The "wen" welding workshop business does welding with bad work postures that cause muscle injury (Musculoskeletal Disorders). For this reason, it is necessary to design a work facility for an efficient welding process. The Nordic Body Map (NBM) questionnaire was used to find out which body parts had complaints that they were not sick, enough pain, illness and evaluation using the Rapid Entire Body Assessment (REBA) method to become an input to improve the operator's work posture to be better. The design of welding facilities is carried out using the Design For Manufacture and Assembly (DFMA) method because it can evaluate the costs and material of new design facilities with pre-existing design facilities in the testing phase. The design results are in the form of a workbench that has a footrest, a welding wire, a material laying place, a bow and vise in a facility, based on testing the lower the REBA score results so that the work posture is better, the facility can be used to weld all products to the workshop weld and efficiency compared to the previous tool at 35%.
{"title":"Perancangan Fasilitas Kerja Proses Pengelasan Yang Ergonomis Dengan Menggunakan Metode Design For Manufacture And Assembly (DFMA) Di Bengkel Las Wen","authors":"Nofirza Nofirza, Anwardi Anwardi, Rika Rika, Fajar Sidik Rudini","doi":"10.20961/PERFORMA.18.1.29824","DOIUrl":"https://doi.org/10.20961/PERFORMA.18.1.29824","url":null,"abstract":"The \"wen\" welding workshop business does welding with bad work postures that cause muscle injury (Musculoskeletal Disorders). For this reason, it is necessary to design a work facility for an efficient welding process. The Nordic Body Map (NBM) questionnaire was used to find out which body parts had complaints that they were not sick, enough pain, illness and evaluation using the Rapid Entire Body Assessment (REBA) method to become an input to improve the operator's work posture to be better. The design of welding facilities is carried out using the Design For Manufacture and Assembly (DFMA) method because it can evaluate the costs and material of new design facilities with pre-existing design facilities in the testing phase. The design results are in the form of a workbench that has a footrest, a welding wire, a material laying place, a bow and vise in a facility, based on testing the lower the REBA score results so that the work posture is better, the facility can be used to weld all products to the workshop weld and efficiency compared to the previous tool at 35%.","PeriodicalId":279428,"journal":{"name":"Performa: Media Ilmiah Teknik Industri","volume":"1 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2019-07-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"129766450","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
Pub Date : 2019-07-24DOI: 10.20961/PERFORMA.18.1.29218
Muhammad Abiyyu Arsyan, Eko Liquiddanu, Eko Pujiyanto
{"title":"Perancangan Sistem Jaminan Halal (SJH) Pada IKM Roti Amira Untuk Memenuhi Persyaratan Dokumentasi Sistem Jaminan Halal","authors":"Muhammad Abiyyu Arsyan, Eko Liquiddanu, Eko Pujiyanto","doi":"10.20961/PERFORMA.18.1.29218","DOIUrl":"https://doi.org/10.20961/PERFORMA.18.1.29218","url":null,"abstract":"","PeriodicalId":279428,"journal":{"name":"Performa: Media Ilmiah Teknik Industri","volume":"41 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2019-07-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"124946581","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
Pub Date : 2019-07-24DOI: 10.20961/PERFORMA.18.1.30202
Oksiana Tiovani, Fakhrina Fahma
PT. XYZ is one of the manufacturing companies in Indonesia. The company produces water pumps. An important component in the water pump is the stator. The observation results in the Stator Assembly line 4 show that low line efficiency occurs because the production process has not run optimally. So that an improvement in the production process is important to do on this line. One method to improve the production process is ECRS based line balancing. By still considering the concept of line balancing, line efficiency can be improved through improving the production process. Through the improvement of the production process, there was a decrease in the number of work stations from 10 work stations to 9 work stations, improvement of line layout and 7th work station (Heating Air Dryer), also an increase in line efficiency from 74.72% to 81.09%.
PT. XYZ是印度尼西亚的一家制造公司。这家公司生产水泵。水泵的一个重要部件是定子。定子4号装配线的观察结果表明,由于生产过程没有达到最佳运行状态,导致生产线效率低下。因此,在这条生产线上改进生产工艺是很重要的。一种改进生产过程的方法是基于ECRS的生产线平衡。通过仍然考虑生产线平衡的概念,可以通过改进生产工艺来提高生产线效率。通过对生产工艺的改进,工位由原来的10个工位减少到9个工位,生产线布局和第7个工位(热风烘干机)的改进,生产线效率由74.72%提高到81.09%。
{"title":"Perbaikan Proses Produksi Menggunakan ECRS Based Line Balancing pada Lini Perakitan Stator 4","authors":"Oksiana Tiovani, Fakhrina Fahma","doi":"10.20961/PERFORMA.18.1.30202","DOIUrl":"https://doi.org/10.20961/PERFORMA.18.1.30202","url":null,"abstract":"PT. XYZ is one of the manufacturing companies in Indonesia. The company produces water pumps. An important component in the water pump is the stator. The observation results in the Stator Assembly line 4 show that low line efficiency occurs because the production process has not run optimally. So that an improvement in the production process is important to do on this line. One method to improve the production process is ECRS based line balancing. By still considering the concept of line balancing, line efficiency can be improved through improving the production process. Through the improvement of the production process, there was a decrease in the number of work stations from 10 work stations to 9 work stations, improvement of line layout and 7th work station (Heating Air Dryer), also an increase in line efficiency from 74.72% to 81.09%.","PeriodicalId":279428,"journal":{"name":"Performa: Media Ilmiah Teknik Industri","volume":"12 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2019-07-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"128267135","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
Pub Date : 2019-07-24DOI: 10.20961/PERFORMA.18.1.32360
R. Astuti, Hana Sekar Ayu Edy purwanto
PT. Y is a company in the pharmaceutical industry that produces finished drugs. Based on observations in the packing process of Tablet XYZ products, it is still found that there are bottlenecks between work stations caused by a lack of equal distribution of work. Work stations whose workload is not evenly distributed, can cause the low of line efficiency. This study improved line balancing using the Ranked Positional Weight method which aims to increase the line efficiency value of the Tablet XYZ packing process. The result of this study is an increase in the value of line efficiency after the distribution of work elements is evenly distributed.
PT. Y是制药行业生产成品药品的公司。根据对Tablet XYZ产品包装过程的观察,仍然发现由于工作分配不均导致工位之间存在瓶颈。工作量分布不均匀的工位,会造成生产线效率低下。本研究利用排名位置权重法改进生产线平衡,旨在提高片剂XYZ包装工艺的生产线效率值。本研究的结果是工作要素分布均匀后,线效率值有所增加。
{"title":"PERBAIKAN LINE BALANCING PROSES PACKING TABLET XYZ MENGGUNAKAN METODE RANKED POSITIONAL WEIGHT DI PT. Y","authors":"R. Astuti, Hana Sekar Ayu Edy purwanto","doi":"10.20961/PERFORMA.18.1.32360","DOIUrl":"https://doi.org/10.20961/PERFORMA.18.1.32360","url":null,"abstract":"PT. Y is a company in the pharmaceutical industry that produces finished drugs. Based on observations in the packing process of Tablet XYZ products, it is still found that there are bottlenecks between work stations caused by a lack of equal distribution of work. Work stations whose workload is not evenly distributed, can cause the low of line efficiency. This study improved line balancing using the Ranked Positional Weight method which aims to increase the line efficiency value of the Tablet XYZ packing process. The result of this study is an increase in the value of line efficiency after the distribution of work elements is evenly distributed.","PeriodicalId":279428,"journal":{"name":"Performa: Media Ilmiah Teknik Industri","volume":"2 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2019-07-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"129527615","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
Pub Date : 2019-07-24DOI: 10.20961/PERFORMA.18.1.19078
Nadiya Pramudian Kurniawati, Novie Susanto
Indonesia Power UBP Mrica ltd. in the Banjarnegara district is a company that runs is the field of provision and distribution of electricity. For a company that specialized in the field of provision and distribution of electricity it is vital to have a place to store items and spare parts for production, usually called warehouse. Beside for a place to store stuff, a warehouse can also function as a temporary storage for products or spare parts that will be used and distributed, either to the consumers or the other warehouses. The main goal of this study is to know how the 5S method is implemented in the warehouse of Indonesia Power UBP Mrica ltd. Implementation here include the labelling of shelf and cabinet, and also the standardization for the whole activities in the warehouse for the sake of optimizing performance in the warehouse. The result of this research will be a suggestion of refinement related to the warehouse performance.
{"title":"ANALISIS PENERAPAN METODE 5S PADA WAREHOUSE FAST MOVING PT.INDONESIA POWER UBP MRICA KABUPATEN BANJARNEGARA","authors":"Nadiya Pramudian Kurniawati, Novie Susanto","doi":"10.20961/PERFORMA.18.1.19078","DOIUrl":"https://doi.org/10.20961/PERFORMA.18.1.19078","url":null,"abstract":"Indonesia Power UBP Mrica ltd. in the Banjarnegara district is a company that runs is the field of provision and distribution of electricity. For a company that specialized in the field of provision and distribution of electricity it is vital to have a place to store items and spare parts for production, usually called warehouse. Beside for a place to store stuff, a warehouse can also function as a temporary storage for products or spare parts that will be used and distributed, either to the consumers or the other warehouses. The main goal of this study is to know how the 5S method is implemented in the warehouse of Indonesia Power UBP Mrica ltd. Implementation here include the labelling of shelf and cabinet, and also the standardization for the whole activities in the warehouse for the sake of optimizing performance in the warehouse. The result of this research will be a suggestion of refinement related to the warehouse performance.","PeriodicalId":279428,"journal":{"name":"Performa: Media Ilmiah Teknik Industri","volume":"16 4 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2019-07-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"116643662","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}