首页 > 最新文献

2020 AEIT International Annual Conference (AEIT)最新文献

英文 中文
Islanding Operation During the 2019 Alto Adige Snowstorm Emergency 2019年上阿迪杰暴风雪紧急情况下的孤岛行动
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241143
E. Carlini, Albert C Pesce, Mirko Piazza, Alessio Salmaso, A. Berizzi, D. Falabretti, Corrado Mattevi
The paper describes the events that led, in November 2019, to a local blackout in Trentino-Alto Adige (Northern Italy). The events were caused by a heavy snowstorm that resulted in about 7000 faults on the electric system for short-circuits, trees falling on electrical lines etc. In consequence, a 132 kV portion of the grid, and the underlying MV/LV distribution grid, remained isolated from the national transmission grid a part of the 132 kV power system. Overall, approximately 25 thousand customers were involved in a local blackout for more than 24 hours. However, the blackout has been mitigated by the attempts of operating the local system as an electric island, exploiting the black start capability of hydro power plants with enough power capacity to supply the island resulting from the disconnection. The paper describes the main features of the island operation, the main problems encountered until the final restoration, the lessons learned and provides a set of suggestions in order to mitigate the effects of such heavy weather phenomena in the future.
该论文描述了导致2019年11月特伦蒂诺-上阿迪杰(意大利北部)当地停电的事件。这些事件是由一场暴风雪引起的,这场暴风雪导致了大约7000个电力系统短路、树木倒在电线上等故障。因此,作为132千伏电力系统的一部分,电网的132千伏部分以及底层的中压/低压配电网仍然与国家输电网隔离。总的来说,大约有2.5万名客户受到了超过24小时的停电影响。然而,通过尝试将当地系统作为一个电岛来运行,利用水力发电厂的黑启动能力,有足够的电力容量来供应停电造成的岛屿,停电已经减轻了。本文介绍了海岛运作的主要特点、在最后修复前遇到的主要问题、所吸取的教训,并提供了一套建议,以便在未来减轻这种恶劣天气现象的影响。
{"title":"Islanding Operation During the 2019 Alto Adige Snowstorm Emergency","authors":"E. Carlini, Albert C Pesce, Mirko Piazza, Alessio Salmaso, A. Berizzi, D. Falabretti, Corrado Mattevi","doi":"10.23919/AEIT50178.2020.9241143","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241143","url":null,"abstract":"The paper describes the events that led, in November 2019, to a local blackout in Trentino-Alto Adige (Northern Italy). The events were caused by a heavy snowstorm that resulted in about 7000 faults on the electric system for short-circuits, trees falling on electrical lines etc. In consequence, a 132 kV portion of the grid, and the underlying MV/LV distribution grid, remained isolated from the national transmission grid a part of the 132 kV power system. Overall, approximately 25 thousand customers were involved in a local blackout for more than 24 hours. However, the blackout has been mitigated by the attempts of operating the local system as an electric island, exploiting the black start capability of hydro power plants with enough power capacity to supply the island resulting from the disconnection. The paper describes the main features of the island operation, the main problems encountered until the final restoration, the lessons learned and provides a set of suggestions in order to mitigate the effects of such heavy weather phenomena in the future.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"56 1","pages":"1-6"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"77198522","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Analysis of the electrolytic corrosion in the railway line Albate-Chiasso albatte - chiasso铁路线电解腐蚀分析
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241126
R. Lamedica, A. Ruvio, G. G. Buffarini, N. Carones, C. Cianfarani
The paper focuses on evaluation of stray current distribution and rail potential for “Albate-Chiasso” DC railway line, that connects Italy and Switzerland. A model has been developed to calculate stray current and rail potential taking into account the European Standard, in order to avoid electrolytic corrosion and electrical safety problems. A real case study has been presented and simulated using Simulink software. A measurement campaign has been used to validate the model proposed.
本文主要对连接意大利和瑞士的“阿尔贝特-基亚索”直流铁路线的杂散电流分布和轨道电位进行了评价。为了避免电解腐蚀和电气安全问题,建立了一个考虑欧洲标准的模型来计算杂散电流和轨道电位。给出了一个实际案例,并利用Simulink软件进行了仿真。一个测量活动已被用来验证所提出的模型。
{"title":"Analysis of the electrolytic corrosion in the railway line Albate-Chiasso","authors":"R. Lamedica, A. Ruvio, G. G. Buffarini, N. Carones, C. Cianfarani","doi":"10.23919/AEIT50178.2020.9241126","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241126","url":null,"abstract":"The paper focuses on evaluation of stray current distribution and rail potential for “Albate-Chiasso” DC railway line, that connects Italy and Switzerland. A model has been developed to calculate stray current and rail potential taking into account the European Standard, in order to avoid electrolytic corrosion and electrical safety problems. A real case study has been presented and simulated using Simulink software. A measurement campaign has been used to validate the model proposed.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"46 1","pages":"1-5"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"79230700","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
FEM based Assessment of Winding Inter-Tum Fault Indicators in Line Connected Induction Motors 基于有限元法的线连异步电动机绕组匝间故障指标评估
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241186
M. Andriollo, Rahul R. Kumar, A. Tortella, Riccardo Zavagnin
The paper aims at the definition of proper indicators for the effective detection of stator inter-turn faults in line connected induction motors. The procedure uses a finite element model related to a standard medium rated motor, tuned taking into account both magnetic saturation and the actual winding scheme. After the experimental check with reference to different load conditions, multiple fault indicators are evaluated by elaborating the motor current components. The same model predicts the effects of asymmetric voltage supply on the current harmonics to prevent misleading fault detection. Moreover, a relation between fault severity and the experimental setup to reproduce similar current asymmetries as in the actual fault condition has been examined. On this basis, some measurements have been carried out, enabling to have a broad check on the fault indicator effectiveness.
本文的目的是确定合适的指标,以便有效地检测线路连接异步电动机定子匝间故障。该程序使用与标准中等额定值电机相关的有限元模型,并考虑磁饱和和实际绕组方案进行调整。在参照不同负载条件进行实验校核后,通过细化电机电流组成,评估多个故障指标。该模型还预测了不对称供电对电流谐波的影响,以防止误检。此外,还研究了故障严重程度与实验设置之间的关系,以再现与实际故障条件相似的电流不对称。在此基础上,进行了一些测量,从而能够对故障指示器的有效性进行广泛的检查。
{"title":"FEM based Assessment of Winding Inter-Tum Fault Indicators in Line Connected Induction Motors","authors":"M. Andriollo, Rahul R. Kumar, A. Tortella, Riccardo Zavagnin","doi":"10.23919/AEIT50178.2020.9241186","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241186","url":null,"abstract":"The paper aims at the definition of proper indicators for the effective detection of stator inter-turn faults in line connected induction motors. The procedure uses a finite element model related to a standard medium rated motor, tuned taking into account both magnetic saturation and the actual winding scheme. After the experimental check with reference to different load conditions, multiple fault indicators are evaluated by elaborating the motor current components. The same model predicts the effects of asymmetric voltage supply on the current harmonics to prevent misleading fault detection. Moreover, a relation between fault severity and the experimental setup to reproduce similar current asymmetries as in the actual fault condition has been examined. On this basis, some measurements have been carried out, enabling to have a broad check on the fault indicator effectiveness.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"106 1","pages":"1-6"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"81216043","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
Improving the minimum distance of QC-LDPC codes by removing cycles 通过去除循环来提高QC-LDPC码的最小距离
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241207
Massimo Battaglioni, M. Baldi, G. Cancellieri
We focus on regular and irregular quasi-cyclic low-density parity-check codes and analyze their codewords. We show that any codeword can be decomposed into component codewords with smaller weight belonging to some component codes. Component codewords can be associated to cycles in the Tanner graph of the code. We transfer these theoretical results into the code design, finding that the removal of some specific classes of cycles yields benefits in terms of minimum distance and error rate performance.
重点研究了正则和不规则准循环低密度奇偶校验码,并分析了它们的码字。我们证明了任何码字都可以被分解成分量码字,这些分量码字的权重较小,属于某些分量码。组件码字可以与代码的坦纳图中的循环相关联。我们将这些理论结果转移到代码设计中,发现去除某些特定类别的循环在最小距离和错误率性能方面产生了好处。
{"title":"Improving the minimum distance of QC-LDPC codes by removing cycles","authors":"Massimo Battaglioni, M. Baldi, G. Cancellieri","doi":"10.23919/AEIT50178.2020.9241207","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241207","url":null,"abstract":"We focus on regular and irregular quasi-cyclic low-density parity-check codes and analyze their codewords. We show that any codeword can be decomposed into component codewords with smaller weight belonging to some component codes. Component codewords can be associated to cycles in the Tanner graph of the code. We transfer these theoretical results into the code design, finding that the removal of some specific classes of cycles yields benefits in terms of minimum distance and error rate performance.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"53 1","pages":"1-5"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"83174429","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
Risk assessment and control in protection against indirect contacts for Medium Voltage earth faults in open-cast mines and quarries 露天矿和采石场中压接地故障间接接触保护的风险评估与控制
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241152
Emilio Giovannini
Open-cast mines and quarries often use high power electrical machinery to extract materials from the site they are located. Due to the power of machinery, these activities require a MV electricity supply. They are very often located in sites where the soil has high resistivity, and it couldn’t be easy to guarantee the protection against indirect contacts according to EN 50522:2010-11 provisions. This is particularly true along the excavation front. The electrical properties of the soil on which the machinery are installed may change quickly and so changes the distribution of the potentials during MV earth faults. Risk control based on touch voltages measurements could not be a reliable technique; better to search structural solutions to guarantee the worker’s protection. The requirements of the EN 50522:2010-11 standard are evaluated not only under the electrical point of view, but keeping in mind the particular context. A metal mesh laid along the operating locations and connected to the metal chassis of the machinery is a simple and reliable solution. Measures executed in Italian quarries confirm this.
露天矿和采石场经常使用大功率电机从它们所处的地点提取材料。由于机械的动力,这些活动需要一个中伏的电力供应。它们通常位于土壤电阻率高的地方,根据EN 50522:2010-11规定,不容易保证对间接接触的保护。沿着挖掘前沿,这一点尤其正确。机械所处土壤的电学性质变化很快,从而改变了中压接地故障时的电位分布。基于触摸电压测量的风险控制不是可靠的技术;更好地寻找结构性解决方案,以保证工人的保护。EN 50522:2010-11标准的要求不仅从电气角度进行评估,而且要牢记特定的环境。沿着操作位置铺设金属网并连接到机械的金属底盘是一种简单可靠的解决方案。在意大利采石场执行的措施证实了这一点。
{"title":"Risk assessment and control in protection against indirect contacts for Medium Voltage earth faults in open-cast mines and quarries","authors":"Emilio Giovannini","doi":"10.23919/AEIT50178.2020.9241152","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241152","url":null,"abstract":"Open-cast mines and quarries often use high power electrical machinery to extract materials from the site they are located. Due to the power of machinery, these activities require a MV electricity supply. They are very often located in sites where the soil has high resistivity, and it couldn’t be easy to guarantee the protection against indirect contacts according to EN 50522:2010-11 provisions. This is particularly true along the excavation front. The electrical properties of the soil on which the machinery are installed may change quickly and so changes the distribution of the potentials during MV earth faults. Risk control based on touch voltages measurements could not be a reliable technique; better to search structural solutions to guarantee the worker’s protection. The requirements of the EN 50522:2010-11 standard are evaluated not only under the electrical point of view, but keeping in mind the particular context. A metal mesh laid along the operating locations and connected to the metal chassis of the machinery is a simple and reliable solution. Measures executed in Italian quarries confirm this.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"10 1","pages":"1-5"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"88734796","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Distributed Voltage Control of DC Microgrids 直流微电网的分布式电压控制
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241184
Baheej Alghamdi, Katharina Wieninger, C. Cañizares
This paper presents a distributed, droop-free voltage control of a dc microgrid in grid-connected and isolated mode. The proposed control technique, based on a distributed consensus approach, addresses reliability issues of centralized controllers that are prone to single point failure, while sharing the loads among Distributed Energy Resources (DERs) more effectively than conventional decentralized droop controllers. The distributed control scheme is implemented, demonstrated, and compared with conventional droop control using time-domain simulations for a model of an actual dc microgrid in Xiamen University, China, based on various realistic scenarios.
本文提出了一种并网隔离模式下直流微电网的分布式无下垂电压控制方法。所提出的控制技术基于分布式共识方法,解决了集中式控制器容易出现单点故障的可靠性问题,同时比传统的分散下垂控制器更有效地在分布式能源(DERs)之间共享负载。在厦门大学的实际直流微电网模型中,基于各种现实场景,采用时域仿真对分布式控制方案进行了实现、演示,并与传统的下垂控制进行了比较。
{"title":"Distributed Voltage Control of DC Microgrids","authors":"Baheej Alghamdi, Katharina Wieninger, C. Cañizares","doi":"10.23919/AEIT50178.2020.9241184","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241184","url":null,"abstract":"This paper presents a distributed, droop-free voltage control of a dc microgrid in grid-connected and isolated mode. The proposed control technique, based on a distributed consensus approach, addresses reliability issues of centralized controllers that are prone to single point failure, while sharing the loads among Distributed Energy Resources (DERs) more effectively than conventional decentralized droop controllers. The distributed control scheme is implemented, demonstrated, and compared with conventional droop control using time-domain simulations for a model of an actual dc microgrid in Xiamen University, China, based on various realistic scenarios.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"15 1","pages":"1-6"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"87316846","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
Reliability evaluation for meshed distribution networks based on minimal cut sets method 基于最小割集法的网状配电网可靠性评估
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241128
Alessandro Bosisio, A. Berizzi, A. Morotti, B. Greco, G. Iannarelli
The paper proposes a reliability evaluation for meshed distribution networks based on minimal cut sets method. Distribution networks with meshed layout but radially operated have been commonly used in urban environments since they give some advantages in terms of lines thermal limit and voltage drop. The evaluation procedure is divided into three steps: firstly, it determines the minimal cut sets from each source node to each load nodes of the DN; secondly, it calculates the failure rate and the outage time for each minimal cut sets identified; lastly, it calculates the system average interruption frequency index and the system average interruption duration index. A sensitivity analysis of two specific system layouts, which we refer to as 1-step ladder and 2-steps ladder, has been carried out varying the maximum power flow allowed during normal operation. The method shows that, to improve reliability, as more as the distribution network is loaded as more as it should be meshed.
提出了一种基于最小割集法的网状配电网可靠性评估方法。网状径向配电网络在线路热极限和电压降方面具有一定的优势,在城市环境中得到了广泛的应用。评估过程分为三步:首先确定DN的每个源节点到每个负载节点的最小割集;其次,计算识别出的每个最小割集的故障率和停机时间;最后,计算了系统平均中断频率指数和系统平均中断时长指数。对两种具体的系统布局进行了灵敏度分析,我们将其称为一阶阶梯和两阶阶梯,并对正常运行时允许的最大功率潮流进行了变化。该方法表明,为了提高可靠性,配电网的负荷越大,配电网的并网率越高。
{"title":"Reliability evaluation for meshed distribution networks based on minimal cut sets method","authors":"Alessandro Bosisio, A. Berizzi, A. Morotti, B. Greco, G. Iannarelli","doi":"10.23919/AEIT50178.2020.9241128","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241128","url":null,"abstract":"The paper proposes a reliability evaluation for meshed distribution networks based on minimal cut sets method. Distribution networks with meshed layout but radially operated have been commonly used in urban environments since they give some advantages in terms of lines thermal limit and voltage drop. The evaluation procedure is divided into three steps: firstly, it determines the minimal cut sets from each source node to each load nodes of the DN; secondly, it calculates the failure rate and the outage time for each minimal cut sets identified; lastly, it calculates the system average interruption frequency index and the system average interruption duration index. A sensitivity analysis of two specific system layouts, which we refer to as 1-step ladder and 2-steps ladder, has been carried out varying the maximum power flow allowed during normal operation. The method shows that, to improve reliability, as more as the distribution network is loaded as more as it should be meshed.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"7 1","pages":"1-6"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"88227388","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
An estimation of tropospheric agents influence on 5G terrestrial radio services in the THz band 对流层因子对THz波段5G地面无线电业务影响的估计
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241086
M. Celidonio, E. Fionda, C. Riva
Recent technological advances made possible the development of devices and integrated circuits operating at frequencies greater than 100 GHz and telco operators, in order to face with the growing demand for bandwidth from users, are increasingly turning their interest to the feasibility of use wireless links also at sub-millimeter frequencies (300 GHz–l THz). This spectral region, also named TeraHertz band, offers greater availability of contiguous bands and is under investigation by international standardization bodies such as ITU and CEPT. The present study intends to provide useful insights to define technical and operational characteristics for 5G applications aimed at land-based fixed services operating in bands up to 1 THz. In this study simulations was carried out to provide an estimation of attenuation levels due to the gaseous component, precipitating events present in the troposphere at the ground level. Furthermore, radio refractivity was also estimated. All results are referred to the Italian territory and for frequencies ranging from 40 to 840 GHz.
最近的技术进步使工作频率超过100千兆赫的设备和集成电路的发展成为可能,电信运营商为了面对用户对带宽日益增长的需求,正日益将他们的兴趣转向在亚毫米频率(300千兆赫- 1太赫兹)使用无线链路的可行性。这个频谱区域,也被称为太赫兹频段,提供了更多的连续频段,并正在由国际电联和CEPT等国际标准化机构进行研究。本研究旨在提供有用的见解,以定义5G应用的技术和操作特征,这些应用的目标是在高达1thz的频段上运行的陆基固定业务。在这项研究中,进行了模拟,以提供由于对流层地面上存在的气体成分和降水事件造成的衰减水平的估计。此外,还估计了射电折射率。所有结果都指向意大利领土,频率范围为40至840千兆赫。
{"title":"An estimation of tropospheric agents influence on 5G terrestrial radio services in the THz band","authors":"M. Celidonio, E. Fionda, C. Riva","doi":"10.23919/AEIT50178.2020.9241086","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241086","url":null,"abstract":"Recent technological advances made possible the development of devices and integrated circuits operating at frequencies greater than 100 GHz and telco operators, in order to face with the growing demand for bandwidth from users, are increasingly turning their interest to the feasibility of use wireless links also at sub-millimeter frequencies (300 GHz–l THz). This spectral region, also named TeraHertz band, offers greater availability of contiguous bands and is under investigation by international standardization bodies such as ITU and CEPT. The present study intends to provide useful insights to define technical and operational characteristics for 5G applications aimed at land-based fixed services operating in bands up to 1 THz. In this study simulations was carried out to provide an estimation of attenuation levels due to the gaseous component, precipitating events present in the troposphere at the ground level. Furthermore, radio refractivity was also estimated. All results are referred to the Italian territory and for frequencies ranging from 40 to 840 GHz.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"51 1","pages":"1-6"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"78291830","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Research Infrastructures integration to foster Smart Grid testing 研究基础设施整合,促进智能电网测试
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241149
L. Pellegrino, R. Lazzari, M. Verga, C. Sandroni
The energy transition is changing the electrical power system. The increasing number of distributed energy resources in the distribution system and the digitalisation of most of the sensors and actuators are bringing the electrical grid to became a Smart Grid. Component and system testing for Smart Grid topics can introduce many challenges. ERIGrid Project tried to Figure out some of the upcoming issues investigating the possibility to expand Smart Grids laboratories potentialities and capabilities by means of research institutes cooperation and Research Infrastructures integration. Different tools for laboratory integration have been developed in the project. Among them a new methodology, called Holistic Test Description, has been developed with the goal to help researchers to clearly identify the test scope and the best test procedure to be adopted. Moreover a new communication tool, called JaNDER, has been developed by Ricerca sul Sistema Energetico (RSE) which is also member of the consortium of ERIGrid Project. This tool allows real time data communication between Research Infrastructures in an easy and effective way enabling a virtual connection between laboratories. These tools have been successfully tested and proved in the Distributed Energy Resources Test Facility (DER-TF) of RSE both by RSE researchers and also external users demonstrating the possibility to largely extend Smart Grid laboratories experimental potentialities. This paper shows some of the developed tools and presents some tests performed in RSE DER-TF that demonstrate how laboratories integration can reduce test set-up timing, optimise laboratory usage and improve the quality of experimental testing activities.
能源转型正在改变电力系统。随着配电系统中分布式能源数量的不断增加,以及大多数传感器和执行器的数字化,电网正在成为智能电网。智能电网主题的组件和系统测试可能会带来许多挑战。ERIGrid项目试图找出一些即将出现的问题,通过研究机构合作和研究基础设施集成的方式来扩大智能电网实验室的潜力和能力的可能性。该项目开发了用于实验室集成的不同工具。其中一种新的方法,称为整体测试描述,已经开发出来,其目的是帮助研究人员清楚地确定测试范围和最好的测试程序被采用。此外,Ricerca sul Sistema Energetico (RSE)也开发了一种名为JaNDER的新型通信工具,RSE也是ERIGrid项目联盟的成员。该工具允许在研究基础设施之间以一种简单有效的方式进行实时数据通信,从而实现实验室之间的虚拟连接。这些工具已经在RSE的分布式能源测试设施(DER-TF)中由RSE研究人员和外部用户成功测试和验证,证明了在很大程度上扩展智能电网实验室实验潜力的可能性。本文展示了一些开发的工具,并展示了在RSE DER-TF中执行的一些测试,这些测试展示了实验室集成如何减少测试设置时间,优化实验室使用并提高实验测试活动的质量。
{"title":"Research Infrastructures integration to foster Smart Grid testing","authors":"L. Pellegrino, R. Lazzari, M. Verga, C. Sandroni","doi":"10.23919/AEIT50178.2020.9241149","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241149","url":null,"abstract":"The energy transition is changing the electrical power system. The increasing number of distributed energy resources in the distribution system and the digitalisation of most of the sensors and actuators are bringing the electrical grid to became a Smart Grid. Component and system testing for Smart Grid topics can introduce many challenges. ERIGrid Project tried to Figure out some of the upcoming issues investigating the possibility to expand Smart Grids laboratories potentialities and capabilities by means of research institutes cooperation and Research Infrastructures integration. Different tools for laboratory integration have been developed in the project. Among them a new methodology, called Holistic Test Description, has been developed with the goal to help researchers to clearly identify the test scope and the best test procedure to be adopted. Moreover a new communication tool, called JaNDER, has been developed by Ricerca sul Sistema Energetico (RSE) which is also member of the consortium of ERIGrid Project. This tool allows real time data communication between Research Infrastructures in an easy and effective way enabling a virtual connection between laboratories. These tools have been successfully tested and proved in the Distributed Energy Resources Test Facility (DER-TF) of RSE both by RSE researchers and also external users demonstrating the possibility to largely extend Smart Grid laboratories experimental potentialities. This paper shows some of the developed tools and presents some tests performed in RSE DER-TF that demonstrate how laboratories integration can reduce test set-up timing, optimise laboratory usage and improve the quality of experimental testing activities.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"34 1","pages":"1-5"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"87990650","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
Reactive Power and AC Voltage Support from Flexible LCC HVDC to Wind Energy Integrated Power System 从柔性LCC HVDC到风能综合电力系统的无功和交流电压支持
Pub Date : 2020-09-23 DOI: 10.23919/AEIT50178.2020.9241102
Ying Xue, Conghuan Yang, Xiao-Ping Zhang
Conventional LCC HVDC system is unable to provide dynamic reactive power and AC voltage support to power system during transient events. This can have adverse impacts on the renewable generation that is connected to the same power system such as wind farms. This paper aims to demonstrate that the Flexible LCC HVDC system can provide dynamic reactive power and AC voltage support to a wind integrated power system. The Flexible LCC HVDC system is able to quickly inject reactive power into the system, reducing the voltage drop and increasing the speed of voltage recovery. This will help the wind farms in riding through the fault. At the same time, due to the elimination of Commutation Failure (CF) in the Flexible LCC HVDC system, it is able to maintain a relatively stable active power transfer as well. Simulation comparisons between the conventional LCC HVDC and the Flexible LCC HVDC based on a wind integrated two area power system have been presented to validate the performance.
传统的LCC直流输电系统无法在暂态事件中为电力系统提供动态无功和交流电压支持。这可能会对连接到风力发电场等同一电力系统的可再生能源发电产生不利影响。本文旨在证明柔性LCC高压直流输电系统可以为风力发电系统提供动态无功和交流电压支持。柔性LCC高压直流系统能够快速向系统注入无功功率,减少电压降,提高电压恢复速度。这将有助于风力发电场穿越断层。同时,由于柔性LCC高压直流系统消除了换相故障(CF),也能够保持相对稳定的有功传输。通过对传统LCC高压直流输电系统和基于风集成两区电力系统的柔性LCC高压直流输电系统的仿真比较,验证了其性能。
{"title":"Reactive Power and AC Voltage Support from Flexible LCC HVDC to Wind Energy Integrated Power System","authors":"Ying Xue, Conghuan Yang, Xiao-Ping Zhang","doi":"10.23919/AEIT50178.2020.9241102","DOIUrl":"https://doi.org/10.23919/AEIT50178.2020.9241102","url":null,"abstract":"Conventional LCC HVDC system is unable to provide dynamic reactive power and AC voltage support to power system during transient events. This can have adverse impacts on the renewable generation that is connected to the same power system such as wind farms. This paper aims to demonstrate that the Flexible LCC HVDC system can provide dynamic reactive power and AC voltage support to a wind integrated power system. The Flexible LCC HVDC system is able to quickly inject reactive power into the system, reducing the voltage drop and increasing the speed of voltage recovery. This will help the wind farms in riding through the fault. At the same time, due to the elimination of Commutation Failure (CF) in the Flexible LCC HVDC system, it is able to maintain a relatively stable active power transfer as well. Simulation comparisons between the conventional LCC HVDC and the Flexible LCC HVDC based on a wind integrated two area power system have been presented to validate the performance.","PeriodicalId":6689,"journal":{"name":"2020 AEIT International Annual Conference (AEIT)","volume":"71 1","pages":"1-4"},"PeriodicalIF":0.0,"publicationDate":"2020-09-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"90464314","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 1
期刊
2020 AEIT International Annual Conference (AEIT)
全部 Acc. Chem. Res. ACS Applied Bio Materials ACS Appl. Electron. Mater. ACS Appl. Energy Mater. ACS Appl. Mater. Interfaces ACS Appl. Nano Mater. ACS Appl. Polym. Mater. ACS BIOMATER-SCI ENG ACS Catal. ACS Cent. Sci. ACS Chem. Biol. ACS Chemical Health & Safety ACS Chem. Neurosci. ACS Comb. Sci. ACS Earth Space Chem. ACS Energy Lett. ACS Infect. Dis. ACS Macro Lett. ACS Mater. Lett. ACS Med. Chem. Lett. ACS Nano ACS Omega ACS Photonics ACS Sens. ACS Sustainable Chem. Eng. ACS Synth. Biol. Anal. Chem. BIOCHEMISTRY-US Bioconjugate Chem. BIOMACROMOLECULES Chem. Res. Toxicol. Chem. Rev. Chem. Mater. CRYST GROWTH DES ENERG FUEL Environ. Sci. Technol. Environ. Sci. Technol. Lett. Eur. J. Inorg. Chem. IND ENG CHEM RES Inorg. Chem. J. Agric. Food. Chem. J. Chem. Eng. Data J. Chem. Educ. J. Chem. Inf. Model. J. Chem. Theory Comput. J. Med. Chem. J. Nat. Prod. J PROTEOME RES J. Am. Chem. Soc. LANGMUIR MACROMOLECULES Mol. Pharmaceutics Nano Lett. Org. Lett. ORG PROCESS RES DEV ORGANOMETALLICS J. Org. Chem. J. Phys. Chem. J. Phys. Chem. A J. Phys. Chem. B J. Phys. Chem. C J. Phys. Chem. Lett. Analyst Anal. Methods Biomater. Sci. Catal. Sci. Technol. Chem. Commun. Chem. Soc. Rev. CHEM EDUC RES PRACT CRYSTENGCOMM Dalton Trans. Energy Environ. Sci. ENVIRON SCI-NANO ENVIRON SCI-PROC IMP ENVIRON SCI-WAT RES Faraday Discuss. Food Funct. Green Chem. Inorg. Chem. Front. Integr. Biol. J. Anal. At. Spectrom. J. Mater. Chem. A J. Mater. Chem. B J. Mater. Chem. C Lab Chip Mater. Chem. Front. Mater. Horiz. MEDCHEMCOMM Metallomics Mol. Biosyst. Mol. Syst. Des. Eng. Nanoscale Nanoscale Horiz. Nat. Prod. Rep. New J. Chem. Org. Biomol. Chem. Org. Chem. Front. PHOTOCH PHOTOBIO SCI PCCP Polym. Chem.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1