首页 > 最新文献

Day 3 Thu, March 24, 2022最新文献

英文 中文
Electrification Transformation from Offshore Power Grid to Power from Shore, a Case Study to Minimize Carbon Emissions for Two Extensive Offshore Oil Fields 从海上电网到岸上电力的电气化转型——两个大型海上油田减少碳排放的案例研究
Pub Date : 2022-03-18 DOI: 10.4043/31550-ms
Yiru Hu, H. Zhang, Yinfeng Qiu
With China committing to achieve carbon neutrality before 2060, the operator has set ambitious targets for minimizing carbon emissions from its oil and gas operations. Two extensive offshore oil fields – QHD32-6 and CDF 11-1 oil fields have been modified to transform its power solution from offshore generation to power from shore (PFS) to reduce carbon emission, improve offshore energy efficiency etc. The two fields comprise 25 production platforms, 2 FPSO with 21 crude oil generators and 9 gas turbine generators. The total peak power demand is about 200MW. Both QHD32-6 and CDF 11-1 oil fields have established their own offshore micro power grid by interlinking centralized offshore generation platforms via 35kV and 10kV submarine cables. This paper first reviews the company strategic factors as well as the national regulatory drivers behind the decision to pursue whole-scale electrification of two super complex offshore oil fields. It then explores technology challenges and solutions by means of a high voltage AC PFS such as tie-in point selection, reactive compensation considerations, key economic criteria such as operation and energy costs, and asset depreciation etc. Considering the consequences of production loss due to power outage, stringent reliability requirements were adopted. A high-speed transfer combine with a 62.3km 110kV interconnecting submarine cable between QHD32-6 and CFD11-1 offshore substations is first introduced in offshore PFS installations. Detailed configuration and its power supply continuity benefit will be discussed. Finally, major cost reduction measures such as unman and digitalization design of 220kV PFS substation are summarized, with lessons learned in a successful development of extensive on-stream oil fields electrification transformation. This electrification transformation is expected to reduce about a total 2.52 million tons of CO2 and 0.067 million tons of NOx emissions, save 2.17 billion cubic meters of fuel gas and 1.13 million tons of standard coals. In September 2021, QHD32-6 and CFD11-1 offshore oil fields have been completed the transformation and back into production. Although on account of a total 132km submarine cables and 200MW power demand, high voltage D.C. is traditionally the first choice, this paper demonstrates high voltage A.C. can be flexibly utilized for long distance large power demand by careful design. While for many upcoming offshore projects, PFS solutions have become attractive in an effort to reduce environmental footprint, this paper presents an on-stream offshore oil fields PFS transformation, extra considerations need to be addressed. The high-speed transfer solution is first used in PFS engineering that can limit a power switching time to milliseconds, exploring a new way to significantly improve power supply continuity with limited investment. Another new information is the unmanned and intelligent design of substations to increase asset adaptability, maintain system relia
随着中国承诺在2060年之前实现碳中和,该运营商制定了雄心勃勃的目标,以最大限度地减少其油气业务的碳排放。两个大型海上油田——QHD32-6和CDF 11-1油田已经被改造,将其电力解决方案从海上发电转变为岸上发电(PFS),以减少碳排放,提高海上能源效率等。这两个油田包括25个生产平台,2个FPSO, 21个原油发电机和9个燃气轮机发电机。总峰值电力需求约200MW。QHD32-6和CDF 11-1油田都通过35kV和10kV海底电缆将海上集中发电平台互联,建立了自己的海上微电网。本文首先回顾了公司的战略因素以及国家监管驱动因素,决定在两个超级复杂的海上油田进行全面电气化。然后,通过高压交流PFS探讨技术挑战和解决方案,如接入点选择,无功补偿考虑,关键经济标准,如运营和能源成本,以及资产折旧等。考虑到停电造成的生产损失,采用了严格的可靠性要求。QHD32-6和CFD11-1海上变电站之间的高速传输组合和62.3公里110kV海底互连电缆首次引入海上PFS装置。详细的配置和它的电源连续性效益将讨论。最后总结了220kV PFS变电站的人性化设计、数字化设计等主要降本措施,总结了油田大范围电气化改造的成功发展经验。此次电气化改造预计将减少约252万吨二氧化碳和0.067万吨氮氧化物排放,节约21.7亿立方米燃气和113万吨标准煤。2021年9月,QHD32-6和CFD11-1海上油田完成改造并恢复生产。虽然由于海底电缆总长132km,电力需求200MW,传统上高压直流是首选,但通过精心设计,可以灵活地利用高压交流来满足长距离大电力需求。虽然对于许多即将到来的海上项目来说,PFS解决方案在减少环境足迹方面变得越来越有吸引力,但本文提出了海上油田的PFS改造,需要解决额外的考虑因素。高速传输解决方案首次用于PFS工程,可以将电源切换时间限制在毫秒级,探索了以有限投资显着提高电源连续性的新方法。另一个新信息是变电站的无人和智能设计,以增加资产适应性,保持系统可靠性并最大限度地降低人工成本。
{"title":"Electrification Transformation from Offshore Power Grid to Power from Shore, a Case Study to Minimize Carbon Emissions for Two Extensive Offshore Oil Fields","authors":"Yiru Hu, H. Zhang, Yinfeng Qiu","doi":"10.4043/31550-ms","DOIUrl":"https://doi.org/10.4043/31550-ms","url":null,"abstract":"\u0000 With China committing to achieve carbon neutrality before 2060, the operator has set ambitious targets for minimizing carbon emissions from its oil and gas operations. Two extensive offshore oil fields – QHD32-6 and CDF 11-1 oil fields have been modified to transform its power solution from offshore generation to power from shore (PFS) to reduce carbon emission, improve offshore energy efficiency etc. The two fields comprise 25 production platforms, 2 FPSO with 21 crude oil generators and 9 gas turbine generators. The total peak power demand is about 200MW. Both QHD32-6 and CDF 11-1 oil fields have established their own offshore micro power grid by interlinking centralized offshore generation platforms via 35kV and 10kV submarine cables.\u0000 This paper first reviews the company strategic factors as well as the national regulatory drivers behind the decision to pursue whole-scale electrification of two super complex offshore oil fields. It then explores technology challenges and solutions by means of a high voltage AC PFS such as tie-in point selection, reactive compensation considerations, key economic criteria such as operation and energy costs, and asset depreciation etc. Considering the consequences of production loss due to power outage, stringent reliability requirements were adopted. A high-speed transfer combine with a 62.3km 110kV interconnecting submarine cable between QHD32-6 and CFD11-1 offshore substations is first introduced in offshore PFS installations. Detailed configuration and its power supply continuity benefit will be discussed. Finally, major cost reduction measures such as unman and digitalization design of 220kV PFS substation are summarized, with lessons learned in a successful development of extensive on-stream oil fields electrification transformation.\u0000 This electrification transformation is expected to reduce about a total 2.52 million tons of CO2 and 0.067 million tons of NOx emissions, save 2.17 billion cubic meters of fuel gas and 1.13 million tons of standard coals. In September 2021, QHD32-6 and CFD11-1 offshore oil fields have been completed the transformation and back into production. Although on account of a total 132km submarine cables and 200MW power demand, high voltage D.C. is traditionally the first choice, this paper demonstrates high voltage A.C. can be flexibly utilized for long distance large power demand by careful design.\u0000 While for many upcoming offshore projects, PFS solutions have become attractive in an effort to reduce environmental footprint, this paper presents an on-stream offshore oil fields PFS transformation, extra considerations need to be addressed. The high-speed transfer solution is first used in PFS engineering that can limit a power switching time to milliseconds, exploring a new way to significantly improve power supply continuity with limited investment. Another new information is the unmanned and intelligent design of substations to increase asset adaptability, maintain system relia","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"114 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"87965830","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
Successful Delivery of Slim Well Design Concept for Future Marginal Fields 成功交付未来边缘油田小井设计理念
Pub Date : 2022-03-18 DOI: 10.4043/31357-ms
Nurul Nadia Ezzatty Abu Bakar, M. Hod, M. A. Abitalhah, A. F. Omar, Hazlan Abdul Hakim
This paper will discuss the key focus areas in successfully delivering a slim well design as a Proof Of Concept (POC) for marginal fields and well cost optimization. Well Tall-A is a Near Field Exploration (NFE) well targeting marginal reservoir which utilize the slim well concept; a 2-hole section well with 9-5/8" as the conductor. For a successful well execution, three (3) key focus areas were identified which are successful operation of 9-5/8" Casing While Drilling (CWD) to section TD, sustainability of 9-5/8" casing as conductor for the whole well life cycle and achievement of well objectives. Tall-A recorded the longest and successful 9-5/8" CWD Level 2 (non-directional) for Asia Pacific with 1168m drilled footage as of year 2020. Lessons learnt from previous PCSB 9-5/8" CWD operation were incorporated for casing bit selection hence a heavy-set casing bit (8 bladed) which has been proven in drilling long hole interval in the Middle East (>1000m) was utilized. Continuous monitoring during execution is essential in ensuring the casing is set at the desired setting depth. Sustainability of the 9-5/8" casing as conductor for the whole well life cycle is critical for a slim well design concept. Several studies and extensive discussions between multiple parties has been incorporated to enable utilization of the 9-5/8" as conductor with required sufficient tension to sustain the exploration well lifecycle. A conductor study was performed which incorporated the Metocean data, rig data and connection Stress Concentration Fatigue (SCF) to qualify the 9-5/8" as conductor. To meet the primary and secondary targets; the 8-1/2" hole needs to be kicked-off early and build up to maximum 44 deg before maintain tangent to final TD at 2752m MDDF. Due to the long open hole (1475m) and well inclination within the avalanche hole cleaning regime (30 to 60 deg), the well is prone to hole cleaning problem and wellbore instability. Hence, it is critical to have good drilling practices and precise mud weight selection to ensure no hole problem encountered. The well was successfully drilled to TD, completed the well testing and P&A. In summary, well Tall-A successfully maneuvered all challenges to deliver the well safely that resulted in Best In Class (BIC) performance. The slim well design concept has been proven achievable and serve as base design for future marginal wells.
本文将讨论成功交付小井设计的关键领域,作为边际油田的概念验证(POC)和井成本优化。Tall-A井是利用小井概念开发的边缘油气藏近场勘探井;以9-5/8”为导体的2孔分段井。为了成功的钻井作业,确定了三个关键的重点领域,即9-5/8”随钻套管(CWD)的成功作业到TD段,9-5/8”套管在整个井生命周期中的可持续性以及井目标的实现。截至2020年,Tall-A在亚太地区创下了最长且成功的9-5/8”CWD 2级(非定向)钻井记录,钻井进尺为1168米。从之前的PCSB 9-5/8”CWD作业中吸取的经验教训被用于套管钻头的选择,因此使用了重型套管钻头(8片),该钻头在中东的长井段(>1000米)的钻井中得到了验证。在执行过程中,连续监测对于确保套管在所需的坐封深度下坐封至关重要。在整个井生命周期内,9-5/8”套管作为导管的可持续性对于小井设计理念至关重要。各方进行了多次研究和广泛讨论,最终确定了采用9-5/8”作为导通,并提供足够的张力,以维持探井的生命周期。结合metoocean数据、钻机数据和连接应力集中疲劳(SCF),进行了一项导线研究,以确定9-5/8”为导线。完成主要目标和次要目标;8-1/2”井眼需要尽早起下钻,并最大达44度,然后在MDDF 2752米处与最终TD保持相切。由于裸眼井长(1475米),井斜在雪崩井眼清洗范围内(30 ~ 60度),容易出现井眼清洗问题和井筒不稳定。因此,良好的钻井作业和精确的泥浆比重选择至关重要,以确保不会遇到任何井眼问题。该井成功钻至TD,完成了试井和弃井作业。综上所述,Tall-A井成功应对了所有挑战,安全交付了该井,取得了同类最佳(BIC)性能。小井设计理念已被证明是可行的,并可作为未来边际井的基础设计。
{"title":"Successful Delivery of Slim Well Design Concept for Future Marginal Fields","authors":"Nurul Nadia Ezzatty Abu Bakar, M. Hod, M. A. Abitalhah, A. F. Omar, Hazlan Abdul Hakim","doi":"10.4043/31357-ms","DOIUrl":"https://doi.org/10.4043/31357-ms","url":null,"abstract":"\u0000 This paper will discuss the key focus areas in successfully delivering a slim well design as a Proof Of Concept (POC) for marginal fields and well cost optimization.\u0000 Well Tall-A is a Near Field Exploration (NFE) well targeting marginal reservoir which utilize the slim well concept; a 2-hole section well with 9-5/8\" as the conductor. For a successful well execution, three (3) key focus areas were identified which are successful operation of 9-5/8\" Casing While Drilling (CWD) to section TD, sustainability of 9-5/8\" casing as conductor for the whole well life cycle and achievement of well objectives.\u0000 Tall-A recorded the longest and successful 9-5/8\" CWD Level 2 (non-directional) for Asia Pacific with 1168m drilled footage as of year 2020. Lessons learnt from previous PCSB 9-5/8\" CWD operation were incorporated for casing bit selection hence a heavy-set casing bit (8 bladed) which has been proven in drilling long hole interval in the Middle East (>1000m) was utilized. Continuous monitoring during execution is essential in ensuring the casing is set at the desired setting depth. Sustainability of the 9-5/8\" casing as conductor for the whole well life cycle is critical for a slim well design concept. Several studies and extensive discussions between multiple parties has been incorporated to enable utilization of the 9-5/8\" as conductor with required sufficient tension to sustain the exploration well lifecycle. A conductor study was performed which incorporated the Metocean data, rig data and connection Stress Concentration Fatigue (SCF) to qualify the 9-5/8\" as conductor. To meet the primary and secondary targets; the 8-1/2\" hole needs to be kicked-off early and build up to maximum 44 deg before maintain tangent to final TD at 2752m MDDF. Due to the long open hole (1475m) and well inclination within the avalanche hole cleaning regime (30 to 60 deg), the well is prone to hole cleaning problem and wellbore instability. Hence, it is critical to have good drilling practices and precise mud weight selection to ensure no hole problem encountered. The well was successfully drilled to TD, completed the well testing and P&A.\u0000 In summary, well Tall-A successfully maneuvered all challenges to deliver the well safely that resulted in Best In Class (BIC) performance. The slim well design concept has been proven achievable and serve as base design for future marginal wells.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"70 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"84412922","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Biggest Wells Plug and Abandonment Campaign – Effective Management & Best Practices Implementation 最大规模的封井和弃井作业——有效的管理和最佳实践实施
Pub Date : 2022-03-18 DOI: 10.4043/31403-ms
Azwan Azim Azihar, Maziah Abu Mukhtar, Shahril Yang, M. Z. A Razak, A. Z. A Rajab, M. A. Tumiran
This paper covers the strategy that led to successful execution of Plug and Abandonment (P&A) campaign. This paper also shares the best practices implementation, and challenges in completion of the biggest plug and abandonment campaign at Alpha Platform in Peninsular Malaysia. Among the challenges are aging wells with numerous integrity issues, well sequence selection and prioritization, monsoon season, stakeholder management as well as piloting new technology applications. In the last 5 years, there are over 50 wells have been successfully abandoned in Malaysia water. The generic abandonment project management framework consists of Initiation Stage, Concept Selection, Scope Definition, Execution, and Post Execution; Close Out. The scope for this paper will detail out the levels for abandonment planning. Screening and clustering, fit-for-purpose strategy, novel technology, innovative contracting strategy are among the pillars in abandonment planning and execution. Effective tools and matrix have been introduced to evaluate the wells candidates. Execution phase is narrowed down to several approaches and best practices that have been implemented to successfully complete all wells at Alpha Platform. The approaches have been customized to safely abandon wells with sustained annulus pressure (SAP) in compliance with the country's regulations. In-depth well study and aggressively piloting new technology are among the keys to tackle numerous well integrity issue in 40 years old wells e.g shallow gas, casing leak, wellhead, and Christmas tree leak. Vigilant logistic management and integrated contract approach also play important roles in reducing the risk and liability to the operator and at the same time developing local players’ capability. The strategy and best practices in completing plug and abandonment of Alpha Platform should be replicated by P&A industry to manage the similar issue in other projects. Integrated and fit-for-purpose abandonment approach act as the foundation to model invaluable high-quality planning, forecasting and Value Creation Plan for P&A project portfolio. This paper will be useful in P&A industry where a lot of lessons learned to be shared in the biggest campaign in Malaysia.
本文介绍了成功执行封井弃井(P&A)作业的策略。本文还分享了在马来西亚半岛Alpha平台完成最大封井弃井作业的最佳实践和挑战。面临的挑战包括井龄老化、井序选择和优先排序、季风季节、利益相关者管理以及新技术应用的试点。在过去的5年里,马来西亚水域有50多口井被成功废弃。通用废弃项目管理框架包括启动阶段、概念选择、范围定义、执行和后期执行;关闭。本文的范围将详细说明废弃规划的级别。筛选和聚类、符合目的策略、新技术、创新承包策略是废弃规划和执行的支柱。引入了有效的工具和矩阵来评估候选井。执行阶段被缩小到几个方法和最佳实践,这些方法和实践已经成功地完成了Alpha平台的所有井。这些方法经过定制,可以在符合国家规定的持续环空压力(SAP)下安全弃井。深入的井研究和积极的新技术试验是解决40年井井完整性问题的关键之一,例如浅层气、套管泄漏、井口泄漏和采油树泄漏。警惕的物流管理和综合合同方式在降低运营商的风险和责任,同时发展当地参与者的能力方面也发挥了重要作用。封堵弃井的策略和最佳实践应该被封堵弃井行业复制,以管理其他项目中的类似问题。综合和适合目的的放弃方法是为P&A项目组合建模宝贵的高质量计划、预测和价值创造计划的基础。这篇论文将对P&A行业有用,因为在马来西亚最大的活动中,有很多经验教训可以分享。
{"title":"Biggest Wells Plug and Abandonment Campaign – Effective Management & Best Practices Implementation","authors":"Azwan Azim Azihar, Maziah Abu Mukhtar, Shahril Yang, M. Z. A Razak, A. Z. A Rajab, M. A. Tumiran","doi":"10.4043/31403-ms","DOIUrl":"https://doi.org/10.4043/31403-ms","url":null,"abstract":"\u0000 This paper covers the strategy that led to successful execution of Plug and Abandonment (P&A) campaign. This paper also shares the best practices implementation, and challenges in completion of the biggest plug and abandonment campaign at Alpha Platform in Peninsular Malaysia. Among the challenges are aging wells with numerous integrity issues, well sequence selection and prioritization, monsoon season, stakeholder management as well as piloting new technology applications.\u0000 In the last 5 years, there are over 50 wells have been successfully abandoned in Malaysia water. The generic abandonment project management framework consists of Initiation Stage, Concept Selection, Scope Definition, Execution, and Post Execution; Close Out. The scope for this paper will detail out the levels for abandonment planning. Screening and clustering, fit-for-purpose strategy, novel technology, innovative contracting strategy are among the pillars in abandonment planning and execution. Effective tools and matrix have been introduced to evaluate the wells candidates. Execution phase is narrowed down to several approaches and best practices that have been implemented to successfully complete all wells at Alpha Platform. The approaches have been customized to safely abandon wells with sustained annulus pressure (SAP) in compliance with the country's regulations. In-depth well study and aggressively piloting new technology are among the keys to tackle numerous well integrity issue in 40 years old wells e.g shallow gas, casing leak, wellhead, and Christmas tree leak. Vigilant logistic management and integrated contract approach also play important roles in reducing the risk and liability to the operator and at the same time developing local players’ capability.\u0000 The strategy and best practices in completing plug and abandonment of Alpha Platform should be replicated by P&A industry to manage the similar issue in other projects. Integrated and fit-for-purpose abandonment approach act as the foundation to model invaluable high-quality planning, forecasting and Value Creation Plan for P&A project portfolio. This paper will be useful in P&A industry where a lot of lessons learned to be shared in the biggest campaign in Malaysia.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"18 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"73654072","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Digital Transformation for the Gulf of Thailand's Assets Condensate Stabilizer Real-Time Optimization 泰国湾资产凝析油稳定器实时优化的数字化转型
Pub Date : 2022-03-18 DOI: 10.4043/31363-ms
N. Atibodhi, Supha-Kitti Dhadachaipathomphong, F. Nazir, Nathachok Namwong
PTTEP's natural gas fields in Gulf of Thailand, has encountered losses in Condensate yield due to suboptimal operating conditions as variation in feed compositions occurs when production line up changes. As a result of this suboptimal operation, some light Condensate is lost into gas phase resulting in lower overall profitability. As part of company's Digital Transformation initiatives, a Condensate Stabilizer Optimization (CSO) solution has been implemented to minimize or eliminate these losses. The objective of CSO is to provide real-time recommended operating conditions to maximize condensate production while maintaining sale condensate specification using optimization technology that considers all relevant condensate stabilization process parameters. The CSO solution leverages Multivariable Predictive Control or Model Predictive Control (MPC) technology and communicates the obtained results to offshore teams via an online web user interface. Besides the dynamic models and MPC technology, the solution also includes an important component of the CSO solution which is the web based online dashboards as they are the key to communicate between the solution and the users. The dashboards include the following key features: – Key operating parameters of Condensate Stabilizer Units including Controlled, Manipulated, and Disturbance Variables – Recommended optimal values of Manipulated Variables to achieve maximum condensate production – Difference between actual vs predicted RVP. This is to visualize current model accuracy – Captured Benefit As of December 2021, the CSO solution has been fully utilized for 5 months, i.e. Go-Live since August 2021. During this period, it has successfully delivered not only safe operating window but also benefits which adds up to 1.49 MUSD/year. As the benefits of the solution have been proven, a plan to proceed with Phase 2 of this project, in which the CSO solution will be integrated with the Distributed Control System (DCS) allowing MPC Controller to automatically adjust process parameters to achieve the most optimal conditions, has been set. Apart from process optimization, the CSO solution can be used to evaluate operating scenarios based on given simulated process parameters, thus becoming a true "Digital Twin" of the Condensate Stabilizer that can replicate its operation at different operating conditions.
PTTEP在泰国湾的天然气田,由于生产线变化时饲料成分的变化,导致操作条件不理想,导致凝析油产量损失。由于这种不理想的操作,一些轻凝析油损失到气相,导致整体盈利能力降低。作为公司数字化转型计划的一部分,冷凝稳定剂优化(CSO)解决方案已经实施,以尽量减少或消除这些损失。CSO的目标是提供实时推荐的操作条件,以最大限度地提高凝析油产量,同时使用优化技术,考虑所有相关的凝析油稳定过程参数,保持销售凝析油规格。CSO解决方案利用多变量预测控制或模型预测控制(MPC)技术,并通过在线web用户界面将获得的结果传达给海上团队。除了动态模型和MPC技术外,该解决方案还包括CSO解决方案的一个重要组成部分,即基于web的在线仪表板,因为它们是解决方案与用户之间通信的关键。仪表板包括以下主要功能:—凝析油稳定器单元的关键操作参数,包括受控变量、被操纵变量和干扰变量—被操纵变量的推荐最佳值,以实现最大的凝析油产量—实际RVP与预测RVP之间的差异。截至2021年12月,CSO解决方案已经充分利用了5个月,即自2021年8月起投入使用。在此期间,它不仅成功地提供了安全的操作窗口,而且还获得了每年1.49亿美元的收益。由于该解决方案的优势已被证明,因此计划继续进行该项目的第二阶段,其中CSO解决方案将与分布式控制系统(DCS)集成,允许MPC控制器自动调整工艺参数以达到最佳状态。除了流程优化之外,CSO解决方案还可以根据给定的模拟过程参数来评估操作方案,从而成为凝析油稳定器的真正“数字孪生”,可以在不同的操作条件下复制其操作。
{"title":"Digital Transformation for the Gulf of Thailand's Assets Condensate Stabilizer Real-Time Optimization","authors":"N. Atibodhi, Supha-Kitti Dhadachaipathomphong, F. Nazir, Nathachok Namwong","doi":"10.4043/31363-ms","DOIUrl":"https://doi.org/10.4043/31363-ms","url":null,"abstract":"\u0000 PTTEP's natural gas fields in Gulf of Thailand, has encountered losses in Condensate yield due to suboptimal operating conditions as variation in feed compositions occurs when production line up changes. As a result of this suboptimal operation, some light Condensate is lost into gas phase resulting in lower overall profitability.\u0000 As part of company's Digital Transformation initiatives, a Condensate Stabilizer Optimization (CSO) solution has been implemented to minimize or eliminate these losses. The objective of CSO is to provide real-time recommended operating conditions to maximize condensate production while maintaining sale condensate specification using optimization technology that considers all relevant condensate stabilization process parameters.\u0000 The CSO solution leverages Multivariable Predictive Control or Model Predictive Control (MPC) technology and communicates the obtained results to offshore teams via an online web user interface.\u0000 Besides the dynamic models and MPC technology, the solution also includes an important component of the CSO solution which is the web based online dashboards as they are the key to communicate between the solution and the users. The dashboards include the following key features:\u0000 – Key operating parameters of Condensate Stabilizer Units including Controlled, Manipulated, and Disturbance Variables – Recommended optimal values of Manipulated Variables to achieve maximum condensate production – Difference between actual vs predicted RVP. This is to visualize current model accuracy – Captured Benefit\u0000 As of December 2021, the CSO solution has been fully utilized for 5 months, i.e. Go-Live since August 2021. During this period, it has successfully delivered not only safe operating window but also benefits which adds up to 1.49 MUSD/year. As the benefits of the solution have been proven, a plan to proceed with Phase 2 of this project, in which the CSO solution will be integrated with the Distributed Control System (DCS) allowing MPC Controller to automatically adjust process parameters to achieve the most optimal conditions, has been set.\u0000 Apart from process optimization, the CSO solution can be used to evaluate operating scenarios based on given simulated process parameters, thus becoming a true \"Digital Twin\" of the Condensate Stabilizer that can replicate its operation at different operating conditions.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"108 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"79209597","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Comparative Review Study on Different Carbon Capture Methods and Applications in Steelmaking Plant from Economical Point of View 从经济角度对不同碳捕集方法及其在炼钢厂应用的比较研究
Pub Date : 2022-03-18 DOI: 10.4043/31540-ms
Thinesh Shakkti Arul Rajoo, K. Elraies, U. Z. Husna, Juhairi Aris Muhamad Shuhili, Mohd Afandi Abu Bakar, Hazliza Haron, Ismail Mohd Saaid, J. Lee, M. N. Mohamad Ibrahim, S. B. Gogoi, A. Saeedi
One of the emerging areas in combatting environmental issue like global warming is carbon capture and storage (CCS) entices a solution by not limiting output of any operation. Carbon capture storage refers to the process of capturing or gathering carbon dioxide released into the atmosphere from various activities and injecting the captured gas underground (aquifer). CCS can be divided into 3 main stages namely capturing, transportation and storage. The carbon dioxide will be captured from a source, being transported and sequestrated underground. In this paper, the main area discussed is the capturing process and application in steelmaking industry from economical point of view. Carbon capture is an expensive process which creates an indecisiveness among different parties to actually put the process in practice. However, this expensive process is not properly quantified which is the main motivation of this study to contribute to the cost quantification of carbon capture. Carbon capture is mainly divided to several methods namely membrane separation, oxyfuel combustion, absorption, adsorption, chemical looping combustion, calcium looping and cryogenic method. Despite of having many capturing methods available, there was no vivid or clear application at a large commercial or industrial scale of several methods which rendered them mooted for comparison's sake. Technologies that have gone beyond technological readiness level (TRL) 4 shall be considered since the relevancy of the comparison can benefit parties planning to spearhead or undertake CCS.
应对全球变暖等环境问题的新兴领域之一是碳捕获和储存(CCS),它通过不限制任何操作的输出来吸引解决方案。碳捕获储存是指捕获或收集各种活动释放到大气中的二氧化碳,并将捕获的气体注入地下(含水层)的过程。CCS可分为捕获、运输和储存三个主要阶段。二氧化碳将从一个源头被捕获,被运输并封存在地下。本文主要从经济角度探讨了捕集工艺及其在炼钢工业中的应用。碳捕获是一个昂贵的过程,它会导致各方在实际实施过程中犹豫不决。然而,这一昂贵的过程没有得到适当的量化,这是本研究的主要动机,有助于碳捕获的成本量化。碳捕集主要分为膜分离法、含氧燃烧法、吸收法、吸附法、化学环法、钙环法和深冷法等几种方法。尽管有许多可用的捕获方法,但有几种方法在大型商业或工业规模上没有生动或明确的应用,这使得它们不适合进行比较。应考虑已经超过技术准备水平(TRL) 4的技术,因为比较的相关性可以使计划率先或承担CCS的各方受益。
{"title":"Comparative Review Study on Different Carbon Capture Methods and Applications in Steelmaking Plant from Economical Point of View","authors":"Thinesh Shakkti Arul Rajoo, K. Elraies, U. Z. Husna, Juhairi Aris Muhamad Shuhili, Mohd Afandi Abu Bakar, Hazliza Haron, Ismail Mohd Saaid, J. Lee, M. N. Mohamad Ibrahim, S. B. Gogoi, A. Saeedi","doi":"10.4043/31540-ms","DOIUrl":"https://doi.org/10.4043/31540-ms","url":null,"abstract":"\u0000 One of the emerging areas in combatting environmental issue like global warming is carbon capture and storage (CCS) entices a solution by not limiting output of any operation. Carbon capture storage refers to the process of capturing or gathering carbon dioxide released into the atmosphere from various activities and injecting the captured gas underground (aquifer). CCS can be divided into 3 main stages namely capturing, transportation and storage. The carbon dioxide will be captured from a source, being transported and sequestrated underground. In this paper, the main area discussed is the capturing process and application in steelmaking industry from economical point of view. Carbon capture is an expensive process which creates an indecisiveness among different parties to actually put the process in practice. However, this expensive process is not properly quantified which is the main motivation of this study to contribute to the cost quantification of carbon capture. Carbon capture is mainly divided to several methods namely membrane separation, oxyfuel combustion, absorption, adsorption, chemical looping combustion, calcium looping and cryogenic method. Despite of having many capturing methods available, there was no vivid or clear application at a large commercial or industrial scale of several methods which rendered them mooted for comparison's sake. Technologies that have gone beyond technological readiness level (TRL) 4 shall be considered since the relevancy of the comparison can benefit parties planning to spearhead or undertake CCS.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"101 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"80873163","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Hybrid Pipeline Fit for Purpose for Multiphase Gas and Condensate Transportation 适用于多相气凝析液输送的混合式管道
Pub Date : 2022-03-18 DOI: 10.4043/31453-ms
Nur Izyan Mukhtar, M. H. A Razak, Z. Jamil
Corrosion and materials degradation factors during normal and abnormal operating conditions are among the essential criterion in evaluating materials suitability for an offshore pipeline transporting treated gas and condensate with contaminants i.e. CO2, Materials resistant to wet H2S damage in accordance with ISO 15156 requirements and mercury. A thorough study was conducted to ascertain the pipeline section that will be exposed to sour service conditions due to substantial Materials resistant to wet H2S damage in accordance with ISO 15156 requirements level along the pipeline during certain transient scenarios. The study was conducted in view of fit-for-purpose solution and CAPEX optimization initiatives for the project. During certain transient scenarios, there is potential exposure to substantial H2S level under wet conditions for a certain pipeline length which increases materials susceptibility to wet H2S damage such as Hydrogen Induced Cracking (HIC)/Stepwise Cracking (SWC) and Sulfide Stress Cracking (SSC). Flow assurance modeling with compositional tracking module was used to determine the level of H2S along the pipeline where few potential scenarios leading to sour conditions were considered. Risk assessments were also conducted to ascertain the impact and mitigations for the scenarios. Based on studies, exposure to sour service conditions is expected at a partial length of the pipeline as the H2S level exceeds the sour service limit during specific transient scenarios. Specific mitigation measures involving chemical injection, process control and safeguarding and operating procedures were outlined. The study successfully demonstrated an optimized materials selection approach for the pipeline.
在正常和异常操作条件下,腐蚀和材料降解因素是评估海上管道输送处理过的气体和含有污染物(如CO2)的冷凝水的材料适用性的基本标准之一,符合ISO 15156要求的耐湿H2S损坏的材料和汞。根据ISO 15156的要求,在某些瞬态情况下,由于管道沿线有大量耐湿H2S损坏的材料,因此进行了全面的研究,以确定管道部分将暴露在酸性条件下。该研究是针对适合目的的解决方案和项目的资本支出优化计划进行的。在某些瞬态情况下,对于一定长度的管道,在潮湿条件下可能会暴露在大量的H2S中,这增加了材料对湿H2S损伤的敏感性,例如氢致开裂(HIC)/逐步开裂(SWC)和硫化物应力开裂(SSC)。使用组合跟踪模块的流动保证建模来确定管道沿线的H2S水平,其中很少考虑可能导致酸性条件的情况。还进行了风险评估,以确定各种情景的影响和缓解措施。根据研究,在特定的瞬态情况下,由于H2S水平超过了含硫服务限值,预计部分管道将暴露于含硫服务条件下。概述了涉及化学品注入、过程控制和保障及操作程序的具体缓解措施。该研究成功地展示了管道材料的优化选择方法。
{"title":"Hybrid Pipeline Fit for Purpose for Multiphase Gas and Condensate Transportation","authors":"Nur Izyan Mukhtar, M. H. A Razak, Z. Jamil","doi":"10.4043/31453-ms","DOIUrl":"https://doi.org/10.4043/31453-ms","url":null,"abstract":"\u0000 Corrosion and materials degradation factors during normal and abnormal operating conditions are among the essential criterion in evaluating materials suitability for an offshore pipeline transporting treated gas and condensate with contaminants i.e. CO2, Materials resistant to wet H2S damage in accordance with ISO 15156 requirements and mercury. A thorough study was conducted to ascertain the pipeline section that will be exposed to sour service conditions due to substantial Materials resistant to wet H2S damage in accordance with ISO 15156 requirements level along the pipeline during certain transient scenarios. The study was conducted in view of fit-for-purpose solution and CAPEX optimization initiatives for the project. During certain transient scenarios, there is potential exposure to substantial H2S level under wet conditions for a certain pipeline length which increases materials susceptibility to wet H2S damage such as Hydrogen Induced Cracking (HIC)/Stepwise Cracking (SWC) and Sulfide Stress Cracking (SSC). Flow assurance modeling with compositional tracking module was used to determine the level of H2S along the pipeline where few potential scenarios leading to sour conditions were considered. Risk assessments were also conducted to ascertain the impact and mitigations for the scenarios. Based on studies, exposure to sour service conditions is expected at a partial length of the pipeline as the H2S level exceeds the sour service limit during specific transient scenarios. Specific mitigation measures involving chemical injection, process control and safeguarding and operating procedures were outlined. The study successfully demonstrated an optimized materials selection approach for the pipeline.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"10 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"86986120","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Oilfield Microbiology: Case Study of Molecular Techniques for Determining the Risk of Microbiologically Influenced Corrosion MIC 油田微生物学:确定微生物影响腐蚀风险的分子技术案例研究
Pub Date : 2022-03-18 DOI: 10.4043/31498-ms
Douglas Grant Bennet
The objective of this paper is to explain the beneficial information obtained during a microbiological study of an oilfield survey, where molecular microbiology techniques where utilised. The inclusion of these techniques highlighted information that would have otherwise been missed and/or misinterpreted. The molecular microbiology techniques deployed during this survey included Quantitative Polymerase Chain Reaction (qPCR) and Next Generation Sequencing (NGS). The aim of PCR technology is to specifically increase a target (gene) from an undetectable amount of starting material. The first step is extraction of DNA from the sample, which will subsequently be subjected to the qPCR technology. During qPCR gene copies are made during thermocycling and a fluorescent marker accumulates, which can be used to quantify the target gene. Similar to the PCR technology, DNA is extracted from the sample and the DNA is amplified. In NGS, this is then sorted into a library of small DNA segments before they are amplified. During the sequencing step each DNA fragment amplified is sequentially identified from light signals emitted by comparing with a DNA library. The results obtained indicated crucial additional information that was not detected by traditional methods. In addition to much higher, truer quantification of known populations of Total Prokaryotes and Sulphate Reducing Prokaryotes, identification of other groups of DNA was possible through the NGS technique analysis. The results provided valuable information, which has subsequently been used to apply successful, targeted mitigation strategies to reduce the risk of MIC to assets.
本文的目的是解释在油田调查微生物学研究中获得的有益信息,其中使用了分子微生物学技术。这些技术的包含突出了本来会被遗漏和/或误解的信息。在本次调查中使用的分子微生物技术包括定量聚合酶链反应(qPCR)和下一代测序(NGS)。PCR技术的目的是从无法检测到的起始物质中特异性地增加目标(基因)。第一步是从样品中提取DNA,随后进行qPCR技术。在qPCR过程中,基因拷贝在热循环过程中产生,并积累荧光标记物,可用于量化目标基因。与PCR技术类似,从样品中提取DNA并扩增DNA。在NGS中,这些DNA片段在被扩增之前被分类到一个小DNA片段库中。在测序步骤中,通过与DNA文库比较,从发出的光信号中依次识别扩增的每个DNA片段。获得的结果显示了传统方法无法检测到的重要附加信息。除了对已知的总原核生物和硫酸盐还原原核生物种群进行更高、更真实的定量分析外,还可以通过NGS技术分析鉴定其他DNA群。研究结果提供了宝贵的信息,这些信息随后被用于实施成功的、有针对性的缓解战略,以降低MIC对资产的风险。
{"title":"Oilfield Microbiology: Case Study of Molecular Techniques for Determining the Risk of Microbiologically Influenced Corrosion MIC","authors":"Douglas Grant Bennet","doi":"10.4043/31498-ms","DOIUrl":"https://doi.org/10.4043/31498-ms","url":null,"abstract":"\u0000 The objective of this paper is to explain the beneficial information obtained during a microbiological study of an oilfield survey, where molecular microbiology techniques where utilised. The inclusion of these techniques highlighted information that would have otherwise been missed and/or misinterpreted.\u0000 The molecular microbiology techniques deployed during this survey included Quantitative Polymerase Chain Reaction (qPCR) and Next Generation Sequencing (NGS).\u0000 The aim of PCR technology is to specifically increase a target (gene) from an undetectable amount of starting material. The first step is extraction of DNA from the sample, which will subsequently be subjected to the qPCR technology. During qPCR gene copies are made during thermocycling and a fluorescent marker accumulates, which can be used to quantify the target gene.\u0000 Similar to the PCR technology, DNA is extracted from the sample and the DNA is amplified. In NGS, this is then sorted into a library of small DNA segments before they are amplified. During the sequencing step each DNA fragment amplified is sequentially identified from light signals emitted by comparing with a DNA library.\u0000 The results obtained indicated crucial additional information that was not detected by traditional methods. In addition to much higher, truer quantification of known populations of Total Prokaryotes and Sulphate Reducing Prokaryotes, identification of other groups of DNA was possible through the NGS technique analysis. The results provided valuable information, which has subsequently been used to apply successful, targeted mitigation strategies to reduce the risk of MIC to assets.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"1 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"82931401","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
Corrosion Management of Wet Gas Sour Gas Carbon Steel Pipeline with Corrosion Inhibitor and Mono-Ethylene-Glycol in NACE Region 3 NACE地区含缓蚀剂和单乙二醇的湿气、酸气碳钢管道腐蚀治理
Pub Date : 2022-03-18 DOI: 10.4043/31512-ms
Chun Ho Leow, Hock Guan Ong, Rachel Lee, C. A. Khoo
This paper will present corrosion management of a wet sour gas carbon steel export pipeline using continuous and batch corrosion inhibitors with mono-ethlene-glycol (MEG) as hydrate mitigation strategy in NACE MR 0175/ ISO 15156 region 3 (severe sour). The wet sour gas carbon steel export pipeline corrosion management via continuous CI and batch inhibitors with closed loop MEG regeneration system is rare worldwide. This is especially challenging when the case study may potentially be the longest wet sour gas, large diameter carbon steel pipeline (approximately 207km × 32 inch) in the world thus far. Pipeline corrosion management and hydrate management aspects when being reviewed holistically, it could provide significant cost savings yet safeguarding the overall technical integrity of the pipeline. The overall corrosion management leverages on Shell's many years of JIP and operating experience in sour service including the pipeline material specification, corrosion management, inspection, and maintenance philosophy. Reliable correlation between reservoir properties and uncertainties severe sour service, flow assurance, chemical behavirous, operating experiences etc were considered to best represent the operating envelope for this wet sour gas carbon steel pipeline. This includes the testing and selection of continuous CI and batch inhibitor, corrosion monitoring, operational pigging, maintenance, and inspection requirements throughout the field life.
本文将介绍在NACE MR 0175/ ISO 15156区域3(严重酸性)中,使用含单乙二醇(MEG)的连续和间歇缓蚀剂作为水合物缓蚀剂的湿酸性气体碳钢出口管道的腐蚀管理。采用连续CI和间歇式缓蚀剂加闭环MEG再生系统对湿式酸气碳钢出口管道进行腐蚀管理,在世界范围内尚属罕见。当案例研究可能是迄今为止世界上最长的湿酸气大直径碳钢管道(约207公里× 32英寸)时,这尤其具有挑战性。从整体上看,管道腐蚀管理和水合物管理方面可以节省大量成本,同时保证管道的整体技术完整性。全面的腐蚀管理利用了壳牌多年的JIP和酸性服务的操作经验,包括管道材料规范,腐蚀管理,检查和维护理念。储层性质与不确定性之间的可靠相关性、高含酸工况、流动保证、化学行为、操作经验等被认为是这条含酸湿气碳钢管道的最佳运行包线。这包括连续CI和间歇抑制剂的测试和选择、腐蚀监测、作业清管、维护和整个油田生命周期的检查要求。
{"title":"Corrosion Management of Wet Gas Sour Gas Carbon Steel Pipeline with Corrosion Inhibitor and Mono-Ethylene-Glycol in NACE Region 3","authors":"Chun Ho Leow, Hock Guan Ong, Rachel Lee, C. A. Khoo","doi":"10.4043/31512-ms","DOIUrl":"https://doi.org/10.4043/31512-ms","url":null,"abstract":"\u0000 This paper will present corrosion management of a wet sour gas carbon steel export pipeline using continuous and batch corrosion inhibitors with mono-ethlene-glycol (MEG) as hydrate mitigation strategy in NACE MR 0175/ ISO 15156 region 3 (severe sour). The wet sour gas carbon steel export pipeline corrosion management via continuous CI and batch inhibitors with closed loop MEG regeneration system is rare worldwide. This is especially challenging when the case study may potentially be the longest wet sour gas, large diameter carbon steel pipeline (approximately 207km × 32 inch) in the world thus far. Pipeline corrosion management and hydrate management aspects when being reviewed holistically, it could provide significant cost savings yet safeguarding the overall technical integrity of the pipeline. The overall corrosion management leverages on Shell's many years of JIP and operating experience in sour service including the pipeline material specification, corrosion management, inspection, and maintenance philosophy. Reliable correlation between reservoir properties and uncertainties severe sour service, flow assurance, chemical behavirous, operating experiences etc were considered to best represent the operating envelope for this wet sour gas carbon steel pipeline. This includes the testing and selection of continuous CI and batch inhibitor, corrosion monitoring, operational pigging, maintenance, and inspection requirements throughout the field life.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"48 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"83386677","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Application of Conformance Control in Stand-Alone Screen SAS Completed Horizontal Wells-A Case Study of Bohai Bay 一致性控制在独立筛管SAS已完井水平井中的应用——以渤海湾为例
Pub Date : 2022-03-18 DOI: 10.4043/31611-ms
Xu Zheng, Y. Lei, Bailin Pei, Wei Zhao
There is high demand for water shutoff in quite a few SAS completed horizontal wells in the Bohai Bay, China. The popular swellable packer in combination with the ICD screen method cannot be adopted because segmentation cannot be achieved in the annulus between the SAS and the borehole wall by the swellable packers for the SAS is unable to be tripped out. A conformance control method is introduced and a case study is provided. When the SAS string is not tripped out, first the path for the particles to flow through is established by perforation. Then, a string of ICD screen with smaller diameter is run in place, followed by the pumping of the continuous pack-off particles into the annulus (the inner annulus) between the ICD screen and the SAS. Meanwhile, the particles being carried by the fluids also pack the annulus (the outer annulus) between the SAS and the borehole wall through the penetrations on the SAS. Thus, the function of axial channeling prevention is realized by the rings of particles. The well in the case study is an old well that suffered from high water cut, sand production and mud clogging simultaneously. For this operation, the filling rate of the particles was 104.2%, indicating the particles were tightly packed in the inner and outer annuluses and segmentation in the production interval was realized. After commissioning, the water rate dropped from the original 638m3/d to 85m3/d. The oil rate resumed to the level before the well was shut in and later slowly increased to 40.3m3/d. Water shutoff and oil enhancement was realized and neither sand production nor mud clogging occurred. Three functions are realized via the adoption of this method. Firstly, water shutoff and oil enhancement are realized via conformance control; secondly, both rings of particles together with the filtering layers in jacket provide better sand control; thirdly, the rings formed by the tightly packed particles are capable of preventing mud clogging. In this paper, perforation is innovatively proposed to establish the path for the particles to flow through so that both annuluses are tightly filled by particles, together with the ICD screens, conformance control is realized along the entire production interval and the target of water shutoff and oil enhancement is achieved. Accordingly, high CAPEX for sidetracking is avoided and the single well ROI is improved.
渤海湾相当一部分SAS完井水平井的关水要求较高。目前流行的可膨胀封隔器与ICD筛管相结合的方法不能被采用,因为可膨胀封隔器无法在SAS与井壁之间的环空中实现分段,因为SAS无法起下钻。介绍了一种一致性控制方法,并给出了实例分析。当SAS管柱没有流出时,首先通过射孔建立粒子流过的路径。然后,下入一串直径较小的ICD筛管,然后将连续的封隔颗粒泵入ICD筛管和SAS之间的环空(内环空)。与此同时,流体携带的颗粒也通过SAS上的穿透填满SAS与井壁之间的环空(外环空)。因此,通过颗粒环来实现防止轴向窜流的功能。该井是一口老井,同时遭受高含水、出砂和泥浆堵塞。该操作颗粒充填率为104.2%,表明颗粒在内外环内充填紧密,实现了生产区间的分段。投产后,产水量由原来的638m3/d降至85m3/d。产油速度恢复到关井前的水平,随后缓慢增加到40.3m3/d。实现了堵水增油,不出砂、不堵泥。采用该方法实现了三个功能。首先,通过控制顺性实现堵水增油;其次,颗粒环和夹套内的过滤层具有较好的防砂效果;第三,由紧密堆积的颗粒形成的环能够防止泥浆堵塞。本文创新性地提出了射孔的方法,建立颗粒的流动路径,使颗粒在两个环空内被颗粒紧密填充,配合ICD筛管,实现了整个生产区间的一致性控制,达到了堵水增油的目的。因此,避免了侧钻的高资本支出,提高了单井的投资回报率。
{"title":"Application of Conformance Control in Stand-Alone Screen SAS Completed Horizontal Wells-A Case Study of Bohai Bay","authors":"Xu Zheng, Y. Lei, Bailin Pei, Wei Zhao","doi":"10.4043/31611-ms","DOIUrl":"https://doi.org/10.4043/31611-ms","url":null,"abstract":"\u0000 \u0000 \u0000 There is high demand for water shutoff in quite a few SAS completed horizontal wells in the Bohai Bay, China. The popular swellable packer in combination with the ICD screen method cannot be adopted because segmentation cannot be achieved in the annulus between the SAS and the borehole wall by the swellable packers for the SAS is unable to be tripped out. A conformance control method is introduced and a case study is provided.\u0000 \u0000 \u0000 \u0000 When the SAS string is not tripped out, first the path for the particles to flow through is established by perforation. Then, a string of ICD screen with smaller diameter is run in place, followed by the pumping of the continuous pack-off particles into the annulus (the inner annulus) between the ICD screen and the SAS. Meanwhile, the particles being carried by the fluids also pack the annulus (the outer annulus) between the SAS and the borehole wall through the penetrations on the SAS. Thus, the function of axial channeling prevention is realized by the rings of particles.\u0000 \u0000 \u0000 \u0000 The well in the case study is an old well that suffered from high water cut, sand production and mud clogging simultaneously. For this operation, the filling rate of the particles was 104.2%, indicating the particles were tightly packed in the inner and outer annuluses and segmentation in the production interval was realized. After commissioning, the water rate dropped from the original 638m3/d to 85m3/d. The oil rate resumed to the level before the well was shut in and later slowly increased to 40.3m3/d. Water shutoff and oil enhancement was realized and neither sand production nor mud clogging occurred. Three functions are realized via the adoption of this method. Firstly, water shutoff and oil enhancement are realized via conformance control; secondly, both rings of particles together with the filtering layers in jacket provide better sand control; thirdly, the rings formed by the tightly packed particles are capable of preventing mud clogging.\u0000 \u0000 \u0000 \u0000 In this paper, perforation is innovatively proposed to establish the path for the particles to flow through so that both annuluses are tightly filled by particles, together with the ICD screens, conformance control is realized along the entire production interval and the target of water shutoff and oil enhancement is achieved. Accordingly, high CAPEX for sidetracking is avoided and the single well ROI is improved.\u0000","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"23 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"89439930","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Automatic Fault Segmentation Using Wavelet Convolutional Neural Networks 基于小波卷积神经网络的故障自动分割
Pub Date : 2022-03-18 DOI: 10.4043/31529-ms
Xu Zhou, Qishuai Yin, Bin Wang
This study presents a novel neural network model to explore its application in automatically interpreting subsurface faults from seismic images. A Wavelet Convolutional Neural Network (CNN) model that incorporates discrete wavelet decomposition is presented, and its capability in segmenting subsurface faults is analyzed. In this study, different neural network models are developed to compare their performance in segmenting subsurface faults. Sliced 2D seismic images are used as the input of the models. Pre-interpreted images with fault locations are used as the output of the models. Different CNN models are created using different pooling methods, including a traditional U-Net model with average pooling method, and an advanced Wavelet CNN model using wavelet pooling method. The results show that the Wavelet CNN model, which incorporates discrete wavelet transformation as the pooling layer, has the best performance comparing to traditional models in segmenting subsurface faults from input seismic images. It is more effective in saving edge features during pooling operations and outperforms the traditional U-Net model in segmenting subsurface faults from seismic images.
本文提出了一种新的神经网络模型,探索其在地震图像地下断层自动解释中的应用。提出了一种结合离散小波分解的小波卷积神经网络(CNN)模型,并分析了其对地下断层的分割能力。在本研究中,建立了不同的神经网络模型,比较了它们在地下断层分割中的性能。采用二维地震图像切片作为模型输入。带有故障位置的预解释图像被用作模型的输出。采用不同的池化方法建立了不同的CNN模型,包括采用平均池化方法的传统U-Net模型和采用小波池化方法的高级小波CNN模型。结果表明,将离散小波变换作为池化层的小波CNN模型在从输入地震图像中分割地下断层方面,比传统模型具有更好的性能。该方法在池化过程中更有效地保存了边缘特征,并且在从地震图像中分割地下断层方面优于传统的U-Net模型。
{"title":"Automatic Fault Segmentation Using Wavelet Convolutional Neural Networks","authors":"Xu Zhou, Qishuai Yin, Bin Wang","doi":"10.4043/31529-ms","DOIUrl":"https://doi.org/10.4043/31529-ms","url":null,"abstract":"\u0000 This study presents a novel neural network model to explore its application in automatically interpreting subsurface faults from seismic images. A Wavelet Convolutional Neural Network (CNN) model that incorporates discrete wavelet decomposition is presented, and its capability in segmenting subsurface faults is analyzed.\u0000 In this study, different neural network models are developed to compare their performance in segmenting subsurface faults. Sliced 2D seismic images are used as the input of the models. Pre-interpreted images with fault locations are used as the output of the models. Different CNN models are created using different pooling methods, including a traditional U-Net model with average pooling method, and an advanced Wavelet CNN model using wavelet pooling method. The results show that the Wavelet CNN model, which incorporates discrete wavelet transformation as the pooling layer, has the best performance comparing to traditional models in segmenting subsurface faults from input seismic images. It is more effective in saving edge features during pooling operations and outperforms the traditional U-Net model in segmenting subsurface faults from seismic images.","PeriodicalId":11011,"journal":{"name":"Day 3 Thu, March 24, 2022","volume":"11 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2022-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"90716039","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
期刊
Day 3 Thu, March 24, 2022
全部 Acc. Chem. Res. ACS Applied Bio Materials ACS Appl. Electron. Mater. ACS Appl. Energy Mater. ACS Appl. Mater. Interfaces ACS Appl. Nano Mater. ACS Appl. Polym. Mater. ACS BIOMATER-SCI ENG ACS Catal. ACS Cent. Sci. ACS Chem. Biol. ACS Chemical Health & Safety ACS Chem. Neurosci. ACS Comb. Sci. ACS Earth Space Chem. ACS Energy Lett. ACS Infect. Dis. ACS Macro Lett. ACS Mater. Lett. ACS Med. Chem. Lett. ACS Nano ACS Omega ACS Photonics ACS Sens. ACS Sustainable Chem. Eng. ACS Synth. Biol. Anal. Chem. BIOCHEMISTRY-US Bioconjugate Chem. BIOMACROMOLECULES Chem. Res. Toxicol. Chem. Rev. Chem. Mater. CRYST GROWTH DES ENERG FUEL Environ. Sci. Technol. Environ. Sci. Technol. Lett. Eur. J. Inorg. Chem. IND ENG CHEM RES Inorg. Chem. J. Agric. Food. Chem. J. Chem. Eng. Data J. Chem. Educ. J. Chem. Inf. Model. J. Chem. Theory Comput. J. Med. Chem. J. Nat. Prod. J PROTEOME RES J. Am. Chem. Soc. LANGMUIR MACROMOLECULES Mol. Pharmaceutics Nano Lett. Org. Lett. ORG PROCESS RES DEV ORGANOMETALLICS J. Org. Chem. J. Phys. Chem. J. Phys. Chem. A J. Phys. Chem. B J. Phys. Chem. C J. Phys. Chem. Lett. Analyst Anal. Methods Biomater. Sci. Catal. Sci. Technol. Chem. Commun. Chem. Soc. Rev. CHEM EDUC RES PRACT CRYSTENGCOMM Dalton Trans. Energy Environ. Sci. ENVIRON SCI-NANO ENVIRON SCI-PROC IMP ENVIRON SCI-WAT RES Faraday Discuss. Food Funct. Green Chem. Inorg. Chem. Front. Integr. Biol. J. Anal. At. Spectrom. J. Mater. Chem. A J. Mater. Chem. B J. Mater. Chem. C Lab Chip Mater. Chem. Front. Mater. Horiz. MEDCHEMCOMM Metallomics Mol. Biosyst. Mol. Syst. Des. Eng. Nanoscale Nanoscale Horiz. Nat. Prod. Rep. New J. Chem. Org. Biomol. Chem. Org. Chem. Front. PHOTOCH PHOTOBIO SCI PCCP Polym. Chem.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1