"title":"First Implementation of Managed Pressure Drilling (MPD) System in Swamp Barge Rig to Drill Narrow Pressure Window HPHT Exploration Well Safely – Return of Experience from Kalimantan, Indonesia","authors":"_. Setiohadi, Praja Hadistira, Muhammad Alfianoor Yudhatama, Daniel Sitompul, Dikha Escodianto Hutabarat, Andre Wiharja, C. Agriawan, A. Martadinata, _. Sudiariaji, Agus Sidianto, Andry Prasthio, F. Irawan","doi":"10.2118/210553-ms","DOIUrl":"https://doi.org/10.2118/210553-ms","url":null,"abstract":"The first ever HPHT exploration well in Kalimantan was drilled by Swamp Barge Rig with narrow pressure window environment. The well was planned to be drilled using 2.9 SG mud weight to 4575 m vertical depth with 0.10 SG pressure window. Maximum predicted bottom hole temperature of the well was 186° C while the maximum expected wellhead pressure (MEWHP) reached 11,300 Psi. MPD becomes mandatory to complete the well and becomes a novel implement for swamp barge rig operation. Therefore, MPD workshop was held among the teams to ensure all personnel become familiar with the system. On other hand, the equipment configuration was set with some modifications to accommodate the operation requirement, contingency, tight stack up below rotary table and hoisting devices limitation. Rotating Control Device (RCD) was stacked up part by part on tight moon pool space. Several modifications were done properly and gave operation flexibility plus robust contingency. RCD alignment was reset periodically and natural rubbers were utilized to enhanced rubbers lifetime in high temperature condition. EKD system with Coriolis utilization was being main mitigation during drilling with limited kick margin that will allow reservoir section to be accessed. Formation pressure investigation was also performed to give additional information on formation pressure for better well assessment. SBP application on dual gradient tripping and managed pressure cementing give a means to secure the well safely and properly during high gas event with losses condition. As the result, MPD implementation enables the operator to complete HPHT exploration well on swamp barge rig project safely despite the complexity and risk of narrow formation pressure window operation.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"38 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"121372186","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Pressurized Mud Cap Drilling Used to Drill and Complete Carbonate Gas Reservoir with Poor Injectivity and Severe Dynamic Losses Offshore Malaysia 加压泥浆帽钻井技术用于马来西亚近海低注入能力和严重动态漏失的碳酸盐岩气藏钻井和完井
Pub Date : 2022-09-27 DOI: 10.2118/210550-ms
T. McCluskey, Ching Shearn Ho, Chai Yong Tan, Eric Timbancaya, Mohammad Annas Omar, Khairil Azam Mohd Khaidzir
This paper describes how PMCD with an overbalanced drilling mud, instead of Light Annular Mud, was used to successfully drill and complete a well in gas bearing carbonates offshore Malaysia. This unconventional approach was adopted after encountering poor formation injectivity and severe dynamic losses in the 8-1/2″ reservoir section. Dynamic losses of 700 bbl/hr were encountered after drilling into the carbonate formation, but the subsequent injectivity test surface pressure prevented the well being converted to PMCD with LAM. LCM pills were spotted and the mud weight was cut by 0.2 ppg but severe dynamic losses continued. An injectivity test was performed with seawater and the surface pressure stabilized around 500 psi. Drilling resumed with overbalanced drilling mud in the annulus, which was top filled during connections to keep the hole full and to monitor the annulus with a nominal surface pressure, while seawater was pumped down the string. After reaching TD, the drilling BHA was retrieved to surface and the 7″ lower completion was run in hole while the well continued to take around 50 bbl/hr static losses. When the lower completion entered the open hole, PMCD was activated to run in and set the liner hanger. This method of unconventional PMCD may be implemented to successfully drill through carbonates with poor injectivity and severe dynamic losses, thereby improving the safety and efficiency of the drilling operations compared to conventional or floating mud cap drilling.
本文介绍了PMCD在马来西亚近海含气碳酸盐岩地层的成功钻井和完井过程中,如何使用过平衡钻井泥浆代替轻质环空泥浆。在8-1/2″油藏段遇到地层注入能力差和严重的动态损失后,采用了这种非常规方法。钻进碳酸盐岩地层后,遇到了700桶/小时的动态漏失,但随后的注入测试表面压力阻止了该井使用LAM转换为PMCD。LCM丸被发现,泥浆重量减少了0.2 ppg,但严重的动态损失继续存在。进行了海水注入测试,表面压力稳定在500psi左右。在接箍过程中,钻井泥浆在环空中达到过平衡,继续进行钻井作业。在接箍过程中,钻井泥浆被顶部填充,以保持井眼满满,并在名义表面压力下监测环空,同时将海水泵入管柱。到达TD后,将钻井底部钻具组合回收到地面,并在井中下入7″下完井,同时井的静态损失继续保持在50桶/小时左右。当下完井进入裸眼井后,启动PMCD下入尾管悬挂器并下入尾管悬挂器。这种非常规PMCD方法可以成功钻穿注入能力差、动态漏失严重的碳酸盐岩,从而提高钻井作业的安全性和效率,优于常规钻井或浮动泥浆帽钻井。
{"title":"Pressurized Mud Cap Drilling Used to Drill and Complete Carbonate Gas Reservoir with Poor Injectivity and Severe Dynamic Losses Offshore Malaysia","authors":"T. McCluskey, Ching Shearn Ho, Chai Yong Tan, Eric Timbancaya, Mohammad Annas Omar, Khairil Azam Mohd Khaidzir","doi":"10.2118/210550-ms","DOIUrl":"https://doi.org/10.2118/210550-ms","url":null,"abstract":"\u0000 This paper describes how PMCD with an overbalanced drilling mud, instead of Light Annular Mud, was used to successfully drill and complete a well in gas bearing carbonates offshore Malaysia. This unconventional approach was adopted after encountering poor formation injectivity and severe dynamic losses in the 8-1/2″ reservoir section.\u0000 Dynamic losses of 700 bbl/hr were encountered after drilling into the carbonate formation, but the subsequent injectivity test surface pressure prevented the well being converted to PMCD with LAM. LCM pills were spotted and the mud weight was cut by 0.2 ppg but severe dynamic losses continued. An injectivity test was performed with seawater and the surface pressure stabilized around 500 psi. Drilling resumed with overbalanced drilling mud in the annulus, which was top filled during connections to keep the hole full and to monitor the annulus with a nominal surface pressure, while seawater was pumped down the string.\u0000 After reaching TD, the drilling BHA was retrieved to surface and the 7″ lower completion was run in hole while the well continued to take around 50 bbl/hr static losses. When the lower completion entered the open hole, PMCD was activated to run in and set the liner hanger.\u0000 This method of unconventional PMCD may be implemented to successfully drill through carbonates with poor injectivity and severe dynamic losses, thereby improving the safety and efficiency of the drilling operations compared to conventional or floating mud cap drilling.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"74 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"129440548","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Expanded IME with New Riser Gas Handling Operation Region 通过新的立管气体处理作业区域扩大了IME
Pub Date : 2022-09-27 DOI: 10.2118/210538-ms
O. Gabaldon, Romar A Gonzalez Luis, Pedro Sousa, Chen Wei, Yuanhang Chen
The Influx Management Envelope (IME) is a proven tool to assess management of influxes taken during MPD operations. Currently, IME establishes limits of manageable influx volumes for given kick intensity/surface back-pressures, to hand over from primary to secondary barrier (i.e., well-control equipment). Opportunities exist for advanced, safe operations when influx circulation up the riser is a concern but dealing with the influx in the hole may introduce additional risks, such as imposing choke line friction pressures (CLFP), particularly in ultra-deepwater operations. A closed riser system allows for safe handling of influxes using the riser/MPD equipment, while isolating the wellbore with the subsea BOP and eliminating risks of fracturing the well or taking additional influxes. We propose expanding the current regions of the IME with a zone in which the decision can be made to circulate the influx to the riser, then isolate the well to handle the influx in the riser with MPD equipment, using the opportunities and methods being developed for industry use. Potential risks to the integrity of the system are analyzed and assessed versus reasonable scenarios. This work is consistent with the current work on providing guidelines for influx management with MPD (IM Annex to API-RP92S, under balloting process by API), and for managing gas in riser with closed riser systems (Riser Gas Handling (RGH) Guidelines, by the IADC UBO&MPD Committee).
流入管理信封(IME)是一种经过验证的工具,用于评估MPD作业期间所采取的流入管理。目前,IME在给定井涌强度/地面反压的情况下,确定了可管理的流入量的限制,以便从一级屏障移交到二级屏障(即井控设备)。当溢流沿着隔水管循环时,先进、安全的作业是有机会的,但处理井内的溢流可能会带来额外的风险,例如施加节流管摩擦压力(CLFP),特别是在超深水作业中。封闭立管系统允许使用立管/MPD设备安全处理流体,同时使用海底防喷器隔离井筒,消除了压裂井或额外注入流体的风险。我们建议扩大IME的现有区域,在该区域内,可以决定将流入流体循环到隔水管,然后利用MPD设备隔离井以处理流入隔水管的流体,利用正在开发的行业应用的机会和方法。根据合理的方案分析和评估系统完整性的潜在风险。这项工作与目前提供MPD流入管理指南(API- rp92s的IM附件,由API投票表决)以及使用封闭立管系统管理立管中的气体(IADC UBO&MPD委员会的立管气体处理(RGH)指南)的工作是一致的。
{"title":"Expanded IME with New Riser Gas Handling Operation Region","authors":"O. Gabaldon, Romar A Gonzalez Luis, Pedro Sousa, Chen Wei, Yuanhang Chen","doi":"10.2118/210538-ms","DOIUrl":"https://doi.org/10.2118/210538-ms","url":null,"abstract":"The Influx Management Envelope (IME) is a proven tool to assess management of influxes taken during MPD operations. Currently, IME establishes limits of manageable influx volumes for given kick intensity/surface back-pressures, to hand over from primary to secondary barrier (i.e., well-control equipment). Opportunities exist for advanced, safe operations when influx circulation up the riser is a concern but dealing with the influx in the hole may introduce additional risks, such as imposing choke line friction pressures (CLFP), particularly in ultra-deepwater operations. A closed riser system allows for safe handling of influxes using the riser/MPD equipment, while isolating the wellbore with the subsea BOP and eliminating risks of fracturing the well or taking additional influxes. We propose expanding the current regions of the IME with a zone in which the decision can be made to circulate the influx to the riser, then isolate the well to handle the influx in the riser with MPD equipment, using the opportunities and methods being developed for industry use. Potential risks to the integrity of the system are analyzed and assessed versus reasonable scenarios. This work is consistent with the current work on providing guidelines for influx management with MPD (IM Annex to API-RP92S, under balloting process by API), and for managing gas in riser with closed riser systems (Riser Gas Handling (RGH) Guidelines, by the IADC UBO&MPD Committee).","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"3 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"133011068","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 2
Reduced Project Duration via Intelligent Scheduling for Ship Production/Repair 通过船舶生产/维修的智能调度减少项目工期
Pub Date : 2022-09-19 DOI: 10.5957/smc-2022-055
R. Richards
Ship and submarine production and repair have benefited significantly from more intelligently allocating resources and managing other constraints, thereby increasing efficiency, and reducing overall project duration. In complex production and repair environments, such as ship production/repair, the method of allocating resources and managing other constraints significantly affects the efficiency of progress and thus the overall project duration. Resources include human resources, equipment resources and physical-space resources. Due to the inherent complexity of resource allocation and constraint management for such complex environments, the project durations can be 25%+ longer than necessary. This paper shares the real-world results experienced by the authors as well as similar results found in the literature showing the major difference in project duration due to resource-scheduling techniques.
船舶和潜艇的生产和维修从更智能地分配资源和管理其他约束条件中受益匪浅,从而提高了效率,缩短了整个项目的工期。在复杂的生产和维修环境中,例如船舶生产/维修,资源分配和管理其他约束的方法会显著影响进度的效率,从而影响整个项目的持续时间。资源包括人力资源、设备资源和物理空间资源。由于这种复杂环境的资源分配和约束管理的固有复杂性,项目持续时间可能比必要的时间长25%以上。本文分享了作者所经历的实际结果,以及在文献中发现的类似结果,表明资源调度技术对项目持续时间的主要影响。
{"title":"Reduced Project Duration via Intelligent Scheduling for Ship Production/Repair","authors":"R. Richards","doi":"10.5957/smc-2022-055","DOIUrl":"https://doi.org/10.5957/smc-2022-055","url":null,"abstract":"Ship and submarine production and repair have benefited significantly from more intelligently allocating resources and managing other constraints, thereby increasing efficiency, and reducing overall project duration. In complex production and repair environments, such as ship production/repair, the method of allocating resources and managing other constraints significantly affects the efficiency of progress and thus the overall project duration. Resources include human resources, equipment resources and physical-space resources. Due to the inherent complexity of resource allocation and constraint management for such complex environments, the project durations can be 25%+ longer than necessary. This paper shares the real-world results experienced by the authors as well as similar results found in the literature showing the major difference in project duration due to resource-scheduling techniques.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"1 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"128390296","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Fuel Choices for Carbon Reduction and Impact on Vessel Design 减少碳排放的燃料选择及其对船舶设计的影响
Pub Date : 2022-09-19 DOI: 10.5957/smc-2022-046
Cameron Baker, R. Tagg, Eugene A. Van Rynbach, Dale Pederson, Julian Gaitley
There are several upcoming regulations focusing on the emissions from maritime transportation requiring owners to rethink their normal operations. One option available to ship owners and operators to achieve compliance with the regulations is to utilize alternate fuels with low-carbon content. These considerations have moved from the future to the present. Current new designs must include plans for future carbon reduction and the widespread availability of low-carbon fuels. This study provides a summary of the available fuels in practical terms that are useful to Naval Architects and Marine Engineers when designing vessels and it will discuss some of the design considerations that must be made to ensure a vessel is transition-ready to operate using these fuels in the near future.
即将出台的几项关于海上运输排放的法规要求船东重新考虑他们的正常运营。船东和经营者可以选择使用低碳替代燃料来实现合规。这些考虑已经从未来转移到现在。当前的新设计必须包括未来碳减排和低碳燃料广泛使用的计划。本研究总结了船舶设计中实用的可用燃料,并讨论了为确保船舶在不久的将来能够过渡到使用这些燃料而必须考虑的一些设计因素。
{"title":"Fuel Choices for Carbon Reduction and Impact on Vessel Design","authors":"Cameron Baker, R. Tagg, Eugene A. Van Rynbach, Dale Pederson, Julian Gaitley","doi":"10.5957/smc-2022-046","DOIUrl":"https://doi.org/10.5957/smc-2022-046","url":null,"abstract":"There are several upcoming regulations focusing on the emissions from maritime transportation requiring owners to rethink their normal operations. One option available to ship owners and operators to achieve compliance with the regulations is to utilize alternate fuels with low-carbon content. These considerations have moved from the future to the present. Current new designs must include plans for future carbon reduction and the widespread availability of low-carbon fuels. This study provides a summary of the available fuels in practical terms that are useful to Naval Architects and Marine Engineers when designing vessels and it will discuss some of the design considerations that must be made to ensure a vessel is transition-ready to operate using these fuels in the near future.","PeriodicalId":336268,"journal":{"name":"Day 2 Wed, September 28, 2022","volume":"13 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-09-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"128495404","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
期刊
Day 2 Wed, September 28, 2022
全部 Acc. Chem. Res. ACS Applied Bio Materials ACS Appl. Electron. Mater. ACS Appl. Energy Mater. ACS Appl. Mater. Interfaces ACS Appl. Nano Mater. ACS Appl. Polym. Mater. ACS BIOMATER-SCI ENG ACS Catal. ACS Cent. Sci. ACS Chem. Biol. ACS Chemical Health & Safety ACS Chem. Neurosci. ACS Comb. Sci. ACS Earth Space Chem. ACS Energy Lett. ACS Infect. Dis. ACS Macro Lett. ACS Mater. Lett. ACS Med. Chem. Lett. ACS Nano ACS Omega ACS Photonics ACS Sens. ACS Sustainable Chem. Eng. ACS Synth. Biol. Anal. Chem. BIOCHEMISTRY-US Bioconjugate Chem. BIOMACROMOLECULES Chem. Res. Toxicol. Chem. Rev. Chem. Mater. CRYST GROWTH DES ENERG FUEL Environ. Sci. Technol. Environ. Sci. Technol. Lett. Eur. J. Inorg. Chem. IND ENG CHEM RES Inorg. Chem. J. Agric. Food. Chem. J. Chem. Eng. Data J. Chem. Educ. J. Chem. Inf. Model. J. Chem. Theory Comput. J. Med. Chem. J. Nat. Prod. J PROTEOME RES J. Am. Chem. Soc. LANGMUIR MACROMOLECULES Mol. Pharmaceutics Nano Lett. Org. Lett. ORG PROCESS RES DEV ORGANOMETALLICS J. Org. Chem. J. Phys. Chem. J. Phys. Chem. A J. Phys. Chem. B J. Phys. Chem. C J. Phys. Chem. Lett. Analyst Anal. Methods Biomater. Sci. Catal. Sci. Technol. Chem. Commun. Chem. Soc. Rev. CHEM EDUC RES PRACT CRYSTENGCOMM Dalton Trans. Energy Environ. Sci. ENVIRON SCI-NANO ENVIRON SCI-PROC IMP ENVIRON SCI-WAT RES Faraday Discuss. Food Funct. Green Chem. Inorg. Chem. Front. Integr. Biol. J. Anal. At. Spectrom. J. Mater. Chem. A J. Mater. Chem. B J. Mater. Chem. C Lab Chip Mater. Chem. Front. Mater. Horiz. MEDCHEMCOMM Metallomics Mol. Biosyst. Mol. Syst. Des. Eng. Nanoscale Nanoscale Horiz. Nat. Prod. Rep. New J. Chem. Org. Biomol. Chem. Org. Chem. Front. PHOTOCH PHOTOBIO SCI PCCP Polym. Chem.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1