Identifying Factors Influencing Time and Cost Overruns in Public Construction Projects in Bhutan 确定影响不丹公共建设项目时间和成本超支的因素
Pub Date : 2023-08-23 DOI: 10.58696/230009
Yeshey Lotay, Ugyen Wangdi
Construction industries worldwide are impacted by time and cost overruns, resulting in significant financial loss and failure to complete projects on time. Clients, contractors, and consultants can plan properly for public construction projects if they have a better understanding of cost and time overruns. The Construction Development Board (now Bhutan Construction and Transport Authority) is the lead agency regulating and overseeing the government construction projects in Bhutan. However, in recent four years, from July 2017 to June 2021, about 50% of the total 2111 government construction projects experienced time and cost overruns, and the total financial loss was Nu. 2,578.86 million. Therefore, study was designed to examine the factors causing delays and cost escalations in the construction project implemented by government during the financial year July 2017 to June 2021. Thus, this study explores identifying factors influencing time and cost overruns to avoid time delays and financial losses. The primary data was collected through the questionnaire survey from engineers of 20 Dzongkhags and 4 Thromdes. The secondary data was collected from the CDB's annual reports, the Construction Association of Bhutan (CAB), and the National Statistics Bureau (NSB). The data was analyzed using the descriptive statistics method, and the relative importance index (RII) was calculated to rank the factors identified from literature reviews. The research results show that financial issue was the critical factor causing delays and cost escalation in the government construction project in Bhutan. Followed by the issue of delays and cost overruns due to shortage of local construction materials, inadequate experience of the contractor, poor site planning, shortage of skilled workers, unrealistic schedule, design change, contractual issues, and project manager competence.
世界各地的建筑行业都受到时间和成本超支的影响,导致重大的经济损失和未能按时完成项目。如果客户、承包商和顾问对成本和时间超支有更好的了解,他们就能正确地规划公共建设项目。不丹建设发展局(现为不丹建设和运输管理局)是不丹管理和监督政府建设项目的领导机构。然而,从2017年7月到2021年6月,近四年来,在2111个政府建设项目中,约有50%的项目出现了时间和成本超支,总财务损失为25.7886亿元。因此,该研究旨在检查在2017年7月至2021年6月财政年度政府实施的建设项目中导致延误和成本上升的因素。因此,本研究探讨识别影响时间和成本超支的因素,以避免时间延误和财务损失。本研究的主要数据是通过问卷调查的方式收集到20个宗卡格和4个血栓的工程师。次要数据收集自国家开发银行的年度报告、不丹建筑协会(CAB)和国家统计局(NSB)。采用描述性统计方法对数据进行分析,计算相对重要指数(relative importance index, RII)对文献综述中发现的因素进行排序。研究结果表明,财政问题是导致不丹政府建设项目延误和成本上升的关键因素。其次是由于当地建筑材料短缺、承包商经验不足、现场规划不佳、技术工人短缺、不切实际的时间表、设计变更、合同问题和项目经理能力而导致的延误和成本超支问题。
{"title":"Identifying Factors Influencing Time and Cost Overruns in Public Construction Projects in Bhutan","authors":"Yeshey Lotay, Ugyen Wangdi","doi":"10.58696/230009","DOIUrl":"https://doi.org/10.58696/230009","url":null,"abstract":"Construction industries worldwide are impacted by time and cost overruns, resulting in significant financial loss and failure to complete projects on time. Clients, contractors, and consultants can plan properly for public construction projects if they have a better understanding of cost and time overruns. The Construction Development Board (now Bhutan Construction and Transport Authority) is the lead agency regulating and overseeing the government construction projects in Bhutan. However, in recent four years, from July 2017 to June 2021, about 50% of the total 2111 government construction projects experienced time and cost overruns, and the total financial loss was Nu. 2,578.86 million. Therefore, study was designed to examine the factors causing delays and cost escalations in the construction project implemented by government during the financial year July 2017 to June 2021. Thus, this study explores identifying factors influencing time and cost overruns to avoid time delays and financial losses. The primary data was collected through the questionnaire survey from engineers of 20 Dzongkhags and 4 Thromdes. The secondary data was collected from the CDB's annual reports, the Construction Association of Bhutan (CAB), and the National Statistics Bureau (NSB). The data was analyzed using the descriptive statistics method, and the relative importance index (RII) was calculated to rank the factors identified from literature reviews. The research results show that financial issue was the critical factor causing delays and cost escalation in the government construction project in Bhutan. Followed by the issue of delays and cost overruns due to shortage of local construction materials, inadequate experience of the contractor, poor site planning, shortage of skilled workers, unrealistic schedule, design change, contractual issues, and project manager competence.","PeriodicalId":251398,"journal":{"name":"Construction Journal of Bhutan","volume":"1 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2023-08-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"130615337","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Analysis of road accidents due to obstruction in sight distance caused by foggy weather using Geographic Information System (GIS) and Artificial Neural Network (ANN) at Jumja along Thimphu-Phuentsholing Highway (Asian Highway 48) 基于地理信息系统(GIS)和人工神经网络(ANN)的廷布-芬特舒林公路(亚洲48号公路)Jumja路段雾天造成视距障碍交通事故分析
Pub Date : 2023-08-23 DOI: 10.58696/230007
Sangey Pasang
Road accident analysis is a crucial technique for determining what elements contribute to collisions and can help lower the accident rate. The consideration of sight distance is a crucial component of highway geometric design in order to guarantee effective traffic operations with the highest level of safety at an affordable price. Road accidents frequently result from reduced visibility caused by foggy weather, hence there is increased interest in studying this issue. This study aims to determine and correlate sight distance, fog blockage, and their effects on traffic accidents at Jumja along Thimphu-Phuentsholing Highway (Asian Highway 48). Data gathering and prediction was aided by the usage of Geographic Information Systems and Artificial Neural Network technologies. Temperature, relative humidity and wind speed for seven years from 2017 to 2023 were considered for fog occurrence to train Artificial Neural Network. Visibility was trained and predicted for summer and winter seasons since the occurrence of fog is prevalent during these seasons. As a result, a correlation value R of 0.998 was found, proving the findings to be almost accurate. This study offers a thorough investigation of how sight distance contributes to traffic accidents at Jumja region. A conclusive finding addressing the significance of sight distance as a contributing factor to traffic accidents due to fog invisibility along Jumja region was made after completion of this study.
道路事故分析是确定导致碰撞的因素的关键技术,可以帮助降低事故率。考虑视距是高速公路几何设计的一个重要组成部分,以保证以可承受的价格获得最高安全水平的有效交通运行。道路交通事故经常是由于大雾天气造成能见度降低而引起的,因此研究这个问题的兴趣增加了。本研究旨在确定和关联视线距离,雾阻塞,以及它们对沿廷布-彭措林公路(亚洲48号公路)的Jumja交通事故的影响。利用地理信息系统和人工神经网络技术辅助数据收集和预测。选取2017 - 2023年7年的温度、相对湿度和风速作为雾的发生条件,训练人工神经网络。由于夏季和冬季经常出现雾,因此训练和预测了夏季和冬季的能见度。结果发现相关值R为0.998,证明研究结果基本准确。本研究对视距对Jumja地区交通事故的影响进行了深入的调查。在完成这项研究后,得出了一个结论性的发现,即视距是Jumja地区由于雾隐身而导致交通事故的一个促成因素。
{"title":"Analysis of road accidents due to obstruction in sight distance caused by foggy weather using Geographic Information System (GIS) and Artificial Neural Network (ANN) at Jumja along Thimphu-Phuentsholing Highway (Asian Highway 48)","authors":"Sangey Pasang","doi":"10.58696/230007","DOIUrl":"https://doi.org/10.58696/230007","url":null,"abstract":"Road accident analysis is a crucial technique for determining what elements contribute to collisions and can help lower the accident rate. The consideration of sight distance is a crucial component of highway geometric design in order to guarantee effective traffic operations with the highest level of safety at an affordable price. Road accidents frequently result from reduced visibility caused by foggy weather, hence there is increased interest in studying this issue. This study aims to determine and correlate sight distance, fog blockage, and their effects on traffic accidents at Jumja along Thimphu-Phuentsholing Highway (Asian Highway 48). Data gathering and prediction was aided by the usage of Geographic Information Systems and Artificial Neural Network technologies. Temperature, relative humidity and wind speed for seven years from 2017 to 2023 were considered for fog occurrence to train Artificial Neural Network. Visibility was trained and predicted for summer and winter seasons since the occurrence of fog is prevalent during these seasons. As a result, a correlation value R of 0.998 was found, proving the findings to be almost accurate. This study offers a thorough investigation of how sight distance contributes to traffic accidents at Jumja region. A conclusive finding addressing the significance of sight distance as a contributing factor to traffic accidents due to fog invisibility along Jumja region was made after completion of this study.","PeriodicalId":251398,"journal":{"name":"Construction Journal of Bhutan","volume":"66 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2023-08-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"115623086","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Enhancing Financial Sustainability of Urban Water Supply Systems in Bhutan: A case study of Thimphu Thromde (Municipality). 提高不丹城市供水系统的财务可持续性:以廷布市为例。
Pub Date : 1900-01-01 DOI: 10.58696/230006
M. Pradhan
In almost all existing Urban Water Supply systems in Bhutan, one major issue confronting the sustainability aspect is the lack of adequate financial resources thereby failing to achieve the intended level of performances in terms of service delivery. Recognizing the poor financial scenario of the systems at the moment, it is deemed necessary to adopt necessary measures/interventions to help improve the existing financial situation and to ensure the optimum level of operation and maintenance. To further substantiate the findings and assessments, a case study for Thimphu Water supply systems was carried out through a conventional approach to examine specific interventions that are deemed vital to address key issues and challenges. In conclusion, based on overall findings and assessment, recommendations have been proposed that are in principle, implementable across all existing urban water supply systems in Bhutan because of the reasons that all water utilities across the country are managed/operated in the same manner as Thimphu Thromde including the organizational set-up of the existing water supply management, mode of financing, availing donor assistance for capital investments, seeking tariff revisions, system designs, amongst others and such parameters are regulated by the Ministry of Infrastructure and Transport. The adoption of the proposed measures, particularly addressing of the ‘non-revenue water’ and conduct of advocacy measures on water conservation would significantly help the water utilities enhance the financial sustainability of the systems thereby resulting in overall improvement in the delivery of water services to the consumers.
在不丹几乎所有现有的城市供水系统中,可持续性方面面临的一个主要问题是缺乏足够的财政资源,因此在提供服务方面未能达到预期的绩效水平。鉴于目前各系统的财务状况不佳,我们认为有必要采取必要的措施/干预措施,以帮助改善现有的财务状况,并确保运作和维修达到最佳水平。为了进一步证实调查结果和评估,通过传统方法对廷布供水系统进行了案例研究,以检查被认为对解决关键问题和挑战至关重要的具体干预措施。最后,根据总体调查结果和评估,提出了原则上可在不丹所有现有城市供水系统中实施的建议,因为全国所有供水设施的管理/运营方式与廷布·索洛德相同,包括现有供水管理的组织机构、融资模式、利用捐助者援助进行资本投资、寻求修订关税、除其他外,系统设计和此类参数由基础设施和交通部规定。采纳拟议的措施,特别是处理“非收入用水”问题,以及开展有关节约用水的宣传措施,将大大有助于水务公司提高系统的财政可持续性,从而全面改善向消费者提供的供水服务。
{"title":"Enhancing Financial Sustainability of Urban Water Supply Systems in Bhutan: A case study of Thimphu Thromde (Municipality).","authors":"M. Pradhan","doi":"10.58696/230006","DOIUrl":"https://doi.org/10.58696/230006","url":null,"abstract":"In almost all existing Urban Water Supply systems in Bhutan, one major issue confronting the sustainability aspect is the lack of adequate financial resources thereby failing to achieve the intended level of performances in terms of service delivery. Recognizing the poor financial scenario of the systems at the moment, it is deemed necessary to adopt necessary measures/interventions to help improve the existing financial situation and to ensure the optimum level of operation and maintenance. To further substantiate the findings and assessments, a case study for Thimphu Water supply systems was carried out through a conventional approach to examine specific interventions that are deemed vital to address key issues and challenges. In conclusion, based on overall findings and assessment, recommendations have been proposed that are in principle, implementable across all existing urban water supply systems in Bhutan because of the reasons that all water utilities across the country are managed/operated in the same manner as Thimphu Thromde including the organizational set-up of the existing water supply management, mode of financing, availing donor assistance for capital investments, seeking tariff revisions, system designs, amongst others and such parameters are regulated by the Ministry of Infrastructure and Transport. The adoption of the proposed measures, particularly addressing of the ‘non-revenue water’ and conduct of advocacy measures on water conservation would significantly help the water utilities enhance the financial sustainability of the systems thereby resulting in overall improvement in the delivery of water services to the consumers.","PeriodicalId":251398,"journal":{"name":"Construction Journal of Bhutan","volume":"22 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"131930921","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
期刊
Construction Journal of Bhutan
全部 Acc. Chem. Res. ACS Applied Bio Materials ACS Appl. Electron. Mater. ACS Appl. Energy Mater. ACS Appl. Mater. Interfaces ACS Appl. Nano Mater. ACS Appl. Polym. Mater. ACS BIOMATER-SCI ENG ACS Catal. ACS Cent. Sci. ACS Chem. Biol. ACS Chemical Health & Safety ACS Chem. Neurosci. ACS Comb. Sci. ACS Earth Space Chem. ACS Energy Lett. ACS Infect. Dis. ACS Macro Lett. ACS Mater. Lett. ACS Med. Chem. Lett. ACS Nano ACS Omega ACS Photonics ACS Sens. ACS Sustainable Chem. Eng. ACS Synth. Biol. Anal. Chem. BIOCHEMISTRY-US Bioconjugate Chem. BIOMACROMOLECULES Chem. Res. Toxicol. Chem. Rev. Chem. Mater. CRYST GROWTH DES ENERG FUEL Environ. Sci. Technol. Environ. Sci. Technol. Lett. Eur. J. Inorg. Chem. IND ENG CHEM RES Inorg. Chem. J. Agric. Food. Chem. J. Chem. Eng. Data J. Chem. Educ. J. Chem. Inf. Model. J. Chem. Theory Comput. J. Med. Chem. J. Nat. Prod. J PROTEOME RES J. Am. Chem. Soc. LANGMUIR MACROMOLECULES Mol. Pharmaceutics Nano Lett. Org. Lett. ORG PROCESS RES DEV ORGANOMETALLICS J. Org. Chem. J. Phys. Chem. J. Phys. Chem. A J. Phys. Chem. B J. Phys. Chem. C J. Phys. Chem. Lett. Analyst Anal. Methods Biomater. Sci. Catal. Sci. Technol. Chem. Commun. Chem. Soc. Rev. CHEM EDUC RES PRACT CRYSTENGCOMM Dalton Trans. Energy Environ. Sci. ENVIRON SCI-NANO ENVIRON SCI-PROC IMP ENVIRON SCI-WAT RES Faraday Discuss. Food Funct. Green Chem. Inorg. Chem. Front. Integr. Biol. J. Anal. At. Spectrom. J. Mater. Chem. A J. Mater. Chem. B J. Mater. Chem. C Lab Chip Mater. Chem. Front. Mater. Horiz. MEDCHEMCOMM Metallomics Mol. Biosyst. Mol. Syst. Des. Eng. Nanoscale Nanoscale Horiz. Nat. Prod. Rep. New J. Chem. Org. Biomol. Chem. Org. Chem. Front. PHOTOCH PHOTOBIO SCI PCCP Polym. Chem.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1