首页 > 最新文献

Australian Geomechanics Journal最新文献

英文 中文
Cost-Effectiveness Of Tailings Dewatering And Stacking 尾矿脱水堆放的成本效益
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2023-03-01 DOI: 10.56295/agj5814
Sophie Flottmann, David Williams, Danish Kazmi
Over the last one hundred years, tailings dams have failed globally at a rate of 2 to 5 per annum. This failure rate is considered unacceptable by the community and by the mining industry. The conventional transport of slurry or thickened tailings and their storage in a tailings dam, requires low capital and operational expenditure, as slurry tailings can be transported by pipeline using relatively inexpensive and robust centrifugal pumps. Recently, the filtration of tailings, their transport by conveyor or truck, and “dry” stacking have been seen as an alternate method of tailings management. However, filtration and dry stacking are considered expensive. Over the full life cycle, including post-closure, of filtration and a dry stack facility, the potential to increase water recovery for recycling and increased options post-closure can lead to a reduction in the total expense of a dry stack facility. This study aimed to contribute to understanding of the cost-effectiveness of tailings dewatering and dry stacking as a tailings management method. Various tailings samples from different locations and with different characteristics were tested for their filtration potential. The potential for monetary savings through the reuse/recycling of the water recovered from the tailings through filtration was a particular focus. While tailings with higher clay mineral contents had more potential for water recovery than coarser-grained tailings, they were also more difficult to dewater. Tailings with lower clay mineral contents were relatively easy to dewater, requiring a short residence time, leading to increased water recovery and volume reduction potential. The results identified that there is significant potential for water recovery, leading to monetary savings through the reuse/recycling of water, potential for storage volume reduction, and potential for higher value post-closure uses.
在过去的一百年里,全球的尾矿坝以每年2到5座的速度倒塌。社区和采矿业认为这种失败率是不可接受的。浆体或浓缩尾矿的常规运输及其在尾矿坝中的储存需要较低的资金和运营支出,因为浆体尾矿可以通过管道运输,使用相对便宜和坚固的离心泵。最近,尾矿的过滤,他们的输送机或卡车运输,和“干”堆已被视为一种备选的尾矿管理方法。然而,过滤和干堆被认为是昂贵的。在整个生命周期中,包括关闭后,过滤和干堆设施,增加水回收再利用的潜力和增加关闭后的选择,可以减少干堆设施的总费用。本研究旨在了解尾矿脱水和干堆作为一种尾矿管理方法的成本效益。对不同地点、不同特性的尾矿样品进行了过滤电位测试。通过过滤从尾矿中回收的水的再利用/再循环节省资金的潜力是一个特别的重点。粘土矿物含量高的尾矿比粗粒尾矿具有更大的回水潜力,但也更难脱水。粘土矿物含量低的尾矿相对容易脱水,停留时间短,采收率和体积缩小潜力增大。结果表明,水回收的潜力巨大,可以通过水的再利用/再循环节省资金,减少储存量的潜力,以及关闭后使用的更高价值的潜力。
{"title":"Cost-Effectiveness Of Tailings Dewatering And Stacking","authors":"Sophie Flottmann, David Williams, Danish Kazmi","doi":"10.56295/agj5814","DOIUrl":"https://doi.org/10.56295/agj5814","url":null,"abstract":"Over the last one hundred years, tailings dams have failed globally at a rate of 2 to 5 per annum. This failure rate is considered unacceptable by the community and by the mining industry. The conventional transport of slurry or thickened tailings and their storage in a tailings dam, requires low capital and operational expenditure, as slurry tailings can be transported by pipeline using relatively inexpensive and robust centrifugal pumps. Recently, the filtration of tailings, their transport by conveyor or truck, and “dry” stacking have been seen as an alternate method of tailings management. However, filtration and dry stacking are considered expensive. Over the full life cycle, including post-closure, of filtration and a dry stack facility, the potential to increase water recovery for recycling and increased options post-closure can lead to a reduction in the total expense of a dry stack facility. This study aimed to contribute to understanding of the cost-effectiveness of tailings dewatering and dry stacking as a tailings management method. Various tailings samples from different locations and with different characteristics were tested for their filtration potential. The potential for monetary savings through the reuse/recycling of the water recovered from the tailings through filtration was a particular focus. While tailings with higher clay mineral contents had more potential for water recovery than coarser-grained tailings, they were also more difficult to dewater. Tailings with lower clay mineral contents were relatively easy to dewater, requiring a short residence time, leading to increased water recovery and volume reduction potential. The results identified that there is significant potential for water recovery, leading to monetary savings through the reuse/recycling of water, potential for storage volume reduction, and potential for higher value post-closure uses.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2023-03-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"44358074","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Managing Geotechnical Uncertainty With Simulation Models: An Introduction 用模拟模型管理岩土工程的不确定性:导论
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-12-01 DOI: 10.56295/agj5741
B. Look
In a standard deterministic analysis discrete scenarios are considered, and a moderately conservative “characteristic” value is used as a design basis. However, fixed or exact values in a real-world geotechnical site seldom occurs. Deterministic approaches may not explicitly consider the ground uncertainty. Simulations using various probabilities provides for this uncertainty as each parameter input is treated as a random variable within certain measured ranges or ability to evaluate. Monte Carlo (MC) sampling is a traditional technique for generating random numbers to sample from a probability distribution. When low probability events occur, a small number of MC iterations might not sample sufficient quantities of these outcomes for inclusion in the simulation model. Latin Hypercube (LH) sampling uses stratification of the input probability distributions, to overcome the limitations of Monte Carlo sampling. The simulation results show low probability outcomes are included in the sampling for the simulation model. At a high number of simulation iterations both provide similar outputs, but at low simulation iterations the LH is more reliable. However, both the MC and LH sampling suffer from impractical values at low or high probability events when the normal probability density function (PDF) is adopted. The normal PDF is commonly used in statistical modelling. Non-normal PDFs often represent the best fit PDF when a goodness of fit test is carried out. The errors associated with using the common normal PDF are shown with the above-mentioned simulation models. This best fit PDF applies whether simulation models as described above is used or even with simple “what if” sensitivity models in traditional analysis.
在标准确定性分析中,考虑了离散场景,并使用适度保守的“特征”值作为设计基础。然而,在真实的岩土工程现场中很少出现固定或精确的值。确定性方法可能不会明确考虑地面的不确定性。使用各种概率的模拟提供了这种不确定性,因为每个参数输入都被视为某些测量范围或评估能力内的随机变量。蒙特卡罗(MC)采样是一种传统的从概率分布中生成随机数进行采样的技术。当发生低概率事件时,少量的MC迭代可能无法对足够数量的这些结果进行采样,以纳入模拟模型。拉丁超立方体(LH)采样使用输入概率分布的分层,以克服蒙特卡罗采样的局限性。模拟结果表明,模拟模型的采样中包含低概率结果。在高模拟迭代次数下,两者都提供相似的输出,但在低模拟迭代次数时,LH更可靠。然而,当采用正态概率密度函数(PDF)时,MC和LH采样在低概率或高概率事件中都会遇到不切实际的值。普通PDF通常用于统计建模。当进行拟合优度测试时,非正态PDF通常代表最佳拟合PDF。与使用普通正态PDF相关联的误差用上述模拟模型示出。无论使用如上所述的模拟模型,还是在传统分析中使用简单的“假设”灵敏度模型,这种最佳拟合PDF都适用。
{"title":"Managing Geotechnical Uncertainty With Simulation Models: An Introduction","authors":"B. Look","doi":"10.56295/agj5741","DOIUrl":"https://doi.org/10.56295/agj5741","url":null,"abstract":"In a standard deterministic analysis discrete scenarios are considered, and a moderately conservative “characteristic” value is used as a design basis. However, fixed or exact values in a real-world geotechnical site seldom occurs. Deterministic approaches may not explicitly consider the ground uncertainty. Simulations using various probabilities provides for this uncertainty as each parameter input is treated as a random variable within certain measured ranges or ability to evaluate. Monte Carlo (MC) sampling is a traditional technique for generating random numbers to sample from a probability distribution. When low probability events occur, a small number of MC iterations might not sample sufficient quantities of these outcomes for inclusion in the simulation model. Latin Hypercube (LH) sampling uses stratification of the input probability distributions, to overcome the limitations of Monte Carlo sampling. The simulation results show low probability outcomes are included in the sampling for the simulation model. At a high number of simulation iterations both provide similar outputs, but at low simulation iterations the LH is more reliable. However, both the MC and LH sampling suffer from impractical values at low or high probability events when the normal probability density function (PDF) is adopted. The normal PDF is commonly used in statistical modelling. Non-normal PDFs often represent the best fit PDF when a goodness of fit test is carried out. The errors associated with using the common normal PDF are shown with the above-mentioned simulation models. This best fit PDF applies whether simulation models as described above is used or even with simple “what if” sensitivity models in traditional analysis.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"49458233","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Rock Mass Parameters For The Brisbane CBD 布里斯班中央商务区的岩体参数
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-12-01 DOI: 10.56295/agj5742
Ralph E Cammack, R. Bertuzzi, Adrian P. L. Smith, R. Brehaut
Rock mass parameters are presented for the typical range of rock conditions encountered in the Brisbane CBD and surrounding area. Rock mass units are classified based on lithology, weathering, intact rock strength and degree of disturbance. The rock mass parameters are based on the Author’s combined experience from Brisbane infrastructure projects including the M7 Clem Jones Tunnel, Airport Link and Cross River Rail. The parameters may be useful for design and construction of future ground engineering projects in Brisbane.
给出了布里斯班中央商务区及周边地区岩石条件的典型范围的岩体参数。岩体单元根据岩性、风化、完整岩石强度和扰动程度进行分类。岩体参数基于作者在布里斯班基础设施项目中的综合经验,包括M7克莱姆-琼斯隧道、机场连接线和跨河铁路。这些参数可能对布里斯班未来地面工程项目的设计和施工有用。
{"title":"Rock Mass Parameters For The Brisbane CBD","authors":"Ralph E Cammack, R. Bertuzzi, Adrian P. L. Smith, R. Brehaut","doi":"10.56295/agj5742","DOIUrl":"https://doi.org/10.56295/agj5742","url":null,"abstract":"Rock mass parameters are presented for the typical range of rock conditions encountered in the Brisbane CBD and surrounding area. Rock mass units are classified based on lithology, weathering, intact rock strength and degree of disturbance. The rock mass parameters are based on the Author’s combined experience from Brisbane infrastructure projects including the M7 Clem Jones Tunnel, Airport Link and Cross River Rail. The parameters may be useful for design and construction of future ground engineering projects in Brisbane.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"41398663","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Melbourne Metro Tunnel Project - Numerical Analysis Of Anisotropic Rock Mass For State Library Station 墨尔本地铁隧道项目-国家图书馆站各向异性岩体的数值分析
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-12-01 DOI: 10.56295/agj5743
Ben Coombes, R. Storry, D. Sainsbury
The Metro Tunnel Project is delivering twin nine-kilometre rail tunnels in Melbourne, Australia. In addition to the tunnels, five new underground stations are being constructed. Two of the new stations – State Library and Town Hall – are complex cavern and adit excavations located in Melbourne’s City Centre which will directly connect to the existing City Loop Stations. The State Library station, located predominantly underneath Swanston Street and a busy tram route, was surrounded by a mixture of modern, educational and heritage developments requiring the excavation sequence and primary support to be designed to ensure minimal surface impacts. To simulate the anisotropic rock mass response to the excavation of the State Library Station, FLAC3D numerical analysis was undertaken. The analysis adopted the ubiquitous joint constitutive model approach and was used to assess the performance of the primary lining design and to determine the impacts the predicted ground displacements may have on the surrounding structures.
澳大利亚墨尔本的地铁隧道项目正在建设两条9公里长的铁路隧道。除了隧道,还有五个新的地铁站正在建设中。其中两个新车站——州立图书馆和市政厅——是位于墨尔本市中心的复杂洞穴和坑道,将直接连接现有的城市环线站。国家图书馆站主要位于斯旺斯顿街和一条繁忙的有轨电车路线下面,周围是现代、教育和遗产发展的混合体,要求挖掘顺序和主要支撑的设计要确保对地面的影响最小。为模拟国家图书馆站开挖过程中岩体的各向异性响应,采用FLAC3D数值分析方法。该分析采用泛在节理本构模型方法,用于评估初级衬砌设计的性能,并确定预测的地面位移对周围结构的影响。
{"title":"Melbourne Metro Tunnel Project - Numerical Analysis Of Anisotropic Rock Mass For State Library Station","authors":"Ben Coombes, R. Storry, D. Sainsbury","doi":"10.56295/agj5743","DOIUrl":"https://doi.org/10.56295/agj5743","url":null,"abstract":"The Metro Tunnel Project is delivering twin nine-kilometre rail tunnels in Melbourne, Australia. In addition to the tunnels, five new underground stations are being constructed. Two of the new stations – State Library and Town Hall – are complex cavern and adit excavations located in Melbourne’s City Centre which will directly connect to the existing City Loop Stations. The State Library station, located predominantly underneath Swanston Street and a busy tram route, was surrounded by a mixture of modern, educational and heritage developments requiring the excavation sequence and primary support to be designed to ensure minimal surface impacts. To simulate the anisotropic rock mass response to the excavation of the State Library Station, FLAC3D numerical analysis was undertaken. The analysis adopted the ubiquitous joint constitutive model approach and was used to assess the performance of the primary lining design and to determine the impacts the predicted ground displacements may have on the surrounding structures.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"42998012","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Characterisation Of Complex Ground Conditions For The Rozelle Interchange Project Rozelle立交工程复杂地面条件的特征
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-12-01 DOI: 10.56295/agj5746
B. Estrada, T. Nash, Andrew de Ambrosis, I. Chan
The Rozelle Interchange Project (RIC) in Sydney is an underground motorway interchange connecting multiple underground and surface arterial roads as well as the future Western Harbour Tunnel and Beaches Link. RIC completes the WestConnex program of works and is a complex array of approximately 22 km of multiple level tunnels, all constructed in an area 2.5 km long and 1.5 km wide. RIC is located within complex ground conditions that include deep soils, regional faults, structural zones and igneous intrusions. Deep natural soils infilling a valley near Rozelle Bay are mostly recent Holocene alluvial, marginal marine and marine deposits. These soils are interlayered, discontinuous, normally to slightly over consolidated and capped by sand and coarse rockfill from 19th century reclamation. There is a strong contrast in the level of detail between borehole and CPT data. Distilling this to provide a geological and geotechnical model for a project wide interpretive report for designers of multiple structures required a hybrid approach to model presentation. This included providing a simplified graphical model and including details from specific investigations and laboratory testing allowing designers flexibility to adopt appropriate parameters for their specific application. Similarly, the rock structural model evolved from development of structural domains to identification and inclusion of regional geological structures overprinting the structural model. Regional scale thrust faults, corridors of structural complexity and igneous intrusions were identified and refined prior to and throughout the design process. These were considered in the design by modification of excavation sequencing and changes to tunnel support. Tunnel excavations encountered these regional features at the locations predicted and with similar character as those described in the model allowing the safe construction of the tunnels.
悉尼的Rozelle立交项目(RIC)是一个地下高速公路立交,连接多条地下和地面主干道,以及未来的西部海港隧道和海滩连接。RIC完成了WestConnex项目的工程,是一个由大约22公里的多层隧道组成的复杂阵列,所有隧道都在2.5公里长、1.5公里宽的区域内建造。RIC位于复杂的地面条件下,包括深层土壤、区域断层、构造带和火成岩侵入体。罗泽尔湾附近山谷的深层天然土壤主要是全新世冲积、边缘海相和海相沉积物。这些土壤是层间的,不连续的,通常有轻微的固结,并被19世纪填海造地的沙子和粗石料覆盖。钻孔资料和CPT资料在详细程度上有很大的差别。将其提炼出来,为多个结构的设计师提供一个项目范围的解释报告的地质和岩土模型,需要一种混合的模型呈现方法。这包括提供简化的图形模型,包括具体调查和实验室测试的细节,允许设计师灵活地采用适合其特定应用的适当参数。同样,岩石构造模式也从构造域的开发发展到覆盖构造模式的区域地质构造的识别和包裹。在设计之前和整个设计过程中,对区域规模的逆冲断层、构造复杂的廊道和火成岩侵入体进行了识别和完善。在设计中通过修改开挖顺序和改变隧道支护来考虑这些问题。隧道开挖在预测的位置遇到了这些区域特征,并且与模型中描述的特征相似,从而允许隧道的安全施工。
{"title":"Characterisation Of Complex Ground Conditions For The Rozelle Interchange Project","authors":"B. Estrada, T. Nash, Andrew de Ambrosis, I. Chan","doi":"10.56295/agj5746","DOIUrl":"https://doi.org/10.56295/agj5746","url":null,"abstract":"The Rozelle Interchange Project (RIC) in Sydney is an underground motorway interchange connecting multiple underground and surface arterial roads as well as the future Western Harbour Tunnel and Beaches Link. RIC completes the WestConnex program of works and is a complex array of approximately 22 km of multiple level tunnels, all constructed in an area 2.5 km long and 1.5 km wide. RIC is located within complex ground conditions that include deep soils, regional faults, structural zones and igneous intrusions. Deep natural soils infilling a valley near Rozelle Bay are mostly recent Holocene alluvial, marginal marine and marine deposits. These soils are interlayered, discontinuous, normally to slightly over consolidated and capped by sand and coarse rockfill from 19th century reclamation. There is a strong contrast in the level of detail between borehole and CPT data. Distilling this to provide a geological and geotechnical model for a project wide interpretive report for designers of multiple structures required a hybrid approach to model presentation. This included providing a simplified graphical model and including details from specific investigations and laboratory testing allowing designers flexibility to adopt appropriate parameters for their specific application. Similarly, the rock structural model evolved from development of structural domains to identification and inclusion of regional geological structures overprinting the structural model. Regional scale thrust faults, corridors of structural complexity and igneous intrusions were identified and refined prior to and throughout the design process. These were considered in the design by modification of excavation sequencing and changes to tunnel support. Tunnel excavations encountered these regional features at the locations predicted and with similar character as those described in the model allowing the safe construction of the tunnels.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"45890868","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Design And Construction Of Roma Street Station Cavern, Cross River Rail, Brisbane 布里斯班克罗斯河铁路罗马街车站洞穴的设计与施工
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-12-01 DOI: 10.56295/agj5744
Bernard Shen, Strath Clarke, A. Rogan, P. McCormack
The new Roma Street underground railway station in Brisbane is being constructed as part of Cross River Rail’s Tunnel, Stations and Development (TSD) package. The joint venture of CPB Contractors, BAM International Australia, Ghella and UGL (CBGU JV) is building the 5.9km long twin tunnels from the Southern Tunnel Portal near Dutton Park station, beneath the Brisbane River and CBD to the Northern Tunnel Portal in Spring Hill. The Cross River Rail project includes excavation and construction of four new underground stations. Roma Street station comprises a 280m long cavern, five smaller connecting tunnels (adits) and three shafts. The station cavern has an excavated span of up to 24.4m with approximately 15m rock cover. It has been excavated within the Neranleigh-Fernvale Group (NFG) rock mass, which comprises weakly metamorphosed sandstone (meta-greywacke and arenite), phyllite and subordinate quartzite and meta-basalt. The station lies within the regional Normanby Fault Zone, characterised by a major fault up to 20m wide comprising a combination of intact rock, rock breccia and clay gouge. The fault zone encountered during the station cavern excavation required heavier primary support and localised foundation treatment. The initial primary (temporary) support of the cavern and adits comprised rock bolts, cable bolts and a thin synthetic fibre-reinforced shotcrete lining. In some areas a passive shotcrete arch lining was required. Overlying piled footings from an existing busway overpass structure were within a metre of the adits’ excavated profile which necessitated a complex load transfer structure at the surface and verification of pile toe levels during tunnel construction. The cavern permanent lining typically comprises steel fibre-reinforced concrete in the crown, bar reinforced concrete for the sidewalls, and bar and steel fibre-reinforced concrete invert slabs. Bar reinforcement is used in the cavern crown where it intersects the adits. Ground loads for the permanent structure had to consider the influence of future developments. This paper presents some of the challenges of the primary support and permanent lining design of the station cavern and adits. It summarises the as-encountered ground conditions, aspects of the primary support and permanent lining design that were geotechnically challenging and the solutions developed to meet the project requirements.
布里斯班新的罗马街地铁站是十字河铁路隧道、车站和发展(TSD)计划的一部分。CPB承包商,BAM国际澳大利亚,Ghella和UGL (CBGU JV)的合资企业正在建造5.9公里长的双隧道,从达顿公园站附近的南部隧道入口,布里斯班河和CBD下方到春山的北部隧道入口。跨河铁路项目包括挖掘和建设四个新的地铁站。罗马街车站包括一个280米长的洞穴,五个较小的连接隧道(坑道)和三个竖井。车站洞室的开挖跨度达24.4米,岩石覆盖面积约为15米。它是在Neranleigh-Fernvale群(NFG)岩体中发现的,该岩体由弱变质砂岩(变质灰岩和砂砾岩)、千层岩和次级石英岩和变质玄武岩组成。该站位于诺曼比断裂带内,其特征是一条宽达20米的主要断层,由完整岩石、岩石角砾岩和粘土泥组成。站洞开挖过程中遇到的断层带需要较重的主支护和局部地基处理。洞室和坑道的初始初始(临时)支护由锚杆、锚索锚杆和薄合成纤维增强喷射混凝土衬砌组成。在一些地区,需要被动喷射混凝土拱衬砌。现有巴士道立交桥结构的上覆桩基距隧道开挖轮廓不到一米,因此需要在隧道表面设置复杂的荷载传递结构,并在隧道施工期间验证桩头水平。洞室永久衬砌通常包括顶部的钢纤维增强混凝土,侧壁的钢筋混凝土以及钢筋和钢纤维增强混凝土的倒拱板。在洞室顶部与坑道相交的地方使用钢筋加固。永久结构的地面荷载必须考虑未来发展的影响。本文介绍了车站洞室和坑道的初支护和永久衬砌设计面临的一些挑战。它总结了所遇到的地面条件,主要支撑和永久衬砌设计的各个方面,这些方面在岩土技术上具有挑战性,以及为满足项目要求而开发的解决方案。
{"title":"Design And Construction Of Roma Street Station Cavern, Cross River Rail, Brisbane","authors":"Bernard Shen, Strath Clarke, A. Rogan, P. McCormack","doi":"10.56295/agj5744","DOIUrl":"https://doi.org/10.56295/agj5744","url":null,"abstract":"The new Roma Street underground railway station in Brisbane is being constructed as part of Cross River Rail’s Tunnel, Stations and Development (TSD) package. The joint venture of CPB Contractors, BAM International Australia, Ghella and UGL (CBGU JV) is building the 5.9km long twin tunnels from the Southern Tunnel Portal near Dutton Park station, beneath the Brisbane River and CBD to the Northern Tunnel Portal in Spring Hill. The Cross River Rail project includes excavation and construction of four new underground stations. Roma Street station comprises a 280m long cavern, five smaller connecting tunnels (adits) and three shafts. The station cavern has an excavated span of up to 24.4m with approximately 15m rock cover. It has been excavated within the Neranleigh-Fernvale Group (NFG) rock mass, which comprises weakly metamorphosed sandstone (meta-greywacke and arenite), phyllite and subordinate quartzite and meta-basalt. The station lies within the regional Normanby Fault Zone, characterised by a major fault up to 20m wide comprising a combination of intact rock, rock breccia and clay gouge. The fault zone encountered during the station cavern excavation required heavier primary support and localised foundation treatment. The initial primary (temporary) support of the cavern and adits comprised rock bolts, cable bolts and a thin synthetic fibre-reinforced shotcrete lining. In some areas a passive shotcrete arch lining was required. Overlying piled footings from an existing busway overpass structure were within a metre of the adits’ excavated profile which necessitated a complex load transfer structure at the surface and verification of pile toe levels during tunnel construction. The cavern permanent lining typically comprises steel fibre-reinforced concrete in the crown, bar reinforced concrete for the sidewalls, and bar and steel fibre-reinforced concrete invert slabs. Bar reinforcement is used in the cavern crown where it intersects the adits. Ground loads for the permanent structure had to consider the influence of future developments. This paper presents some of the challenges of the primary support and permanent lining design of the station cavern and adits. It summarises the as-encountered ground conditions, aspects of the primary support and permanent lining design that were geotechnically challenging and the solutions developed to meet the project requirements.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"46838532","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Geotechnical Considerations Associated With The Poatina Power Station Cavern 与Poatina电站洞穴有关的岩土工程考虑
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-12-01 DOI: 10.56295/agj5745
D. Sainsbury, K. Stacey, B. Sainsbury, P. Hills
The Poatina Power Station Cavern was designed with a focus on the newly emerging rock mechanics theory and principles that were rapidly developing during the 1950’s and 60’s. This included measurement of the in-situ rock mass stress condition and photo-elastic analysis of the induced stress around the planned underground openings. These studies led to the adoption of many ‘firsts’ in rock mechanics that included a trapezoidal roof shape, installation of stress relieving slots and fully encapsulated grouted rebar bolts. Based on historical documentation of the construction of the cavern, a three- dimensional numerical model of the cavern construction sequence has been developed. The model is able to provide an accurate match to the observed and monitored ground conditions during construction that includes observed failure modes and instrumentation data. Based on the calibrated model outcomes, Hydro Tasmania was able to undertake a more informed review of the risks associated with the current and future ground support capacity and were able to reliably assess rehabilitation requirements for the cavern support system.
波阿蒂纳发电站洞穴的设计重点是20世纪50年代和60年代快速发展的新兴岩石力学理论和原理。这包括现场岩体应力条件的测量和计划地下开口周围诱导应力的光弹性分析。这些研究导致了岩石力学中许多“第一”的采用,包括梯形屋顶形状、应力消除槽的安装和完全封装的灌浆钢筋螺栓。基于洞室施工的历史文献,建立了洞室施工序列的三维数值模型。该模型能够在施工期间提供与观测和监测到的地面条件的精确匹配,包括观测到的故障模式和仪器数据。根据校准的模型结果,塔斯马尼亚水电公司能够对与当前和未来地面支护能力相关的风险进行更知情的审查,并能够可靠地评估洞穴支护系统的修复要求。
{"title":"Geotechnical Considerations Associated With The Poatina Power Station Cavern","authors":"D. Sainsbury, K. Stacey, B. Sainsbury, P. Hills","doi":"10.56295/agj5745","DOIUrl":"https://doi.org/10.56295/agj5745","url":null,"abstract":"The Poatina Power Station Cavern was designed with a focus on the newly emerging rock mechanics theory and principles that were rapidly developing during the 1950’s and 60’s. This included measurement of the in-situ rock mass stress condition and photo-elastic analysis of the induced stress around the planned underground openings. These studies led to the adoption of many ‘firsts’ in rock mechanics that included a trapezoidal roof shape, installation of stress relieving slots and fully encapsulated grouted rebar bolts. Based on historical documentation of the construction of the cavern, a three- dimensional numerical model of the cavern construction sequence has been developed. The model is able to provide an accurate match to the observed and monitored ground conditions during construction that includes observed failure modes and instrumentation data. Based on the calibrated model outcomes, Hydro Tasmania was able to undertake a more informed review of the risks associated with the current and future ground support capacity and were able to reliably assess rehabilitation requirements for the cavern support system.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"43128584","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
Use of Bitumen Stabilised Limestone in Western Australian Road Pavements 沥青稳定石灰石在西澳大利亚州道路路面中的应用
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-09-01 DOI: 10.56295/agj5732
Jonathon R Griffin, Z. Rice, R. Clayton, Ben Harvey, C. Leek, M. Bondietti, Ross Keeley, G. Cocks
Bitumen emulsion stabilisation of locally available Tamala Limestone was widely used by State and Local Governments from the mid-1960s through the late-1990s, however its use has declined in recent years. This paper aims to substantiate its benefits as a viable alternative material for use on heavily trafficked roads. The benefits provided through stabilisation of crushed limestone with bitumen emulsion include improved workability, reduced ravelling under construction traffic, lower moisture susceptibility and enhanced mechanical properties. Case studies are presented that show that satisfactory performance has been observed where Bitumen Stabilised Limestone (BSL) is used as a basecourse under heavily trafficked roads. The paper provides a construction methodology and discusses barriers and future opportunities. Two structural design approaches are presented for the use of BSL under sprayed seals and thin asphalt surfacings.
从20世纪60年代中期到90年代末,州政府和地方政府广泛使用当地可获得的Tamala石灰石的沥青乳液稳定,但近年来其使用量有所下降。本文旨在证明其作为一种可行的替代材料在交通繁忙的道路上使用的好处。用沥青乳液稳定破碎的石灰石所带来的好处包括改善工作性、减少施工交通中的松散、降低水分敏感性和增强机械性能。案例研究表明,在交通繁忙的道路下使用沥青稳定石灰石(BSL)作为基层时,观察到了令人满意的性能。本文提供了一种构建方法,并讨论了障碍和未来的机遇。针对BSL在喷射密封和薄沥青路面下的应用,提出了两种结构设计方法。
{"title":"Use of Bitumen Stabilised Limestone in Western Australian Road Pavements","authors":"Jonathon R Griffin, Z. Rice, R. Clayton, Ben Harvey, C. Leek, M. Bondietti, Ross Keeley, G. Cocks","doi":"10.56295/agj5732","DOIUrl":"https://doi.org/10.56295/agj5732","url":null,"abstract":"Bitumen emulsion stabilisation of locally available Tamala Limestone was widely used by State and Local Governments from the mid-1960s through the late-1990s, however its use has declined in recent years. This paper aims to substantiate its benefits as a viable alternative material for use on heavily trafficked roads. The benefits provided through stabilisation of crushed limestone with bitumen emulsion include improved workability, reduced ravelling under construction traffic, lower moisture susceptibility and enhanced mechanical properties. Case studies are presented that show that satisfactory performance has been observed where Bitumen Stabilised Limestone (BSL) is used as a basecourse under heavily trafficked roads. The paper provides a construction methodology and discusses barriers and future opportunities. Two structural design approaches are presented for the use of BSL under sprayed seals and thin asphalt surfacings.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"48913000","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Bulli Pass Landslide Risk Management Part 1 - Hazard Assessment 布利山口滑坡风险管理第1部分-危险性评估
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-09-01 DOI: 10.56295/agj5735
Andrew Hunter, P. Flentje, Alan Moon
The Princes Highway along Bulli Pass is a narrow, heavily trafficked two lane section of the Princes Highway that traverses steep slopes on a grade of 9H:1V on the Illawarra Escarpment, about 11 km north of Wollongong, and 75 km south of Sydney in New South Wales (NSW), Australia. It is an important arterial road for the northern suburbs of Wollongong, connecting Mt Ousley Road (M1 Princes Motorway) at the crest of the escarpment to the suburb of Thirroul on the coastal plain at the base of the escarpment. Bulli Pass has a long history of landslide and rockfall events, some of which were reported as early as 1890. One of the most significant of these events occurred on 17 August 1998 during a 1 in 100 year rainfall event. The 1998 landslide event comprised approximately 38 debris flows and slides and numerous rockfalls which partially inundated a number of cars and trapped about 15 cars on the pass. More recently, in early 2015, a small rockfall penetrated the windscreen of a car travelling up the pass. Transport for New South Wales (TfNSW) commissioned an investigation into slope instability hazards affecting the road in late 2011. This was followed in 2015 by a Risk Mitigation Options study and the detailed design of risk mitigation works in 2016. This paper provides an overview of the methods used to investigate hazards and assess risk at the site over a five year period. This has included research into the landslide history, geomorphological mapping, acquisition and review of airborne laser scanning (ALS) data, review of rainfall data and the development of a landslide volume frequency model. The development of this model allowed hazards to be readily communicated and risks to be assessed. The actual design and construction of the Shallow Landslide Barriers and the Debris Flow Barriers that followed on from these assessments will be discussed in a subsequent companion paper.
沿着布里山口的王子公路是王子公路的一条狭窄、交通繁忙的双车道路段,穿过澳大利亚新南威尔士州(NSW)的伊拉瓦拉悬崖上坡度为9H:1V的陡坡,距离卧龙岗以北约11公里,悉尼以南75公里。它是卧龙岗北郊的一条重要干道,连接悬崖顶部的奥斯利山公路(M1王子高速公路)和悬崖底部沿海平原上的Thirroul郊区。布里山口有着悠久的滑坡和落石事件历史,其中一些事件早在1890年就有报道。其中最重要的一次事件发生在1998年8月17日,当时的降雨量为百分之一。1998年的山体滑坡事件包括大约38个泥石流、滑坡和大量落石,部分淹没了一些汽车,并将大约15辆汽车困在了山口上。最近,在2015年初,一个小落石穿透了一辆沿山口行驶的汽车的挡风玻璃。新南威尔士州交通局(TfNSW)于2011年末委托对影响道路的边坡不稳定危险进行调查。随后在2015年进行了风险缓解方案研究,并在2016年详细设计了风险缓解工程。本文概述了在五年内用于调查现场危险和评估风险的方法。这包括对滑坡历史的研究、地貌测绘、机载激光扫描(ALS)数据的获取和审查、降雨数据的审查以及滑坡体频率模型的开发。该模型的开发使危险可以很容易地进行沟通,并对风险进行评估。这些评估之后的浅层滑坡屏障和泥石流屏障的实际设计和施工将在随后的配套文件中进行讨论。
{"title":"Bulli Pass Landslide Risk Management Part 1 - Hazard Assessment","authors":"Andrew Hunter, P. Flentje, Alan Moon","doi":"10.56295/agj5735","DOIUrl":"https://doi.org/10.56295/agj5735","url":null,"abstract":"The Princes Highway along Bulli Pass is a narrow, heavily trafficked two lane section of the Princes Highway that traverses steep slopes on a grade of 9H:1V on the Illawarra Escarpment, about 11 km north of Wollongong, and 75 km south of Sydney in New South Wales (NSW), Australia. It is an important arterial road for the northern suburbs of Wollongong, connecting Mt Ousley Road (M1 Princes Motorway) at the crest of the escarpment to the suburb of Thirroul on the coastal plain at the base of the escarpment. Bulli Pass has a long history of landslide and rockfall events, some of which were reported as early as 1890. One of the most significant of these events occurred on 17 August 1998 during a 1 in 100 year rainfall event. The 1998 landslide event comprised approximately 38 debris flows and slides and numerous rockfalls which partially inundated a number of cars and trapped about 15 cars on the pass. More recently, in early 2015, a small rockfall penetrated the windscreen of a car travelling up the pass. Transport for New South Wales (TfNSW) commissioned an investigation into slope instability hazards affecting the road in late 2011. This was followed in 2015 by a Risk Mitigation Options study and the detailed design of risk mitigation works in 2016. This paper provides an overview of the methods used to investigate hazards and assess risk at the site over a five year period. This has included research into the landslide history, geomorphological mapping, acquisition and review of airborne laser scanning (ALS) data, review of rainfall data and the development of a landslide volume frequency model. The development of this model allowed hazards to be readily communicated and risks to be assessed. The actual design and construction of the Shallow Landslide Barriers and the Debris Flow Barriers that followed on from these assessments will be discussed in a subsequent companion paper.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"46205709","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
Thornthwaite Moisture Index and Climate Zones in the Northern Territory Thornthwaite湿度指数和北领地气候带
IF 0.2 Q4 Earth and Planetary Sciences Pub Date : 2022-09-01 DOI: 10.56295/agj5733
Stephen Jackson
The Thornthwaite Moisture Index (TMI) is an established climate parameter for geotechnical engineers to categorise a site and enable estimation of seasonal ground movements associated with soil moisture changes. TMI assessment and mapping for the Northern Territory are presented, using the TMI calculation method commonly used for similar recent studies elsewhere in Australia. The assessment included the analysis of 17 sites within the Northern Territory and one site in Queensland which has enabled development of Climate Zone classifications. Climate data was obtained from the Australian Bureau of Meteorology to calculate the TMI on a ‘year by year’ basis over a target period of 29 years (1990 to 2019). Related work in Queensland (Fox 2002) and Western Australia (Hu et al, 2016) has guided the development of the Northern Territory Climate Zone Map. Further work is required to characterise the soil moisture behaviour in arid zones. A general lack of guidance in AS2870 (2011) for arid areas, including much of the Northern Territory, could be addressed with further research and development.
Thornthwaite湿度指数(TMI)是岩土工程师对场地进行分类并能够估计与土壤湿度变化相关的季节性地面运动的既定气候参数。采用澳大利亚其他地方最近进行的类似研究中常用的TMI计算方法,对北领地的TMI进行了评估和绘制。评估包括对北领地的17个地点和昆士兰的一个地点的分析,这使得气候区分类得以发展。气候数据是从澳大利亚气象局获得的,用于在29年(1990年至2019年)的目标期内“逐年”计算TMI。昆士兰(Fox 2002)和西澳大利亚(Hu et al,2016)的相关工作指导了北领地气候带图的绘制。需要进一步的工作来表征干旱地区的土壤水分行为。AS2870(2011)中普遍缺乏对干旱地区(包括北领地大部分地区)的指导,可以通过进一步的研究和开发来解决。
{"title":"Thornthwaite Moisture Index and Climate Zones in the Northern Territory","authors":"Stephen Jackson","doi":"10.56295/agj5733","DOIUrl":"https://doi.org/10.56295/agj5733","url":null,"abstract":"The Thornthwaite Moisture Index (TMI) is an established climate parameter for geotechnical engineers to categorise a site and enable estimation of seasonal ground movements associated with soil moisture changes. TMI assessment and mapping for the Northern Territory are presented, using the TMI calculation method commonly used for similar recent studies elsewhere in Australia. The assessment included the analysis of 17 sites within the Northern Territory and one site in Queensland which has enabled development of Climate Zone classifications. Climate data was obtained from the Australian Bureau of Meteorology to calculate the TMI on a ‘year by year’ basis over a target period of 29 years (1990 to 2019). Related work in Queensland (Fox 2002) and Western Australia (Hu et al, 2016) has guided the development of the Northern Territory Climate Zone Map. Further work is required to characterise the soil moisture behaviour in arid zones. A general lack of guidance in AS2870 (2011) for arid areas, including much of the Northern Territory, could be addressed with further research and development.","PeriodicalId":43619,"journal":{"name":"Australian Geomechanics Journal","volume":null,"pages":null},"PeriodicalIF":0.2,"publicationDate":"2022-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"41869873","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
期刊
Australian Geomechanics Journal
全部 Acc. Chem. Res. ACS Applied Bio Materials ACS Appl. Electron. Mater. ACS Appl. Energy Mater. ACS Appl. Mater. Interfaces ACS Appl. Nano Mater. ACS Appl. Polym. Mater. ACS BIOMATER-SCI ENG ACS Catal. ACS Cent. Sci. ACS Chem. Biol. ACS Chemical Health & Safety ACS Chem. Neurosci. ACS Comb. Sci. ACS Earth Space Chem. ACS Energy Lett. ACS Infect. Dis. ACS Macro Lett. ACS Mater. Lett. ACS Med. Chem. Lett. ACS Nano ACS Omega ACS Photonics ACS Sens. ACS Sustainable Chem. Eng. ACS Synth. Biol. Anal. Chem. BIOCHEMISTRY-US Bioconjugate Chem. BIOMACROMOLECULES Chem. Res. Toxicol. Chem. Rev. Chem. Mater. CRYST GROWTH DES ENERG FUEL Environ. Sci. Technol. Environ. Sci. Technol. Lett. Eur. J. Inorg. Chem. IND ENG CHEM RES Inorg. Chem. J. Agric. Food. Chem. J. Chem. Eng. Data J. Chem. Educ. J. Chem. Inf. Model. J. Chem. Theory Comput. J. Med. Chem. J. Nat. Prod. J PROTEOME RES J. Am. Chem. Soc. LANGMUIR MACROMOLECULES Mol. Pharmaceutics Nano Lett. Org. Lett. ORG PROCESS RES DEV ORGANOMETALLICS J. Org. Chem. J. Phys. Chem. J. Phys. Chem. A J. Phys. Chem. B J. Phys. Chem. C J. Phys. Chem. Lett. Analyst Anal. Methods Biomater. Sci. Catal. Sci. Technol. Chem. Commun. Chem. Soc. Rev. CHEM EDUC RES PRACT CRYSTENGCOMM Dalton Trans. Energy Environ. Sci. ENVIRON SCI-NANO ENVIRON SCI-PROC IMP ENVIRON SCI-WAT RES Faraday Discuss. Food Funct. Green Chem. Inorg. Chem. Front. Integr. Biol. J. Anal. At. Spectrom. J. Mater. Chem. A J. Mater. Chem. B J. Mater. Chem. C Lab Chip Mater. Chem. Front. Mater. Horiz. MEDCHEMCOMM Metallomics Mol. Biosyst. Mol. Syst. Des. Eng. Nanoscale Nanoscale Horiz. Nat. Prod. Rep. New J. Chem. Org. Biomol. Chem. Org. Chem. Front. PHOTOCH PHOTOBIO SCI PCCP Polym. Chem.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1