首页 > 最新文献

Tunnelling and Underground Space Technology最新文献

英文 中文
Innovative design and construction of a closure joint for inland-river immersed tunnels via dry-land construction methods: A case study of the Yuliangzhou tunnel in China 通过旱地施工方法创新设计和建造内陆河沉管隧道的封闭接头:中国鱼梁洲隧道案例研究
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-14 DOI: 10.1016/j.tust.2024.106026

Closure joints constructed to fill the spaces between immersed tunnel elements or between the tunnel elements and adjacent cut-and-cover tunnels are crucial for the longitudinal stability of immersed tunnels and affect the overall cost and duration of tunnel construction. To avoid the obstruction of navigation and reduce the difficulty of constructing closure joints, dry-land construction methods have been widely applied to construct closure joints for inland-river immersed tunnels, in particular using procedures involving axial dry docks. However, the traditional dry-land construction method has many inherent drawbacks. For example, the construction of underwater large-scale reinforced concrete antiretreat structures involves many underwater works, complicated construction processes, long operation time spans and high costs. Based on the Yuliangzhou immersed tunnel in China, a new dry-land construction method for closure joints of inland-river immersed tunnels based on tunnel–soil interface friction was developed to address the abovementioned problems. Considering the adverse influences of back-silting sediment on tunnel–soil interface friction, large-scale laboratory and onsite shear tests were carried out to derive the interface friction coefficients between the tunnel element base slabs and prelaid pebble foundation beds. A composite concrete steel sandwich (CCSS) water-retaining system was designed and assembled to separate the water in the dry dock from the river course. A simplified analysis method based on numerical simulations for the determination of the equivalent horizontal thrust P applied to element ES caused by the dewatering of the axial dry dock was proposed. Based on horizontal antisliding stability analyses of the tunnel elements during the axial dry dock dewatering stage, equations for the key design parameters of the new dry-land construction method were established. Through examination of the static equilibrium of the tunnel elements in the tunnel longitudinal direction, temporary longitudinal displacement constraint (LDC) structures at the immersion joints were designed. Furthermore, the following key construction techniques for the new dry-land construction method were systematically designed: installation of a CCSS water-retaining system at the entrance of the axial dry dock, water sealing at contact gaps, installation of finish-rolled screw-thread (FRST) steel bars as the LDC structures at the immersion joints, and construction of rigid connections between tunnel element ES and the cut-and-cover tunnel. Finally, onsite observation of the deformation states of Gina gaskets and monitoring of the tensile forces of FRST steel bars at the immersion joints verified the successful implementation of the new dry-land construction method, supporting the use of these techniques in closure joint design and construction for inland-river immersed tunnels.

为填充沉管隧道构件之间或隧道构件与相邻明挖隧道之间的空间而建造的封闭缝对沉管隧道的纵向稳定性至关重要,并影响隧道施工的总体成本和工期。为了避免妨碍通航和降低封闭缝施工难度,内陆河沉管隧道的封闭缝施工广泛采用了旱地施工方法,特别是使用轴向旱坞的程序。然而,传统的旱地施工方法存在许多固有缺陷。例如,水下大型钢筋混凝土抗渗结构施工涉及的水下工程多、施工工艺复杂、作业时间跨度长、成本高。针对上述问题,在中国鱼梁洲沉管隧道的基础上,开发了一种基于隧道-土壤界面摩擦力的新型陆河沉管隧道闭合缝旱地施工方法。考虑到反淤泥沙对隧道土界面摩擦力的不利影响,进行了大规模的实验室和现场剪切试验,得出了隧道构件底板与预铺卵石基床之间的界面摩擦系数。设计并组装了一个复合混凝土钢夹层(CCSS)挡水系统,以将干船坞中的水与河道分开。提出了一种基于数值模拟的简化分析方法,用于确定轴向干船坞脱水对元素 ES 所产生的等效水平推力 P。根据轴向干船坞脱水阶段隧道构件的水平防滑稳定性分析,建立了新干地施工方法的关键设计参数方程。通过对隧道构件在隧道纵向的静力平衡进行研究,设计了浸入式接缝处的临时纵向位移约束(LDC)结构。此外,还系统地设计了新型旱地施工方法的以下关键施工技术:在轴向旱坞入口处安装 CCSS 挡水系统、在接触间隙处进行水封、在浸入式接缝处安装精轧螺纹钢筋(FRST)作为 LDC 结构,以及在隧道构件 ES 和明挖回填式隧道之间建立刚性连接。最后,通过现场观察吉娜垫片的变形状态和监测浸入式接头处精轧螺纹钢筋的拉力,验证了新型旱地施工方法的成功实施,支持在内陆河浸入式隧道的封闭接头设计和施工中使用这些技术。
{"title":"Innovative design and construction of a closure joint for inland-river immersed tunnels via dry-land construction methods: A case study of the Yuliangzhou tunnel in China","authors":"","doi":"10.1016/j.tust.2024.106026","DOIUrl":"10.1016/j.tust.2024.106026","url":null,"abstract":"<div><p>Closure joints constructed to fill the spaces between immersed tunnel elements or between the tunnel elements and adjacent cut-and-cover tunnels are crucial for the longitudinal stability of immersed tunnels and affect the overall cost and duration of tunnel construction. To avoid the obstruction of navigation and reduce the difficulty of constructing closure joints, dry-land construction methods have been widely applied to construct closure joints for inland-river immersed tunnels, in particular using procedures involving axial dry docks. However, the traditional dry-land construction method has many inherent drawbacks. For example, the construction of underwater large-scale reinforced concrete antiretreat structures involves many underwater works, complicated construction processes, long operation time spans and high costs. Based on the Yuliangzhou immersed tunnel in China, a new dry-land construction method for closure joints of inland-river immersed tunnels based on tunnel–soil interface friction was developed to address the abovementioned problems. Considering the adverse influences of back-silting sediment on tunnel–soil interface friction, large-scale laboratory and onsite shear tests were carried out to derive the interface friction coefficients between the tunnel element base slabs and prelaid pebble foundation beds. A composite concrete steel sandwich (CCSS) water-retaining system was designed and assembled to separate the water in the dry dock from the river course. A simplified analysis method based on numerical simulations for the determination of the equivalent horizontal thrust <em>P</em> applied to element ES caused by the dewatering of the axial dry dock was proposed. Based on horizontal antisliding stability analyses of the tunnel elements during the axial dry dock dewatering stage, equations for the key design parameters of the new dry-land construction method were established. Through examination of the static equilibrium of the tunnel elements in the tunnel longitudinal direction, temporary longitudinal displacement constraint (LDC) structures at the immersion joints were designed. Furthermore, the following key construction techniques for the new dry-land construction method were systematically designed: installation of a CCSS water-retaining system at the entrance of the axial dry dock, water sealing at contact gaps, installation of finish-rolled screw-thread (FRST) steel bars as the LDC structures at the immersion joints, and construction of rigid connections between tunnel element ES and the cut-and-cover tunnel. Finally, onsite observation of the deformation states of Gina gaskets and monitoring of the tensile forces of FRST steel bars at the immersion joints verified the successful implementation of the new dry-land construction method, supporting the use of these techniques in closure joint design and construction for inland-river immersed tunnels.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141985313","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Greenhouse gas emission reduction potential in road tunnels – Can we reach the European Union goals with existing materials and technologies? 公路隧道的温室气体减排潜力--现有材料和技术能否实现欧盟目标?
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-14 DOI: 10.1016/j.tust.2024.106011

To achieve the European Uniońs climate goals, the Norwegian transport sector has committed to decrease the Greenhouse gas (GHG) emissions by 2030. For infrastructure projects, the GHG emissions from construction must be reduced by 40 %, while the emissions from maintenance must be cut by 50%. This paper investigates how realistic the GHG emission reduction goals are, if available low carbon materials and technologies are fully adopted. To examine this, we have chosen a typical Norwegian road tunnel from which two carbon emission scenarios are presented. While tunnels represent a specific subset of road infrastructure, this study showcases that implementing sustainable practices in drill and blast tunnel construction can align with the European Union’s ambitious 2030 targets. Besides this, the findings can assist stakeholders to get advice on the environmental impacts of tunnel designs.

为实现欧盟的气候目标,挪威交通部门承诺到 2030 年减少温室气体排放。在基础设施项目中,施工产生的温室气体排放量必须减少 40%,而维护产生的排放量必须减少 50%。本文研究了如果完全采用现有的低碳材料和技术,温室气体减排目标的现实性有多大。为此,我们选择了一条典型的挪威公路隧道,并从中提出了两种碳排放方案。虽然隧道是公路基础设施的一个特殊子集,但这项研究表明,在钻爆隧道施工中采用可持续的做法,可以与欧盟雄心勃勃的 2030 年目标保持一致。此外,研究结果还有助于利益相关者获得有关隧道设计对环境影响的建议。
{"title":"Greenhouse gas emission reduction potential in road tunnels – Can we reach the European Union goals with existing materials and technologies?","authors":"","doi":"10.1016/j.tust.2024.106011","DOIUrl":"10.1016/j.tust.2024.106011","url":null,"abstract":"<div><p>To achieve the European Uniońs climate goals, the Norwegian transport sector has committed to decrease the Greenhouse gas (GHG) emissions by 2030. For infrastructure projects, the GHG emissions from construction must be reduced by 40 %, while the emissions from maintenance must be cut by 50%. This paper investigates how realistic the GHG emission reduction goals are, if available low carbon materials and technologies are fully adopted. To examine this, we have chosen a typical Norwegian road tunnel from which two carbon emission scenarios are presented. While tunnels represent a specific subset of road infrastructure, this study showcases that implementing sustainable practices in drill and blast tunnel construction can align with the European Union’s ambitious 2030 targets. Besides this, the findings can assist stakeholders to get advice on the environmental impacts of tunnel designs.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://www.sciencedirect.com/science/article/pii/S0886779824004292/pdfft?md5=051fc553c426cda4c2c1c78e14bf2e57&pid=1-s2.0-S0886779824004292-main.pdf","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141985312","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"OA","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Evaluation of urban underground space via automated constraint identification and hybrid analysis 通过自动约束识别和混合分析评估城市地下空间
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-13 DOI: 10.1016/j.tust.2024.106005

As urbanization progresses, the exploration and development of urban underground space resources have become imperative. Assessments of urban underground space are conducive to understanding the quantity and potential of urban underground resources that can be developed and utilized. The practice of combining urban three-dimensional geological models for suitability assessments of urban underground space is commonly used and has been proven to be effective. However, existing assessment methods struggle to automatically consider the impact of existing facilities, necessitating extensive preliminary investigation. In addition, despite the abundance of evaluation methods, there is a noticeable gap in research applying both subjective and objective evaluation techniques in tandem. To address these problems, this study introduces an innovative framework to automate the identification of existing constraints via a semantic segmentation deep learning method. In addition, a hybrid evaluation method integrating the entropy weight method, the CRITIC method, and the Analytic Hierarchy Process is proposed. This methodology not only fills a gap in existing studies by providing a comprehensive framework for urban underground space evaluations but also offers a novel approach to integrating technological advances into urban planning research. The application of this study in the Sanlong Bay area of Foshan City further demonstrates its practicality and effectiveness, showcasing a significant advancement in the field of urban underground space evaluation.

随着城市化进程的推进,城市地下空间资源的勘探和开发已势在必行。城市地下空间评估有利于了解可开发利用的城市地下资源的数量和潜力。结合城市三维地质模型进行城市地下空间适宜性评估的做法已被普遍采用,并被证明是行之有效的。然而,现有的评估方法难以自动考虑现有设施的影响,需要进行大量的前期调查。此外,尽管有大量的评估方法,但在同时应用主观和客观评估技术的研究方面存在明显差距。为解决这些问题,本研究引入了一个创新框架,通过语义分割深度学习方法自动识别现有限制因素。此外,本研究还提出了一种混合评价方法,该方法综合了熵权法、CRITIC 法和层次分析法。该方法不仅填补了现有研究的空白,为城市地下空间评估提供了一个综合框架,还为将技术进步融入城市规划研究提供了一种新方法。本研究在佛山市三龙湾片区的应用进一步证明了其实用性和有效性,展示了城市地下空间评价领域的重大进展。
{"title":"Evaluation of urban underground space via automated constraint identification and hybrid analysis","authors":"","doi":"10.1016/j.tust.2024.106005","DOIUrl":"10.1016/j.tust.2024.106005","url":null,"abstract":"<div><p>As urbanization progresses, the exploration and development of urban underground space resources have become imperative. Assessments of urban underground space are conducive to understanding the quantity and potential of urban underground resources that can be developed and utilized. The practice of combining urban three-dimensional geological models for suitability assessments of urban underground space is commonly used and has been proven to be effective. However, existing assessment methods struggle to automatically consider the impact of existing facilities, necessitating extensive preliminary investigation. In addition, despite the abundance of evaluation methods, there is a noticeable gap in research applying both subjective and objective evaluation techniques in tandem. To address these problems, this study introduces an innovative framework to automate the identification of existing constraints via a semantic segmentation deep learning method. In addition, a hybrid evaluation method integrating the entropy weight method, the CRITIC method, and the Analytic Hierarchy Process is proposed. This methodology not only fills a gap in existing studies by providing a comprehensive framework for urban underground space evaluations but also offers a novel approach to integrating technological advances into urban planning research. The application of this study in the Sanlong Bay area of Foshan City further demonstrates its practicality and effectiveness, showcasing a significant advancement in the field of urban underground space evaluation.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-13","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141978591","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Considering creep in rock tunnelling with a combined support system: Theoretical solutions and machine-learning solver 利用组合支持系统考虑岩石隧道的蠕变:理论解决方案和机器学习求解器
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-12 DOI: 10.1016/j.tust.2024.106019

This study provides an alternative theoretical approach to analyse the mechanical behaviour of tunnels excavated in time-dependent geomaterials, considering the sequential excavation of tunnels and installation of rockbolts and elastic liner. In the theoretical analyses, the Bolted Rock Mass (BRM) is modelled as a homogeneous material but with higher stiffness. An innovative Machine-Learning-Based solver (MLB-solver) has been developed to evaluate the reinforcement ability of rockbolts for geotechnical applications. After that, the complex variable method, the Laplace transformation technique, and the extension of the correspondence principle, combined with the compatibility and boundary conditions, have been employed to obtain the analytical solutions for stresses and displacements at the rock-support and support-support interfaces. Furthermore, the analytical predictions have been validated by monitoring data from the Lyon-Turin Base Tunnel. Parametric analyses are conducted to investigate the influence of rockbolt length and installation time on tunnel behaviour. Meanwhile, the proposed theoretical solutions have been also applied to analyse tunnel stability. This study offers a new and efficient method for the preliminary design of supported tunnels.

本研究提供了另一种理论方法,用于分析在随时间变化的岩土材料中开挖隧道的力学行为,其中考虑了隧道的顺序开挖以及岩体螺栓和弹性衬砌的安装。在理论分析中,锚杆岩体(BRM)被模拟为均质材料,但具有更高的刚度。已开发出一种创新的基于机器学习的求解器(MLB-求解器),用于评估岩土工程应用中锚杆的加固能力。然后,利用复变法、拉普拉斯变换技术和对应原理的扩展,结合相容性和边界条件,获得了岩石-支撑和支撑-支撑界面上的应力和位移的分析解。此外,里昂-都灵海底隧道的监测数据也对分析预测进行了验证。还进行了参数分析,以研究锚杆长度和安装时间对隧道行为的影响。同时,提出的理论解决方案还被用于分析隧道的稳定性。这项研究为支护隧道的初步设计提供了一种新的高效方法。
{"title":"Considering creep in rock tunnelling with a combined support system: Theoretical solutions and machine-learning solver","authors":"","doi":"10.1016/j.tust.2024.106019","DOIUrl":"10.1016/j.tust.2024.106019","url":null,"abstract":"<div><p>This study provides an alternative theoretical approach to analyse the mechanical behaviour of tunnels excavated in time-dependent geomaterials, considering the sequential excavation of tunnels and installation of rockbolts and elastic liner. In the theoretical analyses, the Bolted Rock Mass (BRM) is modelled as a homogeneous material but with higher stiffness. An innovative Machine-Learning-Based solver (MLB-solver) has been developed to evaluate the reinforcement ability of rockbolts for geotechnical applications. After that, the complex variable method, the Laplace transformation technique, and the extension of the correspondence principle, combined with the compatibility and boundary conditions, have been employed to obtain the analytical solutions for stresses and displacements at the rock-support and support-support interfaces. Furthermore, the analytical predictions have been validated by monitoring data from the Lyon-Turin Base Tunnel. Parametric analyses are conducted to investigate the influence of rockbolt length and installation time on tunnel behaviour. Meanwhile, the proposed theoretical solutions have been also applied to analyse tunnel stability. This study offers a new and efficient method for the preliminary design of supported tunnels.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141978150","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
A novel time-varying inverse Peck formula for forecasting freezing-induced ground heave in tunnel construction 用于预测隧道施工中冰冻引起的地表隆起的新型时变逆派克公式
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-12 DOI: 10.1016/j.tust.2024.106015

The Peck formula is widely used to predict subsurface settlement in tunnel excavation without freezing techniques. However, predicting surface uplift during tunnel construction with artificial ground freezing is still a challenge. This investigation introduces a groundbreaking methodology by creatively inverting the Peck formula. By integrating the inverted Peck formula with the principles of plane freezing theory and considering stratum constraint conditions, we’ve developed a time-varying model to quantify the volume of stratum frost heave and the subsequent surface uplift. Through a meticulous back-analysis coupled with maximum likelihood estimation, this approach enhances the precision in gauging the extent of the frost heave mound, thereby improving the accuracy and simplicity of predicting surface uplift deformation in the tunnel construction process employing ground freezing. The robustness and credibility of this innovative approach are substantiated through an exhaustive comparative analysis juxtaposed with empirical engineering monitoring data and calculations based on the stochastic medium theory. The outcomes demonstrate that the proposed inverted Peck formula excels in its explicit clarity and practical relevance, more closely aligning with the empirical data on surface uplift than predictions derived from the stochastic medium theory, thus offering enhanced predictive performance. This study provides a novel theoretical model for anticipating surface uplift deformations in tunnel construction endeavors using ground freezing techniques, delivering valuable insights and a promising predictive tool for both engineering professionals and academic researchers.

Peck 公式被广泛用于预测无冻结技术的隧道开挖中的地下沉降。然而,在隧道施工过程中使用人工地表冻结技术预测地表隆起仍是一项挑战。这项研究通过创造性地倒置 Peck 公式,引入了一种开创性的方法。通过将倒置派克公式与平面冻结理论的原理相结合,并考虑地层约束条件,我们开发出了一种时变模型,用于量化地层冻胀量和随后的地表隆起。通过缜密的回溯分析和最大似然估计,这种方法提高了测量冻胀丘范围的精度,从而提高了在采用地面冻结的隧道施工过程中预测地表隆起变形的准确性和简便性。通过与经验工程监测数据和基于随机介质理论的计算结果进行详尽的对比分析,证实了这一创新方法的稳健性和可信度。结果表明,所提出的倒置派克公式在清晰度和实用性方面表现出色,与随机介质理论得出的预测结果相比,它与地表隆起的经验数据更加吻合,从而提高了预测性能。这项研究提供了一个新颖的理论模型,用于预测使用地面冻结技术进行隧道施工时的地表隆起变形,为工程专业人员和学术研究人员提供了宝贵的见解和前景广阔的预测工具。
{"title":"A novel time-varying inverse Peck formula for forecasting freezing-induced ground heave in tunnel construction","authors":"","doi":"10.1016/j.tust.2024.106015","DOIUrl":"10.1016/j.tust.2024.106015","url":null,"abstract":"<div><p>The Peck formula is widely used to predict subsurface settlement in tunnel excavation without freezing techniques. However, predicting surface uplift during tunnel construction with artificial ground freezing is still a challenge. This investigation introduces a groundbreaking methodology by creatively inverting the Peck formula. By integrating the inverted Peck formula with the principles of plane freezing theory and considering stratum constraint conditions, we’ve developed a time-varying model to quantify the volume of stratum frost heave and the subsequent surface uplift. Through a meticulous back-analysis coupled with maximum likelihood estimation, this approach enhances the precision in gauging the extent of the frost heave mound, thereby improving the accuracy and simplicity of predicting surface uplift deformation in the tunnel construction process employing ground freezing. The robustness and credibility of this innovative approach are substantiated through an exhaustive comparative analysis juxtaposed with empirical engineering monitoring data and calculations based on the stochastic medium theory. The outcomes demonstrate that the proposed inverted Peck formula excels in its explicit clarity and practical relevance, more closely aligning with the empirical data on surface uplift than predictions derived from the stochastic medium theory, thus offering enhanced predictive performance. This study provides a novel theoretical model for anticipating surface uplift deformations in tunnel construction endeavors using ground freezing techniques, delivering valuable insights and a promising predictive tool for both engineering professionals and academic researchers.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141978590","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Probabilistic time estimation of tunnels constructed with multiple headings 多洞口隧道施工的概率时间估算
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-12 DOI: 10.1016/j.tust.2024.106013

Transport infrastructure projects frequently encounter challenges such as schedule delays and cost overruns, leading to substantial misallocation of public or private resources. These issues are often exacerbated by uncertainties in time and cost estimation outcomes. To address this, various models have been developed in recent years to enable probabilistic estimation for tunneling projects, considering uncertainties. However, the impact of uncertainties on the critical path and its implications on time and cost estimations have not been discussed explicitly and in detail for network underground structures encompassing multiple construction paths. In this study, we update the KTH time and cost estimation model using the Markov Chain Monte Carlo (MCMC) method. This updated model enables simultaneous round-by-round construction simulation across all paths in network underground structures. Consequently, it accommodates uncertainty in the critical path and its influence on time estimation outcomes. Additionally, the updated model introduces an innovative technique to model geological uncertainties along tunnel routes, thereby contributing to the field’s diversity. Practical application of the updated model is showcased using the Uri Hearace tunnel as an illustrative example. The paper also delves into the practical implications of the findings from a decision-maker’s standpoint, as well as discussing the model’s limitations.

交通基础设施项目经常遇到进度延误和成本超支等挑战,导致公共或私人资源的大量错配。时间和成本估算结果的不确定性往往会加剧这些问题。为解决这一问题,近年来开发了各种模型,以便在考虑不确定性的情况下对隧道工程进行概率估算。然而,对于包含多条施工路径的地下网络结构,不确定性对关键路径的影响及其对时间和成本估算的影响尚未得到明确而详细的讨论。在本研究中,我们使用马尔可夫链蒙特卡罗(MCMC)方法更新了 KTH 时间和成本估算模型。更新后的模型可同时对网络地下结构的所有路径进行逐轮施工模拟。因此,它考虑到了关键路径的不确定性及其对时间估算结果的影响。此外,更新后的模型还引入了一项创新技术,对隧道沿线的地质不确定性进行建模,从而促进了该领域的多样性。以乌里赫拉斯隧道为例,展示了更新模型的实际应用。论文还从决策者的角度深入探讨了研究结果的实际意义,并讨论了模型的局限性。
{"title":"Probabilistic time estimation of tunnels constructed with multiple headings","authors":"","doi":"10.1016/j.tust.2024.106013","DOIUrl":"10.1016/j.tust.2024.106013","url":null,"abstract":"<div><p>Transport infrastructure projects frequently encounter challenges such as schedule delays and cost overruns, leading to substantial misallocation of public or private resources. These issues are often exacerbated by uncertainties in time and cost estimation outcomes. To address this, various models have been developed in recent years to enable probabilistic estimation for tunneling projects, considering uncertainties. However, the impact of uncertainties on the critical path and its implications on time and cost estimations have not been discussed explicitly and in detail for network underground structures encompassing multiple construction paths. In this study, we update the KTH time and cost estimation model using the Markov Chain Monte Carlo (MCMC) method. This updated model enables simultaneous round-by-round construction simulation across all paths in network underground structures. Consequently, it accommodates uncertainty in the critical path and its influence on time estimation outcomes. Additionally, the updated model introduces an innovative technique to model geological uncertainties along tunnel routes, thereby contributing to the field’s diversity. Practical application of the updated model is showcased using the Uri Hearace tunnel as an illustrative example. The paper also delves into the practical implications of the findings from a decision-maker’s standpoint, as well as discussing the model’s limitations.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://www.sciencedirect.com/science/article/pii/S0886779824004310/pdfft?md5=516bb625ed44a46e1af743bf5062e214&pid=1-s2.0-S0886779824004310-main.pdf","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141964176","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"OA","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Centrifuge model tests and numerical simulation on ground-borne vibration propagating and vibration reduction scheme for tunnel inner structure 隧道内部结构的地面振动传播和减振方案的离心机模型试验和数值模拟
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-12 DOI: 10.1016/j.tust.2024.105996

Traffic vibration of roads, trains and metro system is increasingly influencing normal life and facility operation in large cities, as population grows and infrastructures get more congested. Aiming to assess the impact of ground-borne vibrations nearby elevated traffic system on a tunnel housing sensitive scientific in struments, this paper employed centrifugal model tests and numerical simulations to analyze the attenuation trending of vertical vibration propagating from the pile foundation supporting the traffic system and vibratory response of the tunnel model, as well as the passive damping effects of a rubber isolation layer in tunnel structure. Model tests were carried out both in saturated sandy soil layer and dry one, under individual pile vibrations. Results from centrifugal tests indicated that vertical vibration energy decreases with increasing propagation distance, with more rapid attenuation in saturated sands compared to dry sands. Comparison within frequency domain of the vibration shows that high-frequency components attenuated faster than low-frequency ones in the ground, and in the 10–50 Hz range, vibrational energy at the tunnel invert was significantly lower than at the crown, with saturated sands exhibiting lower vibrations than dry sands. However, in the 50–100 Hz range, vibrations at the tunnel invert amplified, with saturated sands exhibiting higher vibrations than dry sands. A 5 mm thick rubber isolation layer was shown to reduce vibrations at the center of the tunnel base between 10–60 Hz in saturated sandy soils. Numerical simulations supported the experimental results and further investigated the impact of soil damping ratio and dynamic shear modulus on vibration propagation. An increased damping ratio significantly reduced high-frequency vibrations and vertical acceleration FRF values. A higher dynamic shear modulus led to decreased soil acceleration response under vibration, though the effect diminished with higher excitation frequencies. This integrated experimental and numerical study provides valuable insights for optimizing vibration reduction strategies in tunnel construction, with potential applications to similar engineering projects.

随着人口的增长和基础设施的日益拥挤,道路、火车和地铁系统的交通振动对大城市正常生活和设施运行的影响越来越大。为了评估高架交通系统附近的地面振动对容纳敏感科学仪器的隧道的影响,本文采用离心模型试验和数值模拟,分析了从支撑交通系统的桩基传播的垂直振动的衰减趋势和隧道模型的振动响应,以及隧道结构中橡胶隔离层的被动阻尼效应。模型试验在饱和砂质土层和干燥土层中进行,在单个桩基振动下进行。离心试验结果表明,垂直振动能量随着传播距离的增加而减小,与干燥砂土相比,饱和砂土的垂直振动能量衰减更快。振动频域内的比较表明,地层中高频成分的衰减速度快于低频成分,在 10-50 Hz 范围内,隧道内侧的振动能量明显低于隧道顶部,饱和砂的振动低于干砂。然而,在 50-100 Hz 范围内,隧道进口处的振动放大,饱和砂的振动高于干砂。在饱和砂土中,5 毫米厚的橡胶隔离层可减少隧道底部中心 10-60 赫兹的振动。数值模拟支持了实验结果,并进一步研究了土壤阻尼比和动态剪切模量对振动传播的影响。阻尼比的增加大大降低了高频振动和垂直加速度 FRF 值。动态剪切模量越大,振动下的土壤加速度响应就越小,但随着激励频率的提高,这种影响也会减弱。这项综合实验和数值研究为优化隧道施工中的减震策略提供了宝贵的见解,并有可能应用于类似的工程项目。
{"title":"Centrifuge model tests and numerical simulation on ground-borne vibration propagating and vibration reduction scheme for tunnel inner structure","authors":"","doi":"10.1016/j.tust.2024.105996","DOIUrl":"10.1016/j.tust.2024.105996","url":null,"abstract":"<div><p>Traffic vibration of roads, trains and metro system is increasingly influencing normal life and facility operation in large cities, as population grows and infrastructures get more congested. Aiming to assess the impact of ground-borne vibrations nearby elevated traffic system on a tunnel housing sensitive scientific in struments, this paper employed centrifugal model tests and numerical simulations to analyze the attenuation trending of vertical vibration propagating from the pile foundation supporting the traffic system and vibratory response of the tunnel model, as well as the passive damping effects of a rubber isolation layer in tunnel structure. Model tests were carried out both in saturated sandy soil layer and dry one, under individual pile vibrations. Results from centrifugal tests indicated that vertical vibration energy decreases with increasing propagation distance, with more rapid attenuation in saturated sands compared to dry sands. Comparison within frequency domain of the vibration shows that high-frequency components attenuated faster than low-frequency ones in the ground, and in the 10–50 Hz range, vibrational energy at the tunnel invert was significantly lower than at the crown, with saturated sands exhibiting lower vibrations than dry sands. However, in the 50–100 Hz range, vibrations at the tunnel invert amplified, with saturated sands exhibiting higher vibrations than dry sands. A 5 mm thick rubber isolation layer was shown to reduce vibrations at the center of the tunnel base between 10–60 Hz in saturated sandy soils. Numerical simulations supported the experimental results and further investigated the impact of soil damping ratio and dynamic shear modulus on vibration propagation. An increased damping ratio significantly reduced high-frequency vibrations and vertical acceleration FRF values. A higher dynamic shear modulus led to decreased soil acceleration response under vibration, though the effect diminished with higher excitation frequencies. This integrated experimental and numerical study provides valuable insights for optimizing vibration reduction strategies in tunnel construction, with potential applications to similar engineering projects.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141978153","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
A strain applied method for FEM-2D modelling of TBM tunnels in coarse-grained soils with comparative analysis of case histories 粗粒土中隧道掘进机 FEM-2D 建模的应变应用方法及案例对比分析
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-10 DOI: 10.1016/j.tust.2024.106001

The paper focuses on the prediction of tunnelling-induced settlements in greenfield conditions. The main components of ground deformation are investigated with approaches based on both empirical and numerical solutions. In particular, the study analyses five well documented case histories of shield-driven tunnels bored in coarse-grained soil deposits and compares the predicted and measured settlements.

A specific approach for FEM-2D modelling of soil-shield interaction (called “Strain Applied Method”) has been implemented and its potential for the prediction of the settlement trough has been discussed. The analyses were performed for the green field conditions with the Finite Element software Plaxis. The mechanical behaviour of the soil has been modelled by both the usual linear elasto-plastic model (Mohr-Coulomb, MC) and the advanced Hardening Soil model with small strain stiffness (HSs). The comparison of results shows that the settlements calculated by the HSs model are generally in better agreement with the field measurements. Then, the analysis has been focused on the volume loss obtained for the five case histories, finding some significant correlations between volume loss and the specific parameters required by the proposed FEM-2D model. The predictive capabilities of the 2D model, with parameters estimated by specific correlations, were demonstrated by applying the proposed method for two new case histories, not included in the initial set utilized to find the correlations.

本文的重点是预测绿地条件下隧道引起的沉降。通过基于经验和数值解法的方法,对地面变形的主要组成部分进行了研究。特别是,该研究分析了在粗粒土沉积层中钻孔的五个有据可查的盾构隧道案例,并比较了预测沉降和实测沉降。
{"title":"A strain applied method for FEM-2D modelling of TBM tunnels in coarse-grained soils with comparative analysis of case histories","authors":"","doi":"10.1016/j.tust.2024.106001","DOIUrl":"10.1016/j.tust.2024.106001","url":null,"abstract":"<div><p>The paper focuses on the prediction of tunnelling-induced settlements in greenfield conditions. The main components of ground deformation are investigated with approaches based on both empirical and numerical solutions. In particular, the study analyses five well documented case histories of shield-driven tunnels bored in coarse-grained soil deposits and compares the predicted and measured settlements.</p><p>A specific approach for FEM-2D modelling of soil-shield interaction (called “<em>Strain Applied Method</em>”) has been implemented and its potential for the prediction of the settlement trough has been discussed. The analyses were performed for the <em>green field</em> conditions with the Finite Element software Plaxis. The mechanical behaviour of the soil has been modelled by both the usual linear elasto-plastic model (<em>Mohr-Coulomb, MC</em>) and the advanced <em>Hardening Soil</em> model with small strain stiffness (<em>HSs</em>). The comparison of results shows that the settlements calculated by the <em>HSs</em> model are generally in better agreement with the field measurements. Then, the analysis has been focused on the volume loss obtained for the five case histories, finding some significant correlations between volume loss and the specific parameters required by the proposed FEM-2D model. The predictive capabilities of the 2D model, with parameters estimated by specific correlations, were demonstrated by applying the proposed method for two new case histories, not included in the initial set utilized to find the correlations.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-10","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://www.sciencedirect.com/science/article/pii/S088677982400419X/pdfft?md5=84c99bba2b50c4d91851b157b1d0bd66&pid=1-s2.0-S088677982400419X-main.pdf","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141915213","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"OA","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Machine learning-based framework for predicting the fire-induced spalling in concrete tunnel linings 基于机器学习的混凝土隧道衬砌火灾诱发剥落预测框架
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-10 DOI: 10.1016/j.tust.2024.106000

Fire-induced spalling in concrete is a serious issue in tunnel lining design because it can reduce the load-bearing capacity of the tunnel and the cross-section area of the tunnel lining. The adverse consequences of concrete spalling can cause serious damage to the tunnel lining or even failure occasionally. Hence, concrete spalling at elevated temperatures particularly explosive spalling must be properly assessed by considering it as a crucial factor for fire resistance in concrete tunnel lining designs. In the last several years, there has been a surge of scientific studies aimed at explaining why concrete spalls when exposed to fire. Despite these attempts, a current evaluation method that can reliably forecast the average depth of spalling of concrete tunnel lining has not yet been developed, and a comprehensive analysis of this phenomenon has not been completed. Many areas of structural engineering have benefited from the use of machine learning, but no one has yet attempted to use it to predict the spalling depth of concrete tunnel lining. Most sophisticated techniques in machine learning such as ensemble learning approaches have not been adopted. This study also addressed this issue by developing a database of 415 spalling test results under 16 input variables to provide predictions about the spalling depth of concrete tunnel lining using ensemble learning approaches such as Random Forest (RF), Categorical gradient boosting algorithm (Catboost), Light gradient boosting algorithm (LightGBM) and Extreme gradient boosting algorithm (XGBoost). This research developed a novel machine learning-based framework to predict the spalling behaviour in tunnel lining exposed to fire. Based on the conclusions, XGBoost demonstrated the highest performance in predicting spalling depth in concrete tunnel linings.

火灾引起的混凝土剥落是隧道衬砌设计中的一个严重问题,因为它会降低隧道的承载能力和隧道衬砌的横截面积。混凝土剥落的不良后果会对隧道衬砌造成严重损坏,甚至偶尔会导致隧道衬砌失效。因此,必须将高温下的混凝土剥落,尤其是爆炸性剥落,作为隧道混凝土衬砌设计中防火的一个关键因素进行适当评估。在过去的几年里,旨在解释混凝土遇火剥落原因的科学研究激增。尽管进行了这些尝试,但目前仍未开发出一种能够可靠预测混凝土隧道衬砌平均剥落深度的评估方法,对这一现象的全面分析也尚未完成。结构工程的许多领域都受益于机器学习的应用,但还没有人尝试用它来预测混凝土隧道衬砌的剥落深度。机器学习中最复杂的技术(如集合学习方法)尚未被采用。本研究也针对这一问题,开发了一个包含 16 个输入变量的 415 项剥落测试结果的数据库,利用随机森林 (RF)、分类梯度提升算法 (Catboost)、轻梯度提升算法 (LightGBM) 和极端梯度提升算法 (XGBoost) 等集合学习方法对混凝土隧道衬砌的剥落深度进行预测。这项研究开发了一种基于机器学习的新型框架,用于预测隧道衬砌在火灾中的剥落行为。根据研究结论,XGBoost 在预测混凝土隧道衬砌的剥落深度方面表现出最高的性能。
{"title":"Machine learning-based framework for predicting the fire-induced spalling in concrete tunnel linings","authors":"","doi":"10.1016/j.tust.2024.106000","DOIUrl":"10.1016/j.tust.2024.106000","url":null,"abstract":"<div><p>Fire-induced spalling in concrete is a serious issue in tunnel lining design because it can reduce the load-bearing capacity of the tunnel and the cross-section area of the tunnel lining. The adverse consequences of concrete spalling can cause serious damage to the tunnel lining or even failure occasionally. Hence, concrete spalling at elevated temperatures particularly explosive spalling must be properly assessed by considering it as a crucial factor for fire resistance in concrete tunnel lining designs. In the last several years, there has been a surge of scientific studies aimed at explaining why concrete spalls when exposed to fire. Despite these attempts, a current evaluation method that can reliably forecast the average depth of spalling of concrete tunnel lining has not yet been developed, and a comprehensive analysis of this phenomenon has not been completed. Many areas of structural engineering have benefited from the use of machine learning, but no one has yet attempted to use it to predict the spalling depth of concrete tunnel lining. Most sophisticated techniques in machine learning such as ensemble learning approaches have not been adopted. This study also addressed this issue by developing a database of 415 spalling test results under 16 input variables to provide predictions about the spalling depth of concrete tunnel lining using ensemble learning approaches such as Random Forest (RF), Categorical gradient boosting algorithm (Catboost), Light gradient boosting algorithm (LightGBM) and Extreme gradient boosting algorithm (XGBoost). This research developed a novel machine learning-based framework to predict the spalling behaviour in tunnel lining exposed to fire. Based on the conclusions, XGBoost demonstrated the highest performance in predicting spalling depth in concrete tunnel linings.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-10","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://www.sciencedirect.com/science/article/pii/S0886779824004188/pdfft?md5=222cb9e3968fcfcbcd644d030b5f62ac&pid=1-s2.0-S0886779824004188-main.pdf","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141915040","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"OA","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Analysis of blasting vibration responses in the ramp section of the Beishan Underground Research Laboratory 北山地下实验室斜坡段爆破振动响应分析
IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Pub Date : 2024-08-09 DOI: 10.1016/j.tust.2024.105999

The Beishan Underground Research Laboratory serves as a crucial experimental platform for the geological disposal of high-level radioactive waste in China. To investigate the impact of blasting vibrations generated by the drill and blast method on the ramp entrance section of the laboratory, the blasting vibration signals of the ramp entrance section were analysed, and the distribution characteristics of the vibration velocity and dominant frequency were obtained. By using the wavelet packet transform, the velocity and energy features within the frequency band of the blasting vibration signals were successfully extracted. The calculation formulas for explosive vibration velocity and dominant frequency were derived and verified utilizing dimensional analysis, in accordance with the Equivalent Elastic Boundary theory. The results show that the vibration velocity is highest at the floor of the ramp, lowest at the roof, and intermediate at the sidewall. Variations in the direction of the vibration velocity were also observed at these locations. The blast vibration frequencies at each location are concentrated in the range of 0∼300 Hz, within which the blast vibration velocity and energy tend to decrease from the floor to the roof. However, an increasing trend is observed in some frequency bands within 100 Hz, which requires attention. The derived formulas for the blasting vibration velocity and dominant frequency, except for the calculation deviation of the dominant frequency at the sidewall, have high accuracy, with a R2>0.8. The calculation error of the dominant frequency at the sidewall may be due to the differences in rock mass vibration stiffness, which requires further verification. These research findings provide important guidance for the field construction of the Beishan Underground Research Laboratory and offer valuable references for similar projects in the future.

北山地下研究实验室是中国高放射性废物地质处置的重要实验平台。为研究钻爆法产生的爆破振动对实验室斜井入口段的影响,对斜井入口段的爆破振动信号进行了分析,获得了振动速度和主频的分布特征。利用小波包变换,成功提取了爆破振动信号频带内的速度和能量特征。根据等效弹性边界理论,利用尺寸分析法推导并验证了爆破振动速度和主频的计算公式。结果表明,坡道地面的振动速度最高,坡顶的振动速度最低,侧壁的振动速度居中。在这些位置还观察到振动速度方向的变化。每个位置的爆破振动频率集中在 0∼300 Hz 范围内,在此范围内,爆破振动速度和能量从地面到屋顶呈下降趋势。然而,在 100 Hz 范围内的某些频段中,观察到有增加的趋势,需要引起注意。推导出的爆破振动速度和主频计算公式,除侧壁主频计算偏差外,精度都很高,R>0.8。侧壁主频的计算误差可能是由于岩体振动刚度的差异造成的,需要进一步验证。这些研究成果为北山地下研究室的野外施工提供了重要指导,也为今后类似工程提供了有价值的参考。
{"title":"Analysis of blasting vibration responses in the ramp section of the Beishan Underground Research Laboratory","authors":"","doi":"10.1016/j.tust.2024.105999","DOIUrl":"10.1016/j.tust.2024.105999","url":null,"abstract":"<div><p>The Beishan Underground Research Laboratory serves as a crucial experimental platform for the geological disposal of high-level radioactive waste in China. To investigate the impact of blasting vibrations generated by the drill and blast method on the ramp entrance section of the laboratory, the blasting vibration signals of the ramp entrance section were analysed, and the distribution characteristics of the vibration velocity and dominant frequency were obtained. By using the wavelet packet transform, the velocity and energy features within the frequency band of the blasting vibration signals were successfully extracted. The calculation formulas for explosive vibration velocity and dominant frequency were derived and verified utilizing dimensional analysis, in accordance with the Equivalent Elastic Boundary theory. The results show that the vibration velocity is highest at the floor of the ramp, lowest at the roof, and intermediate at the sidewall. Variations in the direction of the vibration velocity were also observed at these locations. The blast vibration frequencies at each location are concentrated in the range of 0∼300 Hz, within which the blast vibration velocity and energy tend to decrease from the floor to the roof. However, an increasing trend is observed in some frequency bands within 100 Hz, which requires attention. The derived formulas for the blasting vibration velocity and dominant frequency, except for the calculation deviation of the dominant frequency at the sidewall, have high accuracy, with a R<sup>2</sup>&gt;0.8. The calculation error of the dominant frequency at the sidewall may be due to the differences in rock mass vibration stiffness, which requires further verification. These research findings provide important guidance for the field construction of the Beishan Underground Research Laboratory and offer valuable references for similar projects in the future.</p></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":null,"pages":null},"PeriodicalIF":6.7,"publicationDate":"2024-08-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"141915126","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
期刊
Tunnelling and Underground Space Technology
全部 Acc. Chem. Res. ACS Applied Bio Materials ACS Appl. Electron. Mater. ACS Appl. Energy Mater. ACS Appl. Mater. Interfaces ACS Appl. Nano Mater. ACS Appl. Polym. Mater. ACS BIOMATER-SCI ENG ACS Catal. ACS Cent. Sci. ACS Chem. Biol. ACS Chemical Health & Safety ACS Chem. Neurosci. ACS Comb. Sci. ACS Earth Space Chem. ACS Energy Lett. ACS Infect. Dis. ACS Macro Lett. ACS Mater. Lett. ACS Med. Chem. Lett. ACS Nano ACS Omega ACS Photonics ACS Sens. ACS Sustainable Chem. Eng. ACS Synth. Biol. Anal. Chem. BIOCHEMISTRY-US Bioconjugate Chem. BIOMACROMOLECULES Chem. Res. Toxicol. Chem. Rev. Chem. Mater. CRYST GROWTH DES ENERG FUEL Environ. Sci. Technol. Environ. Sci. Technol. Lett. Eur. J. Inorg. Chem. IND ENG CHEM RES Inorg. Chem. J. Agric. Food. Chem. J. Chem. Eng. Data J. Chem. Educ. J. Chem. Inf. Model. J. Chem. Theory Comput. J. Med. Chem. J. Nat. Prod. J PROTEOME RES J. Am. Chem. Soc. LANGMUIR MACROMOLECULES Mol. Pharmaceutics Nano Lett. Org. Lett. ORG PROCESS RES DEV ORGANOMETALLICS J. Org. Chem. J. Phys. Chem. J. Phys. Chem. A J. Phys. Chem. B J. Phys. Chem. C J. Phys. Chem. Lett. Analyst Anal. Methods Biomater. Sci. Catal. Sci. Technol. Chem. Commun. Chem. Soc. Rev. CHEM EDUC RES PRACT CRYSTENGCOMM Dalton Trans. Energy Environ. Sci. ENVIRON SCI-NANO ENVIRON SCI-PROC IMP ENVIRON SCI-WAT RES Faraday Discuss. Food Funct. Green Chem. Inorg. Chem. Front. Integr. Biol. J. Anal. At. Spectrom. J. Mater. Chem. A J. Mater. Chem. B J. Mater. Chem. C Lab Chip Mater. Chem. Front. Mater. Horiz. MEDCHEMCOMM Metallomics Mol. Biosyst. Mol. Syst. Des. Eng. Nanoscale Nanoscale Horiz. Nat. Prod. Rep. New J. Chem. Org. Biomol. Chem. Org. Chem. Front. PHOTOCH PHOTOBIO SCI PCCP Polym. Chem.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1